IDEAS home Printed from https://ideas.repec.org/a/gam/jsusta/v11y2019i5p1256-d209464.html
   My bibliography  Save this article

A Forecast and Mitigation Model of Construction Performance by Assessing Detailed Engineering Maturity at Key Milestones for Offshore EPC Mega-Projects

Author

Listed:
  • Myung-Hun Kim

    (Graduate Institute of Ferrous Technology (GIFT), Pohang University of Science and Technology (POSTECH), 77 Cheongam-Ro, Nam-Ku, Pohang 37673, Korea
    Hyundai Heavy Industries (HHI), Engineering Management Team, 400 Bangeojinsunhwan-doro, Dong-gu, Ulsan 44114, Korea)

  • Eul-Bum Lee

    (Graduate Institute of Ferrous Technology (GIFT), Pohang University of Science and Technology (POSTECH), 77 Cheongam-Ro, Nam-Ku, Pohang 37673, Korea
    Department of Industrial and Management Engineering, Pohang University of Science and Technology (POSTECH), 77 Cheongam-Ro, Nam-Ku, Pohang 37673, Korea)

  • Han-Suk Choi

    (Graduate Institute of Ferrous Technology (GIFT), Pohang University of Science and Technology (POSTECH), 77 Cheongam-Ro, Nam-Ku, Pohang 37673, Korea)

Abstract

The main subject of this research is to develop a forecast and mitigation model of schedule and cost performance during a detailed engineering stage of offshore engineering, procurement and construction (EPC) projects. The weight factors of major elements in detailed engineering completion rating index system (DECRIS) were measured using a fuzzy inference system (FIS) and an analytic hierarchy process (AHP). At five key engineering milestones, from an EPC contract being awarded to the start of construction, detailed engineering maturities were assessed in fourteen historical offshore EPC projects using the DECRIS model. DECRIS cutoff scores for successful project execution were defined at the key engineering milestones. A schedule and cost performance was forecasted and validated through comparison of DECRIS and other models using statistical confidence of a fuzzy set qualitative comparative analysis (fsQCA) and a regression analysis. As a mitigation method for engineering risks to EPC contractors, engineering resource enhancement is recommended for trade-off optimization of cost overrun using a Monte Carlo simulation. The main contribution of this research is that EPC contractors could continuously forecast construction costs and schedule performance utilizing the DECRIS model, and could review the adequacy of engineering resources, assessing the trade-off between said resources and cost/schedule risk mitigation.

Suggested Citation

  • Myung-Hun Kim & Eul-Bum Lee & Han-Suk Choi, 2019. "A Forecast and Mitigation Model of Construction Performance by Assessing Detailed Engineering Maturity at Key Milestones for Offshore EPC Mega-Projects," Sustainability, MDPI, vol. 11(5), pages 1-21, February.
  • Handle: RePEc:gam:jsusta:v:11:y:2019:i:5:p:1256-:d:209464
    as

    Download full text from publisher

    File URL: https://www.mdpi.com/2071-1050/11/5/1256/pdf
    Download Restriction: no

    File URL: https://www.mdpi.com/2071-1050/11/5/1256/
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Saaty, Thomas L., 2003. "Decision-making with the AHP: Why is the principal eigenvector necessary," European Journal of Operational Research, Elsevier, vol. 145(1), pages 85-91, February.
    2. Anthony Garratt & Shaun P. Vahey & Yunyi Zhang, 2019. "Real‐time forecast combinations for the oil price," Journal of Applied Econometrics, John Wiley & Sons, Ltd., vol. 34(3), pages 456-462, April.
    3. Sihem Ben Mahmoud-Jouini & Christophe Midler & Gilles Garel, 2004. "Time to market vs. Time to delivery. Managing speed in Engineering Procurement and construction projects," Post-Print hal-00657615, HAL.
    4. Yakubu Adisa Olawale & Ming Sun, 2010. "Cost and time control of construction projects: inhibiting factors and mitigating measures in practice," Construction Management and Economics, Taylor & Francis Journals, vol. 28(5), pages 509-526.
    5. Sihem Ben Mahmoud-Jouini & Gilles Garel & Christophe Midler, 2004. "Time to market vs time to delivery - Managing speed in engineering procurement and construction projects," Post-Print hal-00278162, HAL.
    6. Myung-Hun Kim & Eul-Bum Lee & Han-Suk Choi, 2018. "Detail Engineering Completion Rating Index System (DECRIS) for Optimal Initiation of Construction Works to Improve Contractors’ Schedule-Cost Performance for Offshore Oil and Gas EPC Projects," Sustainability, MDPI, vol. 10(7), pages 1-31, July.
    7. P. A. Koushki & K. Al-Rashid & N. Kartam, 2005. "Delays and cost increases in the construction of private residential projects in Kuwait," Construction Management and Economics, Taylor & Francis Journals, vol. 23(3), pages 285-294.
    8. David E. Burmaster & Paul D. Anderson, 1994. "Principles of Good Practice for the Use of Monte Carlo Techniques in Human Health and Ecological Risk Assessments," Risk Analysis, John Wiley & Sons, vol. 14(4), pages 477-481, August.
    9. Hyun-Chul Lee & Eul-Bum Lee & Douglas Alleman, 2018. "Schedule Modeling to Estimate Typical Construction Durations and Areas of Risk for 1000 MW Ultra-Critical Coal-Fired Power Plants," Energies, MDPI, vol. 11(10), pages 1-15, October.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Byung-Yun Son & Eul-Bum Lee, 2019. "Using Text Mining to Estimate Schedule Delay Risk of 13 Offshore Oil and Gas EPC Case Studies During the Bidding Process," Energies, MDPI, vol. 12(10), pages 1-25, May.
    2. Carlos Araújo-Rey & Miguel A. Sebastián, 2021. "An Approach to the Analysis of Causes of Delays in Industrial Construction Projects through Planning and Statistical Computing," Sustainability, MDPI, vol. 13(7), pages 1-21, April.
    3. Hui-Ping Tserng & I-Cheng Cho & Chun-Hung Chen & Yu-Fan Liu, 2021. "Developing a Risk Management Process for Infrastructure Projects Using IDEF0," Sustainability, MDPI, vol. 13(12), pages 1-22, June.
    4. Jesus Javier Losada-Maseda & Laura Castro-Santos & Manuel Ángel Graña-López & Ana Isabel García-Diez & Almudena Filgueira-Vizoso, 2020. "Analysis of Contracts to Build Energy Infrastructures to Optimize the OPEX," Sustainability, MDPI, vol. 12(17), pages 1-17, September.
    5. Myung-Hun Kim & Eul-Bum Lee, 2019. "A Forecast Model for the Level of Engineering Maturity Impact on Contractor’s Procurement and Construction Costs for Offshore EPC Megaprojects," Energies, MDPI, vol. 12(12), pages 1-18, June.
    6. Guangbin Wang & Huan Liu & Heng Li & Xiaochun Luo & Jiaxi Liu, 2020. "A Building Project-Based Industrialized Construction Maturity Model Involving Organizational Enablers: A Multi-Case Study in China," Sustainability, MDPI, vol. 12(10), pages 1-35, May.
    7. Georgios K. Koulinas & Alexandros S. Xanthopoulos & Konstantinos A. Sidas & Dimitrios E. Koulouriotis, 2021. "Risks Ranking in a Desalination Plant Construction Project with a Hybrid AHP, Risk Matrix, and Simulation-Based Approach," Water Resources Management: An International Journal, Published for the European Water Resources Association (EWRA), Springer;European Water Resources Association (EWRA), vol. 35(10), pages 3221-3233, August.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Hela Chebbi & Wafi Chtourou, 2005. "Réduire les risques des projets d'innovation dans les multinationales : une approche par les réseaux de connaissances," Post-Print hal-00368112, HAL.
    2. Byung-Yun Son & Eul-Bum Lee, 2019. "Using Text Mining to Estimate Schedule Delay Risk of 13 Offshore Oil and Gas EPC Case Studies During the Bidding Process," Energies, MDPI, vol. 12(10), pages 1-25, May.
    3. Myung-Hun Kim & Eul-Bum Lee, 2019. "A Forecast Model for the Level of Engineering Maturity Impact on Contractor’s Procurement and Construction Costs for Offshore EPC Megaprojects," Energies, MDPI, vol. 12(12), pages 1-18, June.
    4. Kirchner, Alexander & Labusch, Nils & Lopez Cordoba, Adriana & Sartor, Sebastian & Tumbas, Sanja & Villalon, Enrique & Wiethoff, Sebastian, 2011. "Network e-Volution," ERCIS Working Papers 11, University of Münster, European Research Center for Information Systems (ERCIS).
    5. Daekyoung Yi & Eul-Bum Lee & Junyong Ahn, 2019. "Onshore Oil and Gas Design Schedule Management Process Through Time-Impact Simulations Analyses," Sustainability, MDPI, vol. 11(6), pages 1-19, March.
    6. Fang, Lei, 2022. "Measuring and decomposing group performance under centralized management," European Journal of Operational Research, Elsevier, vol. 297(3), pages 1006-1013.
    7. Mauro Bambi & Cristina Girolami & Salvatore Federico & Fausto Gozzi, 2017. "Generically distributed investments on flexible projects and endogenous growth," Economic Theory, Springer;Society for the Advancement of Economic Theory (SAET), vol. 63(2), pages 521-558, February.
    8. Nermin Kişi, 2019. "A Strategic Approach to Sustainable Tourism Development Using the A’WOT Hybrid Method: A Case Study of Zonguldak, Turkey," Sustainability, MDPI, vol. 11(4), pages 1-19, February.
    9. Seyed Rakhshan & Ali Kamyad & Sohrab Effati, 2015. "Ranking decision-making units by using combination of analytical hierarchical process method and Tchebycheff model in data envelopment analysis," Annals of Operations Research, Springer, vol. 226(1), pages 505-525, March.
    10. Kun Chen & Gang Kou & J. Michael Tarn & Yan Song, 2015. "Bridging the gap between missing and inconsistent values in eliciting preference from pairwise comparison matrices," Annals of Operations Research, Springer, vol. 235(1), pages 155-175, December.
    11. Yuan-Wei Du & Wen Zhou, 2019. "DSmT-Based Group DEMATEL Method with Reaching Consensus," Group Decision and Negotiation, Springer, vol. 28(6), pages 1201-1230, December.
    12. Olivier Chanel, 2022. "Impact of COVID‑19 Activity Restrictions on Air Pollution: Methodological Considerations in the Economic Valuation of the Long‑Term Effects on Mortality [Impact sur la pollution de l’air des restri," Working Papers hal-03778336, HAL.
    13. Carmen Herrero & Antonio Villar, 2022. "Sports competitions and the Break-Even rule," Working Papers 22.13, Universidad Pablo de Olavide, Department of Economics.
    14. Reinhard Ellwanger, Stephen Snudden, 2021. "Predictability of Aggregated Time Series," LCERPA Working Papers bm0127, Laurier Centre for Economic Research and Policy Analysis.
    15. Madjid Tavana & Mariya Sodenkamp & Leena Suhl, 2010. "A soft multi-criteria decision analysis model with application to the European Union enlargement," Annals of Operations Research, Springer, vol. 181(1), pages 393-421, December.
    16. Charles N. Haas, 1997. "Importance of Distributional Form in Characterizing Inputs to Monte Carlo Risk Assessments," Risk Analysis, John Wiley & Sons, vol. 17(1), pages 107-113, February.
    17. Jiabin Liu & Ji Han, 2017. "Does a Certain Rule Exist in the Long-Term Change of a City’s Livability? Evidence from New York, Tokyo, and Shanghai," Sustainability, MDPI, vol. 9(10), pages 1-15, September.
    18. Abdelmonaim Okacha & Adil Salhi & Kamal Abdelrahman & Hamid Fattasse & Kamal Lahrichi & Kaoutar Bakhouya & Biraj Kanti Mondal, 2024. "Balancing Environmental and Human Needs: Geographic Information System-Based Analytical Hierarchy Process Land Suitability Planning for Emerging Urban Areas in Bni Bouayach Amid Urban Transformation," Sustainability, MDPI, vol. 16(15), pages 1-24, July.
    19. Zola, Fernanda Cavicchioli & Colmenero, João Carlos & Aragão, Franciely Velozo & Rodrigues, Thaisa & Junior, Aldo Braghini, 2020. "Multicriterial model for selecting a charcoal kiln," Energy, Elsevier, vol. 190(C).
    20. Pan Guo & Xiaofeng Li & Yanlin Jia & Xu Zhang, 2020. "Cloud Model-Based Comprehensive Evaluation Method for Entrepreneurs’ Uncertainty Tolerance," Mathematics, MDPI, vol. 8(9), pages 1-14, September.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jsusta:v:11:y:2019:i:5:p:1256-:d:209464. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.