A New Model for Solving Time-Cost-Quality Trade-Off Problems in Construction

Author

Listed:
  • Fang Fu
  • Tao Zhang

Abstract

A poor quality affects project makespan and its total costs negatively, but it can be recovered by repair works during construction. We construct a new non-linear programming model based on the classic multi-mode resource constrained project scheduling problem considering repair works. In order to obtain satisfactory quality without a high increase of project cost, the objective is to minimize total quality cost which consists of the prevention cost and failure cost according to Quality-Cost Analysis. A binary dependent normal distribution function is adopted to describe the activity quality; Cumulative quality is defined to determine whether to initiate repair works, according to the different relationships among activity qualities, namely, the coordinative and precedence relationship. Furthermore, a shuffled frog-leaping algorithm is developed to solve this discrete trade-off problem based on an adaptive serial schedule generation scheme and adjusted activity list. In the program of the algorithm, the frog-leaping progress combines the crossover operator of genetic algorithm and a permutation-based local search. Finally, an example of a construction project for a framed railway overpass is provided to examine the algorithm performance, and it assist in decision making to search for the appropriate makespan and quality threshold with minimal cost.

Suggested Citation

  • Fang Fu & Tao Zhang, 2016. "A New Model for Solving Time-Cost-Quality Trade-Off Problems in Construction," PLOS ONE, Public Library of Science, vol. 11(12), pages 1-15, December.
  • Handle: RePEc:plo:pone00:0167142
    DOI: 10.1371/journal.pone.0167142
    as

    Download full text from publisher

    File URL: https://journals.plos.org/plosone/article?id=10.1371/journal.pone.0167142
    Download Restriction: no

    File URL: https://journals.plos.org/plosone/article/file?id=10.1371/journal.pone.0167142&type=printable
    Download Restriction: no

    File URL: https://libkey.io/10.1371/journal.pone.0167142?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Hong Zhang & Heng Li, 2010. "Multi-objective particle swarm optimization for construction time-cost tradeoff problems," Construction Management and Economics, Taylor & Francis Journals, vol. 28(1), pages 75-88.
    2. Azadeh, A. & Maleki Shoja, B. & Ghanei, S. & Sheikhalishahi, M., 2015. "A multi-objective optimization problem for multi-state series-parallel systems: A two-stage flow-shop manufacturing system," Reliability Engineering and System Safety, Elsevier, vol. 136(C), pages 62-74.
    3. Tiwari, Vikram & Patterson, James H. & Mabert, Vincent A., 2009. "Scheduling projects with heterogeneous resources to meet time and quality objectives," European Journal of Operational Research, Elsevier, vol. 193(3), pages 780-790, March.
    4. Babu, A. J. G. & Suresh, Nalina, 1996. "Project management with time, cost, and quality considerations," European Journal of Operational Research, Elsevier, vol. 88(2), pages 320-327, January.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Hazır, Öncü & Ulusoy, Gündüz, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," International Journal of Production Economics, Elsevier, vol. 223(C).
    2. Kosztyán, Zsolt T. & Pribojszki-Németh, Anikó & Szalkai, István, 2019. "Hybrid multimode resource-constrained maintenance project scheduling problem," Operations Research Perspectives, Elsevier, vol. 6(C).
    3. Öncü Hazir & Gündüz Ulusoy, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," Post-Print hal-02898162, HAL.
    4. Mehrnoosh Zohrehvandi & Shakib Zohrehvandi & Mohammad Khalilzadeh & Maghsoud Amiri & Fariborz Jolai & Edmundas Kazimieras Zavadskas & Jurgita Antucheviciene, 2024. "A Multi-Objective Mathematical Programming Model for Project-Scheduling Optimization Considering Customer Satisfaction in Construction Projects," Mathematics, MDPI, vol. 12(2), pages 1-16, January.
    5. Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
    6. Paraskevopoulos, Dimitris C. & Laporte, Gilbert & Repoussis, Panagiotis P. & Tarantilis, Christos D., 2017. "Resource constrained routing and scheduling: Review and research prospects," European Journal of Operational Research, Elsevier, vol. 263(3), pages 737-754.
    7. Jeunet, Jully & Bou Orm, Mayassa, 2020. "Optimizing temporary work and overtime in the Time Cost Quality Trade-off Problem," European Journal of Operational Research, Elsevier, vol. 284(2), pages 743-761.
    8. Jin, Maozhu & Song, Lijun & Wang, Yanan & Zeng, Yucheng, 2018. "Longitudinal cooperative robust optimization model for sustainable supply chain management," Chaos, Solitons & Fractals, Elsevier, vol. 116(C), pages 95-105.
    9. De Bruecker, Philippe & Beliën, Jeroen & Van den Bergh, Jorne & Demeulemeester, Erik, 2018. "A three-stage mixed integer programming approach for optimizing the skill mix and training schedules for aircraft maintenance," European Journal of Operational Research, Elsevier, vol. 267(2), pages 439-452.
    10. Kayedpour, Farjam & Amiri, Maghsoud & Rafizadeh, Mahmoud & Shahryari Nia, Arash, 2017. "Multi-objective redundancy allocation problem for a system with repairable components considering instantaneous availability and strategy selection," Reliability Engineering and System Safety, Elsevier, vol. 160(C), pages 11-20.
    11. C-C Chang & R-S Chen, 2007. "Project advancement and its applications to multi-air-route quality budget allocation," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 58(8), pages 1008-1020, August.
    12. Hua Wang & Jon Dieringer & Steve Guntz & Shankarraman Vaidyaraman & Shekhar Viswanath & Nikolaos H. Lappas & Sal Garcia-Munoz & Chrysanthos E. Gounaris, 2021. "Portfolio-Wide Optimization of Pharmaceutical R&D Activities Using Mathematical Programming," Interfaces, INFORMS, vol. 51(4), pages 262-279, July.
    13. Choi, Yunsik & Delise, Lisa A. & Lee, Brandon W. & Neely, Jerry, 2021. "Effective staffing of projects for reconciling conflict between cost efficiency and quality," International Journal of Production Economics, Elsevier, vol. 234(C).
    14. Qingfeng Meng & Zhen Li & Jianguo Du & Huimin Liu & Xiang Ding, 2019. "Negotiation for Time Optimization in Construction Projects with Competitive and Social Welfare Preferences," Complexity, Hindawi, vol. 2019, pages 1-13, January.
    15. Zhao, Jiangbin & Si, Shubin & Cai, Zhiqiang, 2019. "A multi-objective reliability optimization for reconfigurable systems considering components degradation," Reliability Engineering and System Safety, Elsevier, vol. 183(C), pages 104-115.
    16. Zsolt T. Kosztyán & István Szalkai, 2020. "Multimode resource-constrained project scheduling in flexible projects," Journal of Global Optimization, Springer, vol. 76(1), pages 211-241, January.
    17. Kerkhove, L.P. & Vanhoucke, M., 2016. "Incentive contract design for projects: The owner׳s perspective," Omega, Elsevier, vol. 62(C), pages 93-114.
    18. Che, Haiyang & Zeng, Shengkui & Guo, Jianbin, 2019. "Reliability assessment of man-machine systems subject to mutually dependent machine degradation and human errors," Reliability Engineering and System Safety, Elsevier, vol. 190(C), pages 1-1.
    19. Hartmann, Sönke & Briskorn, Dirk, 2008. "A survey of variants and extensions of the resource-constrained project scheduling problem," Working Paper Series 02/2008, Hamburg School of Business Administration (HSBA).
    20. Luise-Sophie Hoffmann & Carolin Kellenbrink & Stefan Helber, 2020. "Simultaneous structuring and scheduling of multiple projects with flexible project structures," Journal of Business Economics, Springer, vol. 90(5), pages 679-711, June.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:plo:pone00:0167142. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: plosone (email available below). General contact details of provider: https://journals.plos.org/plosone/ .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.