Structural equation model for investigating factors affecting delay in Indian construction projects

Author

Listed:
  • Hemanta Doloi
  • Anil Sawhney
  • K.C. Iyer

Abstract

The rapid growth of the Indian construction sector over the last few decades and recurring failure in on-time delivery highlight the need for a systematic analysis of the factors influencing delay. A theoretical structural equation model representing the influence of four key latent variables on project delays in the Indian construction industry has been developed. Data collected from a questionnaire survey and personal interviews, with 77 valid responses from clients, contractors and designers or architects, were used to further formulate and analyse the model. The results of the structural equation model suggest that client’s influence is one of the most significant factors affecting time performance on Indian projects. Client’s influence is also found to be one of the key contributing factors resulting in lack of commitment and contractor’s inefficiency in the project. Lack of efficient construction planning plays the second key role in adverse time performance. While the effect of lack of commitment on contractor’s inefficiency is highly significant, neither of these two factors has any direct impact on time delay in projects. Contrary to the notion that the contractor is the only party responsible for delay in construction projects, the results clearly highlight the importance of the role of clients and technical expertise in planning in achieving satisfactory time performance on Indian projects. It is hoped that these research findings will contribute significantly to the Indian construction industry’s efforts in addressing the root causes of delay and enhancing the time performance on projects.

Suggested Citation

  • Hemanta Doloi & Anil Sawhney & K.C. Iyer, 2012. "Structural equation model for investigating factors affecting delay in Indian construction projects," Construction Management and Economics, Taylor & Francis Journals, vol. 30(10), pages 869-884, October.
  • Handle: RePEc:taf:conmgt:v:30:y:2012:i:10:p:869-884
    DOI: 10.1080/01446193.2012.717705
    as

    Download full text from publisher

    File URL: http://hdl.handle.net/10.1080/01446193.2012.717705
    Download Restriction: Access to full text is restricted to subscribers.

    File URL: https://libkey.io/10.1080/01446193.2012.717705?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. TENENHAUS, Michel, 2008. "Component-based structural equation modelling," HEC Research Papers Series 887, HEC Paris.
    2. Michel Tenenhaus, 2008. "Component-based Structural Equation Modelling," Working Papers hal-00580149, HAL.
    3. Xiao-Hua Jin & Hemanta Doloi & Shi-Yun Gao, 2007. "Relationship-based determinants of building project performance in China," Construction Management and Economics, Taylor & Francis Journals, vol. 25(3), pages 297-304.
    4. Adel Al-Kharashi & Martin Skitmore, 2009. "Causes of delays in Saudi Arabian public sector construction projects," Construction Management and Economics, Taylor & Francis Journals, vol. 27(1), pages 3-23.
    5. Kumar Neeraj Jha & Sudhir Misra, 2007. "Ranking and classification of construction coordination activities in Indian projects," Construction Management and Economics, Taylor & Francis Journals, vol. 25(4), pages 409-421.
    6. Per Erik Eriksson & Ossi Pesamaa, 2007. "Modelling procurement effects on cooperation," Construction Management and Economics, Taylor & Francis Journals, vol. 25(8), pages 893-901.
    7. Yakubu Adisa Olawale & Ming Sun, 2010. "Cost and time control of construction projects: inhibiting factors and mitigating measures in practice," Construction Management and Economics, Taylor & Francis Journals, vol. 28(5), pages 509-526.
    8. Mohan Kumaraswamy & Daniel Chan, 1998. "Contributors to construction delays," Construction Management and Economics, Taylor & Francis Journals, vol. 16(1), pages 17-29.
    9. Arshi Shakeel Faridi & Sameh Monir El-Sayegh, 2006. "Significant factors causing delay in the UAE construction industry," Construction Management and Economics, Taylor & Francis Journals, vol. 24(11), pages 1167-1176.
    10. Hemanta Doloi, 2009. "Relational partnerships: the importance of communication, trust and confidence and joint risk management in achieving project success," Construction Management and Economics, Taylor & Francis Journals, vol. 27(11), pages 1099-1109.
    11. M. D. Mainul Islam & Olusegun Faniran, 2005. "Structural equation model of project planning effectiveness," Construction Management and Economics, Taylor & Francis Journals, vol. 23(2), pages 215-223.
    12. Hemanta Doloi, 2009. "Analysis of pre-qualification criteria in contractor selection and their impacts on project success," Construction Management and Economics, Taylor & Francis Journals, vol. 27(12), pages 1245-1263.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Md. Mohaimenul Islam Sourav & Mohammed Russedul Islam & H M Imran Kays & Md. Hadiuzzaman, 2022. "A Structural Equation Modeling Approach to Understand User's Perceptions of Acceptance of Ride-Sharing Services in Dhaka City," Papers 2210.04086, arXiv.org, revised Jun 2023.
    2. Muhammad Irfan & Sanam Zaib Khan & Nasruddin Hassan & Mazlan Hassan & Muhammad Habib & Salma Khan & Hadi Hassan Khan, 2021. "Role of Project Planning and Project Manager Competencies on Public Sector Project Success," Sustainability, MDPI, vol. 13(3), pages 1-19, January.
    3. Tirataci Hakan & Yaman Hakan, 2023. "Estimation of ideal construction duration in tender preparation stage for housing projects," Organization, Technology and Management in Construction, Sciendo, vol. 15(1), pages 192-212, January.
    4. Akriti Gupta & Aman Chadha & Vijayshri Tiwari & Arup Varma & Vijay Pereira, 2023. "Sustainable training practices: predicting job satisfaction and employee behavior using machine learning techniques," Asian Business & Management, Palgrave Macmillan, vol. 22(5), pages 1913-1936, November.
    5. Mohammad Ajmal Nikjow & Li Liang & Xijing Qi & Samad M. E. Sepasgozar & Nicholas Chileshe, 2021. "Triggers of Delays in International Projects Using Engineering Procurement and Construction Delivery Methods in the Belt and Road Initiative: Case Study of a High-Speed Railway Projects," Sustainability, MDPI, vol. 13(17), pages 1-21, August.
    6. Goutom K. Pall & Adrian J. Bridge & Jason Gray & Martin Skitmore, 2019. "Causes of Delay in Power Transmission Projects: An Empirical Study," Energies, MDPI, vol. 13(1), pages 1-29, December.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Goutom K. Pall & Adrian J. Bridge & Jason Gray & Martin Skitmore, 2019. "Causes of Delay in Power Transmission Projects: An Empirical Study," Energies, MDPI, vol. 13(1), pages 1-29, December.
    2. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2018. "Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project," Sustainability, MDPI, vol. 10(12), pages 1-18, December.
    3. A. Q. Adeleke & A. Y. Bahaudin & A. M. Kamaruddeen, 2018. "Organizational Internal Factors and Construction Risk Management among Nigerian Construction Companies," Global Business Review, International Management Institute, vol. 19(4), pages 921-938, August.
    4. Gyeongcheol Cho & Heungsun Hwang & Marko Sarstedt & Christian M. Ringle, 2020. "Cutoff criteria for overall model fit indexes in generalized structured component analysis," Journal of Marketing Analytics, Palgrave Macmillan, vol. 8(4), pages 189-202, December.
    5. Yazan Issa Abu Aisheh, 2021. "Lessons Learned, Barriers, and Improvement Factors for Mega Building Construction Projects in Developing Countries: Review Study," Sustainability, MDPI, vol. 13(19), pages 1-17, September.
    6. Alam, Mohammad Zahedul & Hu, Wang & Kaium, Md Abdul & Hoque, Md Rakibul & Alam, Mirza Mohammad Didarul, 2020. "Understanding the determinants of mHealth apps adoption in Bangladesh: A SEM-Neural network approach," Technology in Society, Elsevier, vol. 61(C).
    7. Achintya Ghatak & Adarsh Garg, 2022. "Power transmission project: a framework to align project success with organization goal," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 13(4), pages 1817-1833, August.
    8. Basco, Rodrigo & Hair, Joseph F. & Ringle, Christian M. & Sarstedt, Marko, 2022. "Advancing family business research through modeling nonlinear relationships: Comparing PLS-SEM and multiple regression," Journal of Family Business Strategy, Elsevier, vol. 13(3).
    9. Rainer Schlittgen, 2018. "Estimation of generalized structured component analysis models with alternating least squares," Computational Statistics, Springer, vol. 33(1), pages 527-548, March.
    10. Arif ÇETİN & Salih GÜNEY, 2019. "İBB Spor İstanbul’da Çalışanların Örgütsel Adalet ve Örgütsel Güven Algılarının Örgütsel Bağlılık Davranışı Üzerindeki Etkisi ve Buna Yönelik Bir Uygulama," Istanbul Management Journal, Istanbul University Business School, vol. 0(87), pages 93-109, June.
    11. Gyeongcheol Cho & Christopher Schlaegel & Heungsun Hwang & Younyoung Choi & Marko Sarstedt & Christian M. Ringle, 2022. "Integrated Generalized Structured Component Analysis: On the Use of Model Fit Criteria in International Management Research," Management International Review, Springer, vol. 62(4), pages 569-609, August.
    12. Heungsun Hwang & Gyeongcheol Cho, 2020. "Global Least Squares Path Modeling: A Full-Information Alternative to Partial Least Squares Path Modeling," Psychometrika, Springer;The Psychometric Society, vol. 85(4), pages 947-972, December.
    13. Florian Schuberth & Jörg Henseler & Theo K. Dijkstra, 2018. "Partial least squares path modeling using ordinal categorical indicators," Quality & Quantity: International Journal of Methodology, Springer, vol. 52(1), pages 9-35, January.
    14. A. R. Abdul-Aziz & Albert Luguterah & Bashiru I. I. Saeed, 2021. "Comparative Performance of Estimation Maximization Among Residual Estimators: A Structural Equation Modelling Perspective," International Journal of Statistics and Probability, Canadian Center of Science and Education, vol. 10(2), pages 138-138, March.
    15. Sener, Abdurrezzak & Barut, Mehmet & Oztekin, Asil & Avcilar, Mutlu Yuksel & Yildirim, Mehmet Bayram, 2019. "The role of information usage in a retail supply chain: A causal data mining and analytical modeling approach," Journal of Business Research, Elsevier, vol. 99(C), pages 87-104.
    16. Michel Tenenhaus & Arthur Tenenhaus & Patrick J. F. Groenen, 2017. "Regularized Generalized Canonical Correlation Analysis: A Framework for Sequential Multiblock Component Methods," Psychometrika, Springer;The Psychometric Society, vol. 82(3), pages 737-777, September.
    17. Joseph F. Hair & G. Tomas M. Hult & Christian M. Ringle & Marko Sarstedt & Kai Oliver Thiele, 2017. "Mirror, mirror on the wall: a comparative evaluation of composite-based structural equation modeling methods," Journal of the Academy of Marketing Science, Springer, vol. 45(5), pages 616-632, September.
    18. Arthur Tenenhaus & Michel Tenenhaus, 2011. "Regularized Generalized Canonical Correlation Analysis," Psychometrika, Springer;The Psychometric Society, vol. 76(2), pages 257-284, April.
    19. Karin Schermelleh-Engel & Christina Werner & Andreas Klein & Helfried Moosbrugger, 2010. "Nonlinear structural equation modeling: is partial least squares an alternative?," AStA Advances in Statistical Analysis, Springer;German Statistical Society, vol. 94(2), pages 167-184, June.
    20. Giuliano Marella & Valentina Antoniucci, 2019. "Time Overrun in Public Works—Evidence from North-East Italy," Sustainability, MDPI, vol. 11(24), pages 1-17, December.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:taf:conmgt:v:30:y:2012:i:10:p:869-884. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Longhurst (email available below). General contact details of provider: http://www.tandfonline.com/RCME20 .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.