Development of a Predictive Model Based on the Alignment Tool in the Early Stages of Projects: The Case of Saudi Arabia Infrastructure Projects

Author

Listed:
  • Abdulrahman Bin Mahmoud

    (Civil Engineering Department, King Saud University, P.O. Box 800, Riyadh 11421, Saudi Arabia)

  • Abdullah Alrashdi

    (Civil Engineering Department, King Saud University, P.O. Box 800, Riyadh 11421, Saudi Arabia)

  • Salman Akhtar

    (Civil Engineering Department, King Saud University, P.O. Box 800, Riyadh 11421, Saudi Arabia)

  • Ayman Altuwaim

    (Civil Engineering Department, King Saud University, P.O. Box 800, Riyadh 11421, Saudi Arabia)

  • Abdulmohsen Almohsen

    (Civil Engineering Department, King Saud University, P.O. Box 800, Riyadh 11421, Saudi Arabia)

Abstract

The construction industry plays a substantial role in shaping the economies of many countries. Construction management faces various challenges that can lead to project failures, particularly in infrastructure projects struggling to meet cost and time requirements. Inadequate project planning and the intricate nature of construction projects can cause participants’ project goals to not align. It is crucial to address these challenges early in the planning stages to ensure project success. This research involved investigating previous studies to understand current practices for improving infrastructure project planning and selecting the best pre-project planning tool. Infrastructure projects in the Saudi construction industry are used as a case study. A questionnaire was prepared based on essential alignment issues affecting team alignment during pre-project planning. Participants rated the level of agreement with alignment issues and the overall success of a project they worked on. The study utilized descriptive and inferential analysis techniques to assess infrastructure project success rates and develop a predictive model driven by the alignment tool. Multiple linear regression techniques were used during the model’s development, and validation and reliability outputs were obtained. By evaluating all relevant stakeholders, the model generates a score to facilitate the pre-project planning process, increasing the likelihood of project success. The study found that the model’s predictive accuracy was 94%. This research is significant in creating a predictive model applicable to infrastructure projects, enhancing project management practices by enabling project teams to evaluate project progress, identify projects in need of corrective action, and ultimately improve project performance, leading to cost and time savings.

Suggested Citation

  • Abdulrahman Bin Mahmoud & Abdullah Alrashdi & Salman Akhtar & Ayman Altuwaim & Abdulmohsen Almohsen, 2024. "Development of a Predictive Model Based on the Alignment Tool in the Early Stages of Projects: The Case of Saudi Arabia Infrastructure Projects," Sustainability, MDPI, vol. 16(18), pages 1-18, September.
  • Handle: RePEc:gam:jsusta:v:16:y:2024:i:18:p:8122-:d:1479941
    as

    Download full text from publisher

    File URL: https://www.mdpi.com/2071-1050/16/18/8122/pdf
    Download Restriction: no

    File URL: https://www.mdpi.com/2071-1050/16/18/8122/
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Arshi Shakeel Faridi & Sameh Monir El-Sayegh, 2006. "Significant factors causing delay in the UAE construction industry," Construction Management and Economics, Taylor & Francis Journals, vol. 24(11), pages 1167-1176.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2018. "Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project," Sustainability, MDPI, vol. 10(12), pages 1-18, December.
    2. R. Jayaraman, 2021. "An Empirical Study of Delays in Large Engineering Projects: An Indian Experience," Jindal Journal of Business Research, , vol. 10(1), pages 49-76, June.
    3. Yazan Issa Abu Aisheh, 2021. "Lessons Learned, Barriers, and Improvement Factors for Mega Building Construction Projects in Developing Countries: Review Study," Sustainability, MDPI, vol. 13(19), pages 1-17, September.
    4. Achintya Ghatak & Adarsh Garg, 2022. "Power transmission project: a framework to align project success with organization goal," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 13(4), pages 1817-1833, August.
    5. Antonio Héctor Álvarez-Pozo & Miguel Ignacio Parma-García & Isabel Ortiz-Marcos & Luis Fernando Bautista & Evangelina Atanes-Sánchez, 2024. "Analysis of Causes of Delays and Cost Overruns as Well as Mitigation Measures to Improve Profitability and Sustainability in Turnkey Industrial Projects," Sustainability, MDPI, vol. 16(4), pages 1-16, February.
    6. Deena Badran & Radhi AlZubaidi & Senthilkumar Venkatachalam, 2023. "Identification of Key Design Phase-Related Risks in DBB Projects in the UAE—Towards Developing a BIM Solution," Sustainability, MDPI, vol. 15(8), pages 1-23, April.
    7. Dr. Mwenda, Mary Nyawira & Dr. Otieno- Omutoko Lillian & Prof. Christopher Gakuu, 2021. "The Nexus between Project Monitoring and Evaluation and Quality of Residential Buildings in Nairobi County, Kenya," International Journal of Research and Innovation in Social Science, International Journal of Research and Innovation in Social Science (IJRISS), vol. 5(1), pages 354-362, January.
    8. Ihsan Issa Ahmad Hosani & Fikri T. Dweiri & Udechukwu Ojiako, 0. "A study of cost overruns in complex multi-stakeholder road projects in the United Arab Emirates," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 0, pages 1-10.
    9. Hongtao Xie & Junwei Zheng & Yunhua Zhang & Hongyang Li, 2019. "Effects of Payment Delays at Two Links in Payment Chains on the Progress of Construction Projects: System Dynamic Modeling and Simulation," Sustainability, MDPI, vol. 11(15), pages 1-25, July.
    10. Hussain, Shahid & Xuetong, Wang & Maqbool, Rashid & Hussain, Mustansar & Shahnawaz, Muhammad, 2022. "The influence of government support, organizational innovativeness and community participation in renewable energy project success: A case of Pakistan," Energy, Elsevier, vol. 239(PC).
    11. Goutom K. Pall & Adrian J. Bridge & Jason Gray & Martin Skitmore, 2019. "Causes of Delay in Power Transmission Projects: An Empirical Study," Energies, MDPI, vol. 13(1), pages 1-29, December.
    12. Ihsan Issa Ahmad Hosani & Fikri T. Dweiri & Udechukwu Ojiako, 2020. "A study of cost overruns in complex multi-stakeholder road projects in the United Arab Emirates," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 11(6), pages 1250-1259, December.
    13. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2019. "Materials Challenges in Reconstruction of Historical Projects: A Case Study of the Old Riwaq Project," Sustainability, MDPI, vol. 11(17), pages 1-19, August.
    14. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2020. "Delay Factors Management and Ranking for Reconstruction and Rehabilitation Projects Based on the Relative Importance Index (RII)," Sustainability, MDPI, vol. 12(15), pages 1-21, July.
    15. Faham Tahmasebinia & Vicheth Song, 2022. "Significant Factors Causing Delay in the Cambodian Construction Industry," Sustainability, MDPI, vol. 14(6), pages 1-24, March.
    16. Hemanta Doloi & Anil Sawhney & K.C. Iyer, 2012. "Structural equation model for investigating factors affecting delay in Indian construction projects," Construction Management and Economics, Taylor & Francis Journals, vol. 30(10), pages 869-884, October.
    17. Murat Gunduz & Hamza M. A. Lutfi, 2021. "Go/No-Go Decision Model for Owners Using Exhaustive CHAID and QUEST Decision Tree Algorithms," Sustainability, MDPI, vol. 13(2), pages 1-24, January.
    18. Md. Mohaimenul Islam Sourav & Mohammed Russedul Islam & H M Imran Kays & Md. Hadiuzzaman, 2022. "A Structural Equation Modeling Approach to Understand User's Perceptions of Acceptance of Ride-Sharing Services in Dhaka City," Papers 2210.04086, arXiv.org, revised Jun 2023.
    19. Shahid Hussain & Fangwei Zhu & Zaigham Ali & Xiaohang Xu, 2017. "Rural Residents’ Perception of Construction Project Delays in Pakistan," Sustainability, MDPI, vol. 9(11), pages 1-16, November.
    20. Lerche, J. & Lorentzen, S. & Enevoldsen, P. & Neve, H.H., 2022. "The impact of COVID -19 on offshore wind project productivity – A case study," Renewable and Sustainable Energy Reviews, Elsevier, vol. 158(C).

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jsusta:v:16:y:2024:i:18:p:8122-:d:1479941. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.