Project Contracts and Payment Schedules: The Client's Problem

Author

Listed:
  • Nalini Dayanand

    (Dialogos, Inc., 12 Farnsworth Street, Boston, Massachusetts 02210)

  • Rema Padman

    (The H. John Heinz III School of Public Policy and Management, Carnegie Mellon University, Pittsburgh, Pennsylvania 15213)

Abstract

Contractual agreements have assumed significant complexity in recent times because of the emergence of strategies like outsourcing and partnering in the successful completion of large software development, manufacturing, and construction projects. A client and contractor enter into an agreement for a project either by bidding or negotiation. Effective and efficient bidding, negotiation, and subsequent monitoring are hindered by the lack of appropriate decision support tools for the management of project finances. Progress payments to the contractor are an important issue in project management because of their potential impact on project finances and activity schedules. In this paper, we consider the problem of simultaneously determining the amount, location, and timing of progress payments in projects from a client's perspective. We develop three mixed-integer linear programming models, based on some practical methods of determining payment schedules from different types of project contracts. We discuss properties of the models and draw insights about the characteristics of optimal payment schedules obtained with each model by an experimental study on a sample of 10 small projects. Our analysis shows that, contrary to current practice, the client obtains the greatest benefit by scheduling the project for early completion such that the payments are not made at regular intervals. It is also cost effective for the client to make payments either in the early stages of the project or toward the end, even though this causes considerable variation in the time gap between payments. We also evaluate the impact of the client's preferred payment schedules on the contractor's finances and activity schedules, and draw some conclusions on the interdependence of payment and project parameters on the objectives of both parties entering the contractual agreement.

Suggested Citation

  • Nalini Dayanand & Rema Padman, 2001. "Project Contracts and Payment Schedules: The Client's Problem," Management Science, INFORMS, vol. 47(12), pages 1654-1667, December.
  • Handle: RePEc:inm:ormnsc:v:47:y:2001:i:12:p:1654-1667
    DOI: 10.1287/mnsc.47.12.1654.10242
    as

    Download full text from publisher

    File URL: http://dx.doi.org/10.1287/mnsc.47.12.1654.10242
    Download Restriction: no

    File URL: https://libkey.io/10.1287/mnsc.47.12.1654.10242?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Herroelen, Willy S. & Van Dommelen, Patrick & Demeulemeester, Erik L., 1997. "Project network models with discounted cash flows a guided tour through recent developments," European Journal of Operational Research, Elsevier, vol. 100(1), pages 97-121, July.
    2. A. H. Russell, 1970. "Cash Flows in Networks," Management Science, INFORMS, vol. 16(5), pages 357-373, January.
    3. Elmaghraby, Salah E. & Herroelen, Willy S., 1990. "The scheduling of activities to maximize the net present value of projects," European Journal of Operational Research, Elsevier, vol. 49(1), pages 35-49, November.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Estévez-Fernández, Arantza, 2012. "A game theoretical approach to sharing penalties and rewards in projects," European Journal of Operational Research, Elsevier, vol. 216(3), pages 647-657.
    2. Zhang, Jingwen & Elmaghraby, Salah E., 2014. "The relevance of the “alphorn of uncertainty” to the financial management of projects under uncertainty," European Journal of Operational Research, Elsevier, vol. 238(1), pages 65-76.
    3. Kolisch, Rainer & Padman, Rema, 1997. "An integrated survey of project scheduling," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 463, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    4. Shi Chen & Hau Lee, 2017. "Incentive Alignment and Coordination of Project Supply Chains," Management Science, INFORMS, vol. 63(4), pages 1011-1025, April.
    5. Zhengwen He & Nengmin Wang & Pengxiang Li, 2014. "Simulated annealing for financing cost distribution based project payment scheduling from a joint perspective," Annals of Operations Research, Springer, vol. 213(1), pages 203-220, February.
    6. Wenbo Shi & Tianke Feng, 2016. "Examining supply contracts under cost and demand uncertainties from supplier’s perspective: a real options approach," International Journal of Production Research, Taylor & Francis Journals, vol. 54(1), pages 83-97, January.
    7. Moon, Yongma & Yao, Tao & Jiang, Bin, 2011. "Outsourcing versus joint venture from vendor's perspective," International Journal of Production Economics, Elsevier, vol. 129(1), pages 23-31, January.
    8. Minhyuk Jung & Shira You & Seokho Chi & Ilhan Yu & Bon-Gang Hwang, 2018. "The Relationship between Unbilled Accounts Receivable and Financial Performance of Construction Contractors," Sustainability, MDPI, vol. 10(8), pages 1-14, July.
    9. Cyril Briand & Sandra Ulrich Ngueveu & Přemysl Šůcha, 2017. "Finding an optimal Nash equilibrium to the multi-agent project scheduling problem," Journal of Scheduling, Springer, vol. 20(5), pages 475-491, October.
    10. Hartmann, Sönke & Briskorn, Dirk, 2008. "A survey of variants and extensions of the resource-constrained project scheduling problem," Working Paper Series 02/2008, Hamburg School of Business Administration (HSBA).
    11. Chung-Lun Li & Nicholas G. Hall, 2019. "Work Package Sizing and Project Performance," Operations Research, INFORMS, vol. 67(1), pages 123-142, January.
    12. Sobel, Matthew J. & Szmerekovsky, Joseph G. & Tilson, Vera, 2009. "Scheduling projects with stochastic activity duration to maximize expected net present value," European Journal of Operational Research, Elsevier, vol. 198(3), pages 697-705, November.
    13. Kimms, Alf & Fischer, Sven, 1998. "Zahlungsorientierte Gestaltung von Werkverträgen," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 467, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    14. Pascale Crama & Bert De Reyck & Zeger Degraeve, 2008. "Milestone Payments or Royalties? Contract Design for R&D Licensing," Operations Research, INFORMS, vol. 56(6), pages 1539-1552, December.
    15. Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
    16. Leyman, Pieter & Vanhoucke, Mario, 2017. "Capital- and resource-constrained project scheduling with net present value optimization," European Journal of Operational Research, Elsevier, vol. 256(3), pages 757-776.
    17. Banaszak, Z.A. & Zaremba, M.B. & Muszynski, W., 2009. "Constraint programming for project-driven manufacturing," International Journal of Production Economics, Elsevier, vol. 120(2), pages 463-475, August.
    18. He, Zhengwen & Liu, Renjing & Jia, Tao, 2012. "Metaheuristics for multi-mode capital-constrained project payment scheduling," European Journal of Operational Research, Elsevier, vol. 223(3), pages 605-613.
    19. He, Zhengwen & Xu, Yu, 2008. "Multi-mode project payment scheduling problems with bonus-penalty structure," European Journal of Operational Research, Elsevier, vol. 189(3), pages 1191-1207, September.
    20. Dalia H. Dorrah & Brenda McCabe, 2023. "Integrated Agent-Based Simulation and Game Theory Decision Support Framework for Cash Flow and Payment Management in Construction Projects," Sustainability, MDPI, vol. 16(1), pages 1-25, December.
    21. He, Zhengwen & Wang, Nengmin & Jia, Tao & Xu, Yu, 2009. "Simulated annealing and tabu search for multi-mode project payment scheduling," European Journal of Operational Research, Elsevier, vol. 198(3), pages 688-696, November.
    22. Kerkhove, L.P. & Vanhoucke, M., 2016. "Incentive contract design for projects: The owner׳s perspective," Omega, Elsevier, vol. 62(C), pages 93-114.
    23. Tony Chen & Ted Klastorin & Michael R. Wagner, 2015. "Incentive Contracts in Serial Stochastic Projects," Manufacturing & Service Operations Management, INFORMS, vol. 17(3), pages 290-301, July.
    24. Joseph G. Szmerekovsky, 2005. "The Impact of Contractor Behavior on the Client's Payment-Scheduling Problem," Management Science, INFORMS, vol. 51(4), pages 629-640, April.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Mika, Marek & Waligora, Grzegorz & Weglarz, Jan, 2005. "Simulated annealing and tabu search for multi-mode resource-constrained project scheduling with positive discounted cash flows and different payment models," European Journal of Operational Research, Elsevier, vol. 164(3), pages 639-668, August.
    2. Joseph G. Szmerekovsky & George L. Vairaktarakis, 2006. "Maximizing project cash availability," Naval Research Logistics (NRL), John Wiley & Sons, vol. 53(4), pages 272-284, June.
    3. He, Zhengwen & Wang, Nengmin & Jia, Tao & Xu, Yu, 2009. "Simulated annealing and tabu search for multi-mode project payment scheduling," European Journal of Operational Research, Elsevier, vol. 198(3), pages 688-696, November.
    4. Wiesemann, Wolfram & Kuhn, Daniel & Rustem, Berç, 2010. "Maximizing the net present value of a project under uncertainty," European Journal of Operational Research, Elsevier, vol. 202(2), pages 356-367, April.
    5. De Reyck, Bert & Herroelen, willy, 1998. "A branch-and-bound procedure for the resource-constrained project scheduling problem with generalized precedence relations," European Journal of Operational Research, Elsevier, vol. 111(1), pages 152-174, November.
    6. Creemers, Stefan, 2018. "Maximizing the expected net present value of a project with phase-type distributed activity durations: An efficient globally optimal solution procedure," European Journal of Operational Research, Elsevier, vol. 267(1), pages 16-22.
    7. Kolisch, R. & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Omega, Elsevier, vol. 29(3), pages 249-272, June.
    8. Bruni, Maria Elena & Hazır, Öncü, 2024. "A risk-averse distributionally robust project scheduling model to address payment delays," European Journal of Operational Research, Elsevier, vol. 318(2), pages 398-407.
    9. Wenhui Zhao & Nicholas G. Hall & Zhixin Liu, 2020. "Project Evaluation and Selection with Task Failures," Production and Operations Management, Production and Operations Management Society, vol. 29(2), pages 428-446, February.
    10. Mario Vanhoucke & Erik Demeulemeester & Willy Herroelen, 2001. "On Maximizing the Net Present Value of a Project Under Renewable Resource Constraints," Management Science, INFORMS, vol. 47(8), pages 1113-1121, August.
    11. He, Zhengwen & Xu, Yu, 2008. "Multi-mode project payment scheduling problems with bonus-penalty structure," European Journal of Operational Research, Elsevier, vol. 189(3), pages 1191-1207, September.
    12. M. Vanhoucke, 2006. "An efficient hybrid search algorithm for various optimization problems," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 06/365, Ghent University, Faculty of Economics and Business Administration.
    13. Etgar, Ran & Gelbard, Roy & Cohen, Yuval, 2017. "Optimizing version release dates of research and development long-term processes," European Journal of Operational Research, Elsevier, vol. 259(2), pages 642-653.
    14. Ulusoy, Gunduz & Cebelli, Serkan, 2000. "An equitable approach to the payment scheduling problem in project management," European Journal of Operational Research, Elsevier, vol. 127(2), pages 262-278, December.
    15. Yukang He & Tao Jia & Weibo Zheng, 2024. "Simulated annealing for centralised resource-constrained multiproject scheduling to minimise the maximal cash flow gap under different payment patterns," Annals of Operations Research, Springer, vol. 338(1), pages 115-149, July.
    16. Herroelen, Willy S. & Van Dommelen, Patrick & Demeulemeester, Erik L., 1997. "Project network models with discounted cash flows a guided tour through recent developments," European Journal of Operational Research, Elsevier, vol. 100(1), pages 97-121, July.
    17. Nursel Kavlak & Gündüz Ulusoy & Funda Sivrikaya Şerifoğlu & Ş. İlker Birbil, 2009. "Client‐contractor bargaining on net present value in project scheduling with limited resources," Naval Research Logistics (NRL), John Wiley & Sons, vol. 56(2), pages 93-112, March.
    18. Weglarz, Jan & Józefowska, Joanna & Mika, Marek & Waligóra, Grzegorz, 2011. "Project scheduling with finite or infinite number of activity processing modes - A survey," European Journal of Operational Research, Elsevier, vol. 208(3), pages 177-205, February.
    19. Zhengwen He & Nengmin Wang & Pengxiang Li, 2014. "Simulated annealing for financing cost distribution based project payment scheduling from a joint perspective," Annals of Operations Research, Springer, vol. 213(1), pages 203-220, February.
    20. Etgar, Ran & Shtub, Avraham & LeBlanc, Larry J., 1997. "Scheduling projects to maximize net present value -- the case of time-dependent, contingent cash flows," European Journal of Operational Research, Elsevier, vol. 96(1), pages 90-96, January.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:inm:ormnsc:v:47:y:2001:i:12:p:1654-1667. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Asher (email available below). General contact details of provider: https://edirc.repec.org/data/inforea.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.