Incentive Contracts in Serial Stochastic Projects

Author

Listed:
  • Tony Chen

    (Department of Information Systems and Operations Management, Michael G. Foster School of Business, University of Washington, Seattle, Washington 98195)

  • Ted Klastorin

    (Department of Information Systems and Operations Management, Michael G. Foster School of Business, University of Washington, Seattle, Washington 98195)

  • Michael R. Wagner

    (Department of Information Systems and Operations Management, Michael G. Foster School of Business, University of Washington, Seattle, Washington 98195)

Abstract

In this paper we propose an incentive payment contract for stochastic projects defined by a series of stages or tasks that are outsourced to independent subcontractors. Projects defined by sequentially completed independent stages are common in new product development and other high-risk projects. Our goal is to maximize the client’s expected discounted profit. Our proposed contract reflects the convex time-cost trade-off that is well known in the project scheduling literature. We show that this type of contract dominates a fixed price contract with respect to expected client’s profit and schedule performance, regardless of payment timing considerations. Using a piecewise linear approximation, we show that our contract is a generalization of an incentive/disincentive contract that is frequently used in practice. We show how our contract can be used to find the optimal due date and penalties/bonuses in an incentive/disincentive contract. We compare this contract with several variations and discuss implications for both the client and subcontractors.

Suggested Citation

  • Tony Chen & Ted Klastorin & Michael R. Wagner, 2015. "Incentive Contracts in Serial Stochastic Projects," Manufacturing & Service Operations Management, INFORMS, vol. 17(3), pages 290-301, July.
  • Handle: RePEc:inm:ormsom:v:17:y:2015:i:3:p:290-301
    DOI: 10.1287/msom.2015.0528
    as

    Download full text from publisher

    File URL: http://dx.doi.org/10.1287/msom.2015.0528
    Download Restriction: no

    File URL: https://libkey.io/10.1287/msom.2015.0528?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Nalini Dayanand & Rema Padman, 2001. "Project Contracts and Payment Schedules: The Client's Problem," Management Science, INFORMS, vol. 47(12), pages 1654-1667, December.
    2. Leonardo P. Santiago & Pirooz Vakili, 2005. "On the Value of Flexibility in R&D Projects," Management Science, INFORMS, vol. 51(8), pages 1206-1218, August.
    3. Fernando Bernstein & Awi Federgruen, 2005. "Decentralized Supply Chains with Competing Retailers Under Demand Uncertainty," Management Science, INFORMS, vol. 51(1), pages 18-29, January.
    4. Joel Goh & Nicholas G. Hall, 2013. "Total Cost Control in Project Management via Satisficing," Management Science, INFORMS, vol. 59(6), pages 1354-1372, June.
    5. Elmaghraby, Salah E., 2005. "On the fallacy of averages in project risk management," European Journal of Operational Research, Elsevier, vol. 165(2), pages 307-313, September.
    6. Martin L. Weitzman, 1980. "The "Ratchet Principle" and Performance Incentives," Bell Journal of Economics, The RAND Corporation, vol. 11(1), pages 302-308, Spring.
    7. Scott A. Shane & Karl T. Ulrich, 2004. "50th Anniversary Article: Technological Innovation, Product Development, and Entrepreneurship in Management Science," Management Science, INFORMS, vol. 50(2), pages 133-144, February.
    8. Genaro Gutierrez & Anand Paul, 2000. "Analysis of the Effects of Uncertainty, Risk-Pooling, and Subcontracting Mechanisms on Project Performance," Operations Research, INFORMS, vol. 48(6), pages 927-938, December.
    9. Dharma Kwon, H. & Lippman, Steven A. & Tang, Christopher S., 2011. "Sourcing decisions of project tasks with exponential completion times: Impact on operating profits," International Journal of Production Economics, Elsevier, vol. 134(1), pages 138-150, November.
    10. Tavares, L. V., 2002. "A review of the contribution of Operational Research to Project Management," European Journal of Operational Research, Elsevier, vol. 136(1), pages 1-18, January.
    11. Arnold H. Buss & Meir J. Rosenblatt, 1997. "Activity Delay in Stochastic Project Networks," Operations Research, INFORMS, vol. 45(1), pages 126-139, February.
    12. Kamien, Morton I & Schwartz, Nancy L, 1972. "Timing of Innovations Under Rivalry," Econometrica, Econometric Society, vol. 40(1), pages 43-60, January.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Chen, Bo & Hall, Nicholas G., 2021. "Incentive schemes for resolving Parkinson’s Law in project management," European Journal of Operational Research, Elsevier, vol. 288(2), pages 666-681.
    2. Anil Aswani & Zuo-Jun Max Shen & Auyon Siddiq, 2019. "Data-Driven Incentive Design in the Medicare Shared Savings Program," Operations Research, INFORMS, vol. 67(4), pages 1002-1026, July.
    3. Bai, Jiaru & So, Kut C. & Tang, Christopher, 2016. "A queueing model for managing small projects under uncertainties," European Journal of Operational Research, Elsevier, vol. 253(3), pages 777-790.
    4. Shivam Gupta & Anupam Agrawal & Jennifer K. Ryan, 2023. "Agile contracting: Managing incentives under uncertain needs," Production and Operations Management, Production and Operations Management Society, vol. 32(3), pages 972-988, March.
    5. Shi Chen & Hau Lee, 2017. "Incentive Alignment and Coordination of Project Supply Chains," Management Science, INFORMS, vol. 63(4), pages 1011-1025, April.
    6. Zhihua Chen & Yanfei Lan & Ruiqing Zhao & Changjing Shang, 2019. "Deadline-based incentive contracts in project management with cost salience," Fuzzy Optimization and Decision Making, Springer, vol. 18(4), pages 451-473, December.
    7. Shi Chen & Ted Klastorin & Michael R. Wagner, 2021. "Designing practical coordinating contracts in decentralized projects," Naval Research Logistics (NRL), John Wiley & Sons, vol. 68(2), pages 183-198, March.
    8. Ju Myung Song & Yao Zhao & Xin Xu, 2021. "Incentives and Gaming in Collaborative Projects Under Risk-Sharing Partnerships," Manufacturing & Service Operations Management, INFORMS, vol. 23(2), pages 453-470, March.
    9. Stylianos Kavadias & Karl T. Ulrich, 2020. "Innovation and New Product Development: Reflections and Insights from the Research Published in the First 20 Years of Manufacturing & Service Operations Management," Manufacturing & Service Operations Management, INFORMS, vol. 22(1), pages 84-92, January.
    10. Jinjin Liu & Hua Ke & Yuan Gao, 2022. "Manufacturer’s R &D cooperation contract: linear fee or revenue-sharing payment in a low-carbon supply chain," Annals of Operations Research, Springer, vol. 318(1), pages 323-355, November.
    11. Morvarid Rahmani & Guillaume Roels & Uday S. Karmarkar, 2017. "Collaborative Work Dynamics in Projects with Co‐Production," Production and Operations Management, Production and Operations Management Society, vol. 26(4), pages 686-703, April.
    12. Yu, Xinning & Lan, Yanfei & Zhao, Ruiqing, 2021. "Strategic green technology innovation in a two-stage alliance: Vertical collaboration or co-development?," Omega, Elsevier, vol. 98(C).
    13. Kerkhove, L.P. & Vanhoucke, M., 2016. "Incentive contract design for projects: The owner׳s perspective," Omega, Elsevier, vol. 62(C), pages 93-114.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Shi Chen & Ted Klastorin & Michael R. Wagner, 2021. "Designing practical coordinating contracts in decentralized projects," Naval Research Logistics (NRL), John Wiley & Sons, vol. 68(2), pages 183-198, March.
    2. Sobel, Matthew J. & Szmerekovsky, Joseph G. & Tilson, Vera, 2009. "Scheduling projects with stochastic activity duration to maximize expected net present value," European Journal of Operational Research, Elsevier, vol. 198(3), pages 697-705, November.
    3. Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
    4. Hazır, Öncü & Ulusoy, Gündüz, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," International Journal of Production Economics, Elsevier, vol. 223(C).
    5. Hermans, Ben & Leus, Roel & Looy, Bart Van, 2023. "Deciding on scheduling, secrecy, and patenting during the new product development process: The relevance of project planning models," Omega, Elsevier, vol. 116(C).
    6. Jiao Wang & Kai Yang & Ruiqing Zhao, 2017. "The impact of decision criteria on deadline-based incentive contracts in project management," Journal of Intelligent Manufacturing, Springer, vol. 28(3), pages 643-655, March.
    7. Zhang, Jingwen & Elmaghraby, Salah E., 2014. "The relevance of the “alphorn of uncertainty” to the financial management of projects under uncertainty," European Journal of Operational Research, Elsevier, vol. 238(1), pages 65-76.
    8. Hartmann, Sönke & Briskorn, Dirk, 2008. "A survey of variants and extensions of the resource-constrained project scheduling problem," Working Paper Series 02/2008, Hamburg School of Business Administration (HSBA).
    9. Wiesemann, Wolfram & Kuhn, Daniel & Rustem, Berç, 2010. "Maximizing the net present value of a project under uncertainty," European Journal of Operational Research, Elsevier, vol. 202(2), pages 356-367, April.
    10. Dharma Kwon, H. & Lippman, Steven A. & Tang, Christopher S., 2011. "Sourcing decisions of project tasks with exponential completion times: Impact on operating profits," International Journal of Production Economics, Elsevier, vol. 134(1), pages 138-150, November.
    11. Yangyang Liang & Nanfang Cui & Tian Wang & Erik Demeulemeester, 2019. "Robust resource-constrained max-NPV project scheduling with stochastic activity duration," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 41(1), pages 219-254, March.
    12. Öncü Hazir & Gündüz Ulusoy, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," Post-Print hal-02898162, HAL.
    13. Yousry Abdelkader, 2010. "Adjustment of the moments of the project completion times when activity times are exponentially distributed," Annals of Operations Research, Springer, vol. 181(1), pages 503-514, December.
    14. Estévez-Fernández, Arantza, 2012. "A game theoretical approach to sharing penalties and rewards in projects," European Journal of Operational Research, Elsevier, vol. 216(3), pages 647-657.
    15. Liliana Meza-González & Jaime Marie Sepulveda, 2019. "The impact of competition with China in the US market on innovation in Mexican manufacturing firms," Latin American Economic Review, Springer;Centro de Investigaciòn y Docencia Económica (CIDE), vol. 28(1), pages 1-21, December.
    16. Moon, Ilkyeong & Feng, Xuehao, 2017. "Supply chain coordination with a single supplier and multiple retailers considering customer arrival times and route selection," Transportation Research Part E: Logistics and Transportation Review, Elsevier, vol. 106(C), pages 78-97.
    17. Wendi Tian & Erik Demeulemeester, 2014. "Railway scheduling reduces the expected project makespan over roadrunner scheduling in a multi-mode project scheduling environment," Annals of Operations Research, Springer, vol. 213(1), pages 271-291, February.
    18. Yang, Jian & Qi, Xiangtong, 2009. "On the design of coordinating contracts," International Journal of Production Economics, Elsevier, vol. 122(2), pages 581-594, December.
    19. Jackson, William III & Nandakumar, Purushottaman & Roth, Aleda V., 2003. "Market structure, consumer banking, and optimal level of service quality," Review of Financial Economics, Elsevier, vol. 12(1), pages 49-63.
    20. Yucai Wu & Jiguang Wang & Changhong Li, 2019. "Decisions of Supply Chain Considering Chain-to-Chain Competition and Service Negative Spillover Effect," Sustainability, MDPI, vol. 11(6), pages 1-19, March.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:inm:ormsom:v:17:y:2015:i:3:p:290-301. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Asher (email available below). General contact details of provider: https://edirc.repec.org/data/inforea.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.