An Empirical Study of Delays in Large Engineering Projects: An Indian Experience

Author

Listed:
  • R. Jayaraman

Abstract

This article analyzes factors responsible for delays in two large projects undertaken by an Indian organization over a period of 7 years. The research work critically examines the reasons for delays using questionnaires in four core areas of project work. An in depth analysis has identified 10 factors, which cause delays, viz., inept project planning practices, inadequate and inexperienced consultant personnel, recurring stakeholders interactions, incomplete understanding of the client’s requirements, unfamiliarity with documentation needs in the client country, subsequent client and inspection agency-driven change requirements, incomplete preparation at the hook-up yard, and delays in vendor mobilization/inadequate vendor expertise. The original contribution of this research is in the areas of analyzing and understanding delays due to doing work in offshore locations, doing project management work using documents in offshore country language, understanding offshore country laws and regulations, in-depth understanding of the root causes of delays using detailed, segmented questionnaires and analysis of the sequential nature of project management work.

Suggested Citation

  • R. Jayaraman, 2021. "An Empirical Study of Delays in Large Engineering Projects: An Indian Experience," Jindal Journal of Business Research, , vol. 10(1), pages 49-76, June.
  • Handle: RePEc:sae:jjlobr:v:10:y:2021:i:1:p:49-76
    DOI: 10.1177/22786821211000222
    as

    Download full text from publisher

    File URL: https://journals.sagepub.com/doi/10.1177/22786821211000222
    Download Restriction: no

    File URL: https://libkey.io/10.1177/22786821211000222?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Kamath, Amit & Jayaraman, R, 2013. "CONQUAS Systems Standard for High Quality Project Management," MPRA Paper 48767, University Library of Munich, Germany, revised 2013.
    2. Arshi Shakeel Faridi & Sameh Monir El-Sayegh, 2006. "Significant factors causing delay in the UAE construction industry," Construction Management and Economics, Taylor & Francis Journals, vol. 24(11), pages 1167-1176.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Ajayi Babatunde Oluwaseun & Chinda Thanwadee, 2022. "Dynamics of Pertinent Project Delay Variables in the Thai Construction Sector: Mathematical Analysis," Engineering Management in Production and Services, Sciendo, vol. 14(2), pages 26-45, June.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2018. "Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project," Sustainability, MDPI, vol. 10(12), pages 1-18, December.
    2. Yazan Issa Abu Aisheh, 2021. "Lessons Learned, Barriers, and Improvement Factors for Mega Building Construction Projects in Developing Countries: Review Study," Sustainability, MDPI, vol. 13(19), pages 1-17, September.
    3. Achintya Ghatak & Adarsh Garg, 2022. "Power transmission project: a framework to align project success with organization goal," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 13(4), pages 1817-1833, August.
    4. Antonio Héctor Álvarez-Pozo & Miguel Ignacio Parma-García & Isabel Ortiz-Marcos & Luis Fernando Bautista & Evangelina Atanes-Sánchez, 2024. "Analysis of Causes of Delays and Cost Overruns as Well as Mitigation Measures to Improve Profitability and Sustainability in Turnkey Industrial Projects," Sustainability, MDPI, vol. 16(4), pages 1-16, February.
    5. Deena Badran & Radhi AlZubaidi & Senthilkumar Venkatachalam, 2023. "Identification of Key Design Phase-Related Risks in DBB Projects in the UAE—Towards Developing a BIM Solution," Sustainability, MDPI, vol. 15(8), pages 1-23, April.
    6. Dr. Mwenda, Mary Nyawira & Dr. Otieno- Omutoko Lillian & Prof. Christopher Gakuu, 2021. "The Nexus between Project Monitoring and Evaluation and Quality of Residential Buildings in Nairobi County, Kenya," International Journal of Research and Innovation in Social Science, International Journal of Research and Innovation in Social Science (IJRISS), vol. 5(1), pages 354-362, January.
    7. Ihsan Issa Ahmad Hosani & Fikri T. Dweiri & Udechukwu Ojiako, 0. "A study of cost overruns in complex multi-stakeholder road projects in the United Arab Emirates," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 0, pages 1-10.
    8. Hongtao Xie & Junwei Zheng & Yunhua Zhang & Hongyang Li, 2019. "Effects of Payment Delays at Two Links in Payment Chains on the Progress of Construction Projects: System Dynamic Modeling and Simulation," Sustainability, MDPI, vol. 11(15), pages 1-25, July.
    9. Chen Wang & Yutong Tang & Mukhtar A. Kassem & Hong Yeow Ong & Jeffrey Boon Hui Yap & Kherun Nita Ali, 2022. "Novel Quality-Embedded Earned Value Performance Analysis Tool for Sustainable Project Portfolio Production," Sustainability, MDPI, vol. 14(13), pages 1-28, July.
    10. Hussain, Shahid & Xuetong, Wang & Maqbool, Rashid & Hussain, Mustansar & Shahnawaz, Muhammad, 2022. "The influence of government support, organizational innovativeness and community participation in renewable energy project success: A case of Pakistan," Energy, Elsevier, vol. 239(PC).
    11. Goutom K. Pall & Adrian J. Bridge & Jason Gray & Martin Skitmore, 2019. "Causes of Delay in Power Transmission Projects: An Empirical Study," Energies, MDPI, vol. 13(1), pages 1-29, December.
    12. Ihsan Issa Ahmad Hosani & Fikri T. Dweiri & Udechukwu Ojiako, 2020. "A study of cost overruns in complex multi-stakeholder road projects in the United Arab Emirates," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 11(6), pages 1250-1259, December.
    13. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2019. "Materials Challenges in Reconstruction of Historical Projects: A Case Study of the Old Riwaq Project," Sustainability, MDPI, vol. 11(17), pages 1-19, August.
    14. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2020. "Delay Factors Management and Ranking for Reconstruction and Rehabilitation Projects Based on the Relative Importance Index (RII)," Sustainability, MDPI, vol. 12(15), pages 1-21, July.
    15. Faham Tahmasebinia & Vicheth Song, 2022. "Significant Factors Causing Delay in the Cambodian Construction Industry," Sustainability, MDPI, vol. 14(6), pages 1-24, March.
    16. Hemanta Doloi & Anil Sawhney & K.C. Iyer, 2012. "Structural equation model for investigating factors affecting delay in Indian construction projects," Construction Management and Economics, Taylor & Francis Journals, vol. 30(10), pages 869-884, October.
    17. Murat Gunduz & Hamza M. A. Lutfi, 2021. "Go/No-Go Decision Model for Owners Using Exhaustive CHAID and QUEST Decision Tree Algorithms," Sustainability, MDPI, vol. 13(2), pages 1-24, January.
    18. Md. Mohaimenul Islam Sourav & Mohammed Russedul Islam & H M Imran Kays & Md. Hadiuzzaman, 2022. "A Structural Equation Modeling Approach to Understand User's Perceptions of Acceptance of Ride-Sharing Services in Dhaka City," Papers 2210.04086, arXiv.org, revised Jun 2023.
    19. Shahid Hussain & Fangwei Zhu & Zaigham Ali & Xiaohang Xu, 2017. "Rural Residents’ Perception of Construction Project Delays in Pakistan," Sustainability, MDPI, vol. 9(11), pages 1-16, November.
    20. Lerche, J. & Lorentzen, S. & Enevoldsen, P. & Neve, H.H., 2022. "The impact of COVID -19 on offshore wind project productivity – A case study," Renewable and Sustainable Energy Reviews, Elsevier, vol. 158(C).

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:sae:jjlobr:v:10:y:2021:i:1:p:49-76. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: SAGE Publications (email available below). General contact details of provider: .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.