IDEAS home Printed from https://ideas.repec.org/a/eee/ejores/v273y2019i2p585-595.html
   My bibliography  Save this article

Setting optimal planned leadtimes in configure-to-order assembly systems

Author

Listed:
  • Jansen, Sjors
  • Atan, Zümbül
  • Adan, Ivo
  • Kok, Ton de

Abstract

We study a configure-to-order assembly system consisting of multiple parallel subassembly stages and one final assembly stage. Each stage has a stochastic leadtime. The system is controlled by planned leadtimes at each stage. Planned leadtimes are used to plan start and finish times at all stages. The system incurs holding cost for each stage from the planned start time of the stage until the final product is delivered to the customer. In addition, a penalty cost is incurred if the final assembly stage is late. The objective is to set the planned leadtimes for each stage such that the total expected cost is minimized. We prove that the optimal planned leadtimes satisfy a set of Newsvendor equations and show that the probability that a stage is “blamed” for the lateness of the system equals a Newsvendor fractile. We derive structural properties of the optimal solution and compare it with the optimal solution under an alternative holding cost regime.

Suggested Citation

  • Jansen, Sjors & Atan, Zümbül & Adan, Ivo & Kok, Ton de, 2019. "Setting optimal planned leadtimes in configure-to-order assembly systems," European Journal of Operational Research, Elsevier, vol. 273(2), pages 585-595.
  • Handle: RePEc:eee:ejores:v:273:y:2019:i:2:p:585-595
    DOI: 10.1016/j.ejor.2018.08.036
    as

    Download full text from publisher

    File URL: http://www.sciencedirect.com/science/article/pii/S0377221718307318
    Download Restriction: Full text for ScienceDirect subscribers only

    File URL: https://libkey.io/10.1016/j.ejor.2018.08.036?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Chauhan, Satyaveer S. & Dolgui, Alexandre & Proth, Jean-Marie, 2009. "A continuous model for supply planning of assembly systems with stochastic component procurement times," International Journal of Production Economics, Elsevier, vol. 120(2), pages 411-417, August.
    2. Zümbül Atan & Ton de Kok & Nico P. Dellaert & Richard van Boxel & Fred Janssen, 2016. "Setting Planned Leadtimes in Customer-Order-Driven Assembly Systems," Manufacturing & Service Operations Management, INFORMS, vol. 18(1), pages 122-140, February.
    3. Ben-Ammar, Oussama & Dolgui, Alexandre & Wu, Desheng Dash, 2018. "Planned lead times optimization for multi-level assembly systems under uncertainties," Omega, Elsevier, vol. 78(C), pages 39-56.
    4. J. A. Buzacott & J. G. Shanthikumar, 1994. "Safety Stock versus Safety Time in MRP Controlled Production Systems," Management Science, INFORMS, vol. 40(12), pages 1678-1689, December.
    5. Atan, Zümbül & Ahmadi, Taher & Stegehuis, Clara & Kok, Ton de & Adan, Ivo, 2017. "Assemble-to-order systems: A review," European Journal of Operational Research, Elsevier, vol. 261(3), pages 866-879.
    6. Matsuura, Haruki & Tsubone, Hitoshi & Kanezashi, Masakazu, 1996. "Setting planned lead times for multi-operation jobs," European Journal of Operational Research, Elsevier, vol. 88(2), pages 287-303, January.
    7. Candace Arai Yano, 1987. "Setting Planned Leadtimes in Serial Production Systems with Tardiness Costs," Management Science, INFORMS, vol. 33(1), pages 95-106, January.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Liu, Liming & Xu, He & Zhu, Stuart X., 2020. "Push verse pull: Inventory-leadtime tradeoff for managing system variability," European Journal of Operational Research, Elsevier, vol. 287(1), pages 119-132.
    2. Quetschlich, Mathias & Moetz, André & Otto, Boris, 2021. "Optimisation model for multi-item multi-echelon supply chains with nested multi-level products," European Journal of Operational Research, Elsevier, vol. 290(1), pages 144-158.
    3. Slama, Ilhem & Ben-Ammar, Oussama & Thevenin, Simon & Dolgui, Alexandre & Masmoudi, Faouzi, 2022. "Stochastic program for disassembly lot-sizing under uncertain component refurbishing lead times," European Journal of Operational Research, Elsevier, vol. 303(3), pages 1183-1198.
    4. Taher Ahmadi & Zümbül Atan & Ton de Kok & Ivo Adan, 2019. "Optimal control policies for an inventory system with commitment lead time," Naval Research Logistics (NRL), John Wiley & Sons, vol. 66(3), pages 193-212, April.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Zümbül Atan & Ton de Kok & Nico P. Dellaert & Richard van Boxel & Fred Janssen, 2016. "Setting Planned Leadtimes in Customer-Order-Driven Assembly Systems," Manufacturing & Service Operations Management, INFORMS, vol. 18(1), pages 122-140, February.
    2. Liu, Liming & Xu, He & Zhu, Stuart X., 2020. "Push verse pull: Inventory-leadtime tradeoff for managing system variability," European Journal of Operational Research, Elsevier, vol. 287(1), pages 119-132.
    3. Louly, Mohamed-Aly & Dolgui, Alexandre, 2011. "Optimal time phasing and periodicity for MRP with POQ policy," International Journal of Production Economics, Elsevier, vol. 131(1), pages 76-86, May.
    4. Ben-Ammar, Oussama & Dolgui, Alexandre & Wu, Desheng Dash, 2018. "Planned lead times optimization for multi-level assembly systems under uncertainties," Omega, Elsevier, vol. 78(C), pages 39-56.
    5. Taher Ahmadi & Zümbül Atan & Ton de Kok & Ivo Adan, 2019. "Optimal control policies for an inventory system with commitment lead time," Naval Research Logistics (NRL), John Wiley & Sons, vol. 66(3), pages 193-212, April.
    6. Rong Yuan & Stephen C. Graves, 2016. "Setting optimal production lot sizes and planned lead times in a job shop," International Journal of Production Research, Taylor & Francis Journals, vol. 54(20), pages 6105-6120, October.
    7. Altendorfer, Klaus, 2015. "Influence of lot size and planned lead time on service level and inventory for a single-stage production system with advance demand information and random required lead times," International Journal of Production Economics, Elsevier, vol. 170(PB), pages 478-488.
    8. Altendorfer, Klaus & Minner, Stefan, 2011. "Simultaneous optimization of capacity and planned lead time in a two-stage production system with different customer due dates," European Journal of Operational Research, Elsevier, vol. 213(1), pages 134-146, August.
    9. Louly, Mohamed-Aly & Dolgui, Alexandre, 2013. "Optimal MRP parameters for a single item inventory with random replenishment lead time, POQ policy and service level constraint," International Journal of Production Economics, Elsevier, vol. 143(1), pages 35-40.
    10. Ben-Ammar, Oussama & Bettayeb, Belgacem & Dolgui, Alexandre, 2019. "Optimization of multi-period supply planning under stochastic lead times and a dynamic demand," International Journal of Production Economics, Elsevier, vol. 218(C), pages 106-117.
    11. Liberopoulos, George, 2008. "On the tradeoff between optimal order-base-stock levels and demand lead-times," European Journal of Operational Research, Elsevier, vol. 190(1), pages 136-155, October.
    12. Wilhelm, W. E. & Som, Pradip, 1998. "Analysis of a single-stage, single-product, stochastic, MRP-controlled assembly system," European Journal of Operational Research, Elsevier, vol. 108(1), pages 74-93, July.
    13. Sinha, Priyank & Kumar, Sameer & Chandra, Charu, 2023. "Strategies for ensuring required service level for COVID-19 herd immunity in Indian vaccine supply chain," European Journal of Operational Research, Elsevier, vol. 304(1), pages 339-352.
    14. Jacobs, F. Robert & Bendoly, Elliot, 2003. "Enterprise resource planning: Developments and directions for operations management research," European Journal of Operational Research, Elsevier, vol. 146(2), pages 233-240, April.
    15. Izack Cohen & Boaz Golany & Avraham Shtub, 2005. "Managing Stochastic, Finite Capacity, Multi-Project Systems through the Cross-Entropy Methodology," Annals of Operations Research, Springer, vol. 134(1), pages 183-199, February.
    16. Rahimi-Ghahroodi, S. & Al Hanbali, A. & Vliegen, I.M.H. & Cohen, M.A., 2019. "Joint optimization of spare parts inventory and service engineers staffing with full backlogging," International Journal of Production Economics, Elsevier, vol. 212(C), pages 39-50.
    17. Shi Chen & Hau Lee, 2017. "Incentive Alignment and Coordination of Project Supply Chains," Management Science, INFORMS, vol. 63(4), pages 1011-1025, April.
    18. Milne, R. John & Mahapatra, Santosh & Wang, Chi-Tai, 2015. "Optimizing planned lead times for enhancing performance of MRP systems," International Journal of Production Economics, Elsevier, vol. 167(C), pages 220-231.
    19. repec:dgr:rugsom:02a42 is not listed on IDEAS
    20. Slama, Ilhem & Ben-Ammar, Oussama & Thevenin, Simon & Dolgui, Alexandre & Masmoudi, Faouzi, 2022. "Stochastic program for disassembly lot-sizing under uncertain component refurbishing lead times," European Journal of Operational Research, Elsevier, vol. 303(3), pages 1183-1198.
    21. Hum, Sin-Hoon & Parlar, Mahmut & Zhou, Yun, 2018. "Measurement and optimization of responsiveness in supply chain networks with queueing structures," European Journal of Operational Research, Elsevier, vol. 264(1), pages 106-118.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:ejores:v:273:y:2019:i:2:p:585-595. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/locate/eor .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.