IDEAS home Printed from https://ideas.repec.org/a/eee/proeco/v131y2011i1p76-86.html
   My bibliography  Save this article

Optimal time phasing and periodicity for MRP with POQ policy

Author

Listed:
  • Louly, Mohamed-Aly
  • Dolgui, Alexandre

Abstract

This paper deals with component supply planning for assembly systems where several types of components are ordered from external suppliers to produce a single type of finished product. Actual component lead times are often different from those contracted because of random delays. An MRP approach with periodic order quantity (POQ) policy is used for the supply planning of components. Our aim is to find the optimal values of the order periodicity and planned lead times at the offsetting step of the MRP procedure. The goal is to minimise the sum of the average component holding, finished product backlogging and setup costs. Several theoretical properties of the objective function are proven and an efficient optimization algorithm is developed. The proofs of the explicit form and properties of the objective function as well as the development of the optimization algorithm occupy a large portion of this paper. The method developed can be used for the optimization of time phasing and periodicity for such an MRP system under lead time uncertainties.

Suggested Citation

  • Louly, Mohamed-Aly & Dolgui, Alexandre, 2011. "Optimal time phasing and periodicity for MRP with POQ policy," International Journal of Production Economics, Elsevier, vol. 131(1), pages 76-86, May.
  • Handle: RePEc:eee:proeco:v:131:y:2011:i:1:p:76-86
    as

    Download full text from publisher

    File URL: http://www.sciencedirect.com/science/article/pii/S0925-5273(10)00175-1
    Download Restriction: Full text for ScienceDirect subscribers only
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Nicholas C. Petruzzi & Maqbool Dada, 1999. "Pricing and the Newsvendor Problem: A Review with Extensions," Operations Research, INFORMS, vol. 47(2), pages 183-194, April.
    2. Fujiwara, Okitsugu & Sedarage, Dayani, 1997. "An optimal (Q,r) policy for a multipart assembly system under stochastic part procurement lead times," European Journal of Operational Research, Elsevier, vol. 100(3), pages 550-556, August.
    3. Bookbinder, James H. & Cakanyildirim, Metin, 1999. "Random lead times and expedited orders in (Q,r) inventory systems," European Journal of Operational Research, Elsevier, vol. 115(2), pages 300-313, June.
    4. Chauhan, Satyaveer S. & Dolgui, Alexandre & Proth, Jean-Marie, 2009. "A continuous model for supply planning of assembly systems with stochastic component procurement times," International Journal of Production Economics, Elsevier, vol. 120(2), pages 411-417, August.
    5. Riezebos, Jan, 2006. "Inventory order crossovers," International Journal of Production Economics, Elsevier, vol. 104(2), pages 666-675, December.
    6. Liberopoulos, George & Tsikis, Isidoros & Delikouras, Stefanos, 2010. "Backorder penalty cost coefficient "b": What could it be?," International Journal of Production Economics, Elsevier, vol. 123(1), pages 166-178, January.
    7. Robert S. Kaplan, 1970. "A Dynamic Inventory Model with Stochastic Lead Times," Management Science, INFORMS, vol. 16(7), pages 491-507, March.
    8. Xin X. He & Susan H. Xu & J. Keith Ord & Jack C. Hayya, 1998. "An Inventory Model with Order Crossover," Operations Research, INFORMS, vol. 46(3-supplem), pages 112-119, June.
    9. Dolgui, Alexandre & Ould-Louly, Mohamed-Aly, 2002. "A model for supply planning under lead time uncertainty," International Journal of Production Economics, Elsevier, vol. 78(2), pages 145-152, July.
    10. Tang, Ou & Grubbstrom, Robert W. & Zanoni, Simone, 2007. "Planned lead time determination in a make-to-order remanufacturing system," International Journal of Production Economics, Elsevier, vol. 108(1-2), pages 426-435, July.
    11. Purushottaman Nandakumar & Thomas E. Morton, 1993. "Near Myopic Heuristics for the Fixed-Life Perishability Problem," Management Science, INFORMS, vol. 39(12), pages 1490-1498, December.
    12. Tang, Ou & Grubbstrom, Robert W., 2005. "Considering stochastic lead times in a manufacturing/remanufacturing system with deterministic demands and returns," International Journal of Production Economics, Elsevier, vol. 93(1), pages 285-300, January.
    13. Tang, Ou & Grubbstrom, Robert W., 2003. "The detailed coordination problem in a two-level assembly system with stochastic lead times," International Journal of Production Economics, Elsevier, vol. 81(1), pages 415-429, January.
    14. Louly, Mohamed-Aly & Dolgui, Alexandre & Hnaien, Faicel, 2008. "Supply planning for single-level assembly system with stochastic component delivery times and service-level constraint," International Journal of Production Economics, Elsevier, vol. 115(1), pages 236-247, September.
    15. Ould-Louly, Mohamed-Aly & Dolgui, Alexandre, 2004. "The MPS parameterization under lead time uncertainty," International Journal of Production Economics, Elsevier, vol. 90(3), pages 369-376, August.
    16. Wilhelm, W. E. & Som, Pradip, 1998. "Analysis of a single-stage, single-product, stochastic, MRP-controlled assembly system," European Journal of Operational Research, Elsevier, vol. 108(1), pages 74-93, July.
    17. Mula, J. & Poler, R. & Garcia-Sabater, J.P. & Lario, F.C., 2006. "Models for production planning under uncertainty: A review," International Journal of Production Economics, Elsevier, vol. 103(1), pages 271-285, September.
    18. Candace Arai Yano, 1987. "Setting Planned Leadtimes in Serial Production Systems with Tardiness Costs," Management Science, INFORMS, vol. 33(1), pages 95-106, January.
    19. van Donselaar, K. H. & Gubbels, B. J., 2002. "How to release orders in order to minimise system inventory and system nervousness?," International Journal of Production Economics, Elsevier, vol. 78(3), pages 335-343, August.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Faicel Hnaien & Alexandre Dolgui & Desheng Dash Wu, 2016. "Single-period inventory model for one-level assembly system with stochastic lead times and demand," International Journal of Production Research, Taylor & Francis Journals, vol. 54(1), pages 186-203, January.
    2. Manuel Díaz-Madroñero & Josefa Mula & Mariano Jiménez & David Peidro, 2017. "A rolling horizon approach for material requirement planning under fuzzy lead times," International Journal of Production Research, Taylor & Francis Journals, vol. 55(8), pages 2197-2211, April.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Louly, Mohamed-Aly & Dolgui, Alexandre & Hnaien, Faicel, 2008. "Supply planning for single-level assembly system with stochastic component delivery times and service-level constraint," International Journal of Production Economics, Elsevier, vol. 115(1), pages 236-247, September.
    2. Louly, Mohamed-Aly Ould & Dolgui, Alexandre, 2009. "Calculating safety stocks for assembly systems with random component procurement lead times: A branch and bound algorithm," European Journal of Operational Research, Elsevier, vol. 199(3), pages 723-731, December.
    3. Louly, Mohamed-Aly & Dolgui, Alexandre, 2013. "Optimal MRP parameters for a single item inventory with random replenishment lead time, POQ policy and service level constraint," International Journal of Production Economics, Elsevier, vol. 143(1), pages 35-40.
    4. Ben-Ammar, Oussama & Bettayeb, Belgacem & Dolgui, Alexandre, 2019. "Optimization of multi-period supply planning under stochastic lead times and a dynamic demand," International Journal of Production Economics, Elsevier, vol. 218(C), pages 106-117.
    5. Chauhan, Satyaveer S. & Dolgui, Alexandre & Proth, Jean-Marie, 2009. "A continuous model for supply planning of assembly systems with stochastic component procurement times," International Journal of Production Economics, Elsevier, vol. 120(2), pages 411-417, August.
    6. Louly, Mohamed-Aly & Dolgui, Alexandre, 2012. "A note on analytic calculation of planned lead times for assembly systems under POQ policy and service level constraint," International Journal of Production Economics, Elsevier, vol. 140(2), pages 778-781.
    7. Manuel Díaz-Madroñero & Josefa Mula & Mariano Jiménez & David Peidro, 2017. "A rolling horizon approach for material requirement planning under fuzzy lead times," International Journal of Production Research, Taylor & Francis Journals, vol. 55(8), pages 2197-2211, April.
    8. Ben-Ammar, Oussama & Dolgui, Alexandre & Wu, Desheng Dash, 2018. "Planned lead times optimization for multi-level assembly systems under uncertainties," Omega, Elsevier, vol. 78(C), pages 39-56.
    9. Faicel Hnaien & Alexandre Dolgui & Desheng Dash Wu, 2016. "Single-period inventory model for one-level assembly system with stochastic lead times and demand," International Journal of Production Research, Taylor & Francis Journals, vol. 54(1), pages 186-203, January.
    10. Borodin, Valeria & Dolgui, Alexandre & Hnaien, Faicel & Labadie, Nacima, 2016. "Component replenishment planning for a single-level assembly system under random lead times: A chance constrained programming approach," International Journal of Production Economics, Elsevier, vol. 181(PA), pages 79-86.
    11. Rappold, James A. & Yoho, Keenan D., 2014. "Setting safety stocks for stable rotation cycle schedules," International Journal of Production Economics, Elsevier, vol. 156(C), pages 146-158.
    12. Riezebos, Jan, 2006. "Inventory order crossovers," International Journal of Production Economics, Elsevier, vol. 104(2), pages 666-675, December.
    13. Hayya, Jack C. & Bagchi, Uttarayan & Kim, Jeon G. & Sun, Daewon, 2008. "On static stochastic order crossover," International Journal of Production Economics, Elsevier, vol. 114(1), pages 404-413, July.
    14. Ould-Louly, Mohamed-Aly & Dolgui, Alexandre, 2004. "The MPS parameterization under lead time uncertainty," International Journal of Production Economics, Elsevier, vol. 90(3), pages 369-376, August.
    15. Achin Srivastav & Sunil Agrawal, 2020. "On a single item single stage mixture inventory models with independent stochastic lead times," Operational Research, Springer, vol. 20(4), pages 2189-2227, December.
    16. Lin, James T. & Chen, Tzu-Li & Lin, Yen-Ting, 2009. "Critical material planning for TFT-LCD production industry," International Journal of Production Economics, Elsevier, vol. 122(2), pages 639-655, December.
    17. Chatfield, Dean C. & Pritchard, Alan M., 2018. "Crossover aware base stock decisions for service-driven systems," Transportation Research Part E: Logistics and Transportation Review, Elsevier, vol. 114(C), pages 312-330.
    18. Thomas Wensing & Heinrich Kuhn, 2015. "Analysis of production and inventory systems when orders may cross over," Annals of Operations Research, Springer, vol. 231(1), pages 265-281, August.
    19. Hayya, Jack C. & Harrison, Terry P. & He, X. James, 2011. "The impact of stochastic lead time reduction on inventory cost under order crossover," European Journal of Operational Research, Elsevier, vol. 211(2), pages 274-281, June.
    20. Sivadasan, Suja & Smart, Janet & Huaccho Huatuco, Luisa & Calinescu, Anisoara, 2013. "Reducing schedule instability by identifying and omitting complexity-adding information flows at the supplier–customer interface," International Journal of Production Economics, Elsevier, vol. 145(1), pages 253-262.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:proeco:v:131:y:2011:i:1:p:76-86. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/locate/ijpe .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.