Predicting Extension of Time and Increasing Contract Price in Road Infrastructure Projects Using a Sugeno Fuzzy Logic Model
Author
Abstract
Suggested Citation
Download full text from publisher
References listed on IDEAS
- Nevena Simić & Nenad Ivanišević & Đorđe Nedeljković & Aleksandar Senić & Zoran Stojadinović & Marija Ivanović, 2023. "Early Highway Construction Cost Estimation: Selection of Key Cost Drivers," Sustainability, MDPI, vol. 15(6), pages 1-20, March.
- J. H. M. Tah & V. Carr, 2000. "A proposal for construction project risk assessment using fuzzy logic," Construction Management and Economics, Taylor & Francis Journals, vol. 18(4), pages 491-500.
- Daeseok Han & Jin-Hyuk Lee & Ki-Tae Park, 2022. "Deterioration Models for Bridge Pavement Materials for a Life Cycle Cost Analysis," Sustainability, MDPI, vol. 14(18), pages 1-15, September.
Citations
Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
Cited by:
- Dragan Lazarević & Đorđe Popović & Muhammed Yasin Çodur & Momčilo Dobrodolac, 2024. "Fuzzy Logic Approach for Evaluating Electromobility Alternatives in Last-Mile Delivery: Belgrade as a Case Study," Energies, MDPI, vol. 17(24), pages 1-45, December.
Most related items
These are the items that most often cite the same works as this one and are cited by the same works as this one.- Hani Alyami & Paul Tae-Woo Lee & Zaili Yang & Ramin Riahi & Stephen Bonsall & Jin Wang, 2014. "An advanced risk analysis approach for container port safety evaluation," Maritime Policy & Management, Taylor & Francis Journals, vol. 41(7), pages 634-650, December.
- Gholamreza Dehdasht & Rosli Mohamad Zin & M. Salim Ferwati & Mu’azu Mohammed Abdullahi & Ali Keyvanfar & Ronald McCaffer, 2017. "DEMATEL-ANP Risk Assessment in Oil and Gas Construction Projects," Sustainability, MDPI, vol. 9(8), pages 1-24, August.
- Patricia Romero-Lankao & Daniel M. Gnatz & Olga Wilhelmi & Mary Hayden, 2016. "Urban Sustainability and Resilience: From Theory to Practice," Sustainability, MDPI, vol. 8(12), pages 1-19, November.
- Abraham Park & Chen Yu Chang, 2013. "Impacts of Construction Events on the Project Equity Value of the Channel Tunnel Project," ERES eres2013_97, European Real Estate Society (ERES).
- Usama H. Issa & Ashraf Balabel & Mohammed Abdelhakeem & Medhat M. A. Osman, 2021. "Developing a Risk Model for Assessment and Control of the Spread of COVID-19," Risks, MDPI, vol. 9(2), pages 1-15, February.
- Sabriye Topal & Emine Atasoylu, 2022. "A Fuzzy Risk Assessment Model for Small Scale Construction Work," Sustainability, MDPI, vol. 14(8), pages 1-17, April.
- Cabrera Llanos, Agustín I. & Ortiz Arango, Francisco & Dávila Aragón, Griselda, 2022. "Caracterización de la productividad de una empresa mexicana desarrolladora de tecnología mediante control difuso [Characterization of the productivity of a Mexican technology development company th," Revista de Métodos Cuantitativos para la Economía y la Empresa = Journal of Quantitative Methods for Economics and Business Administration, Universidad Pablo de Olavide, Department of Quantitative Methods for Economics and Business Administration, vol. 34(1), pages 281-304, December.
- John Malu Nzioki & Dr. Mary Nyawira Mwenda, 2021. "Enhancing Performance of the Building Construction Industry through Quantitative Risk Analysis and Risk Response: A Case of Exchequer Funded Building Construction Projects in Machakos County, Kenya," International Journal of Research and Innovation in Social Science, International Journal of Research and Innovation in Social Science (IJRISS), vol. 5(3), pages 31-39, March.
- Huiru Zhao & Nana Li, 2015. "Risk Evaluation of a UHV Power Transmission Construction Project Based on a Cloud Model and FCE Method for Sustainability," Sustainability, MDPI, vol. 7(3), pages 1-30, March.
- Cunbin Li & Yunqi Liu & Shuke Li, 2016. "Risk Evaluation of Qinghai–Tibet Power Grid Interconnection Project for Sustainability," Sustainability, MDPI, vol. 8(1), pages 1-19, January.
- Xiao, Zengqi & Lam, Jasmine Siu Lee, 2019. "Willingness to take contractual risk in port public-private partnerships under economic volatility: The role of institutional environment in emerging economies," Transport Policy, Elsevier, vol. 81(C), pages 106-116.
- Jelena M. Andrić & Jiayuan Wang & Ruoyu Zhong, 2019. "Identifying the Critical Risks in Railway Projects Based on Fuzzy and Sensitivity Analysis: A Case Study of Belt and Road Projects," Sustainability, MDPI, vol. 11(5), pages 1-18, March.
- Jeffrey Kouton & Wilfried Sanogo & Nandi Djomgoue, 2023. "Risk allocation in energy infrastructure PPPs projects in selected African countries: does institutional quality, PPPs experience and income level make a difference?," Economic Change and Restructuring, Springer, vol. 56(1), pages 537-580, February.
- Xiao, Zengqi & Lam, Jasmine Siu Lee, 2020. "The impact of institutional conditions on willingness to take contractual risk in port public-private partnerships of developing countries," Transportation Research Part A: Policy and Practice, Elsevier, vol. 133(C), pages 12-26.
- Wajiha Ansari & Muhammad Asim & Salman Manzoor, 2020. "A systematic frame work of schedule risk management for power grid engineering projects,sustainable development," Technium Social Sciences Journal, Technium Science, vol. 5(1), pages 185-216, March.
- Usama Issa & Ibrahim Sharaky & Mamdooh Alwetaishi & Ashraf Balabel & Amal Shamseldin & Ahmed Abdelhafiz & Mohammed Al-Surf & Mosleh Al-Harthi & Medhat M. A. Osman, 2021. "Developing and Applying a Model for Evaluating Risks Affecting Greening Existing Buildings," Sustainability, MDPI, vol. 13(11), pages 1-21, June.
- Ning Wang & Cheng-shun Xu & Xiu-li Du & Ming-ju Zhang, 2018. "A risk assessment method of deep excavation based on Bayesian analysis and expert elicitation," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 9(2), pages 452-466, April.
- Hasan Mahmoud & Vian Ahmed & Salwa Beheiry, 2021. "Construction Cash Flow Risk Index," JRFM, MDPI, vol. 14(6), pages 1-17, June.
- Seyed Morteza Hatefi & Mohammad Ehsan Basiri & Jolanta Tamošaitienė, 2019. "An Evidential Model for Environmental Risk Assessment in Projects Using Dempster–Shafer Theory of Evidence," Sustainability, MDPI, vol. 11(22), pages 1-16, November.
- Gu, Shuang & Li, Keping & Feng, Tao & Yan, Dongyang & Liu, Yanyan, 2022. "The prediction of potential risk path in railway traffic events," Reliability Engineering and System Safety, Elsevier, vol. 222(C).
More about this item
Keywords
road infrastructure; Sugeno fuzzy logic; Extension of Time (EoT); Increasing Contract Price (ICP); risk management;All these keywords.
Statistics
Access and download statisticsCorrections
All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jmathe:v:12:y:2024:i:18:p:2852-:d:1477839. See general information about how to correct material in RePEc.
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.
For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .
Please note that corrections may take a couple of weeks to filter through the various RePEc services.