Integrated production and transportation scheduling problem under nonlinear cost structures

Author

Listed:
  • Wang, Julong
  • Liu, Zhixue
  • Li, Feng

Abstract

We consider an integrated production and transportation scheduling problem arising in several make-to-order settings, where customer orders have release times and pre-specified delivery time windows. These orders are first processed in a plant and, thereafter, delivered to their customer sites by transporters (e.g., freight trains, ships, or air flights) with fixed departure times and nonlinear transportation cost functions. If the processing of an order is completed but not immediately delivered, it will be stored temporarily, incurring inventory holding costs. The objective is finding an integrated schedule for production and transportation such that the total cost of inventory holding and transportation is minimized. In this study, we consider the following two cases: one where partial delivery is not allowed, and the other where partial delivery is allowed. For each case, we propose an exact algorithm to find optimal solutions for small-scale instances, and a heuristic algorithm to find near-optimal solutions for large-scale instances. For the randomly generated test instances, the computational results reveal that the exact algorithms significantly outperform a commercial optimization solver in terms of the computational times and the number of instances solved within a specified time limit, and the heuristic algorithms are capable of generating near-optimal solutions within a reasonable computational time. Finally, we incorporate considerations of sequence-dependent setup time into the problem and apply the approaches for designing the algorithms to address the more general problem.

Suggested Citation

  • Wang, Julong & Liu, Zhixue & Li, Feng, 2024. "Integrated production and transportation scheduling problem under nonlinear cost structures," European Journal of Operational Research, Elsevier, vol. 313(3), pages 883-904.
  • Handle: RePEc:eee:ejores:v:313:y:2024:i:3:p:883-904
    DOI: 10.1016/j.ejor.2023.08.030
    as

    Download full text from publisher

    File URL: http://www.sciencedirect.com/science/article/pii/S0377221723006604
    Download Restriction: Full text for ScienceDirect subscribers only

    File URL: https://libkey.io/10.1016/j.ejor.2023.08.030?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Agnetis, Alessandro & Aloulou, Mohamed Ali & Fu, Liang-Liang, 2014. "Coordination of production and interstage batch delivery with outsourced distribution," European Journal of Operational Research, Elsevier, vol. 238(1), pages 130-142.
    2. Lixin Tang & Feng Li & Zhi-Long Chen, 2019. "Integrated Scheduling of Production and Two-Stage Delivery of Make-to-Order Products: Offline and Online Algorithms," INFORMS Journal on Computing, INFORMS, vol. 31(3), pages 493-514, July.
    3. Marshall L. Fisher, 2004. "The Lagrangian Relaxation Method for Solving Integer Programming Problems," Management Science, INFORMS, vol. 50(12_supple), pages 1861-1871, December.
    4. Hark-Chin Hwang, 2010. "Economic Lot-Sizing for Integrated Production and Transportation," Operations Research, INFORMS, vol. 58(2), pages 428-444, April.
    5. Lap Mui Ann Chan & Ana Muriel & Zuo-Jun Max Shen & David Simchi-Levi & Chung-Piaw Teo, 2002. "Effective Zero-Inventory-Ordering Policies for the Single-Warehouse Multiretailer Problem with Piecewise Linear Cost Structures," Management Science, INFORMS, vol. 48(11), pages 1446-1460, November.
    6. Campbell, James F., 1990. "Freight consolidation and routing with transportation economies of scale," Transportation Research Part B: Methodological, Elsevier, vol. 24(5), pages 345-361, October.
    7. Keely L. Croxton & Bernard Gendron & Thomas L. Magnanti, 2003. "Models and Methods for Merge-in-Transit Operations," Transportation Science, INFORMS, vol. 37(1), pages 1-22, February.
    8. Allahverdi, Ali & Gupta, Jatinder N. D. & Aldowaisan, Tariq, 1999. "A review of scheduling research involving setup considerations," Omega, Elsevier, vol. 27(2), pages 219-239, April.
    9. Kathryn E. Stecke & Xuying Zhao, 2007. "Production and Transportation Integration for a Make-to-Order Manufacturing Company with a Commit-to-Delivery Business Mode," Manufacturing & Service Operations Management, INFORMS, vol. 9(2), pages 206-224, September.
    10. Devapriya, Priyantha & Ferrell, William & Geismar, Neil, 2017. "Integrated production and distribution scheduling with a perishable product," European Journal of Operational Research, Elsevier, vol. 259(3), pages 906-916.
    11. Tobias Harks & Felix G. König & Jannik Matuschke & Alexander T. Richter & Jens Schulz, 2016. "An Integrated Approach to Tactical Transportation Planning in Logistics Networks," Transportation Science, INFORMS, vol. 50(2), pages 439-460, May.
    12. Gordon, Valery & Proth, Jean-Marie & Chu, Chengbin, 2002. "A survey of the state-of-the-art of common due date assignment and scheduling research," European Journal of Operational Research, Elsevier, vol. 139(1), pages 1-25, May.
    13. Simin Zhang & Haiqing Song, 2018. "Production and Distribution Planning in Danone Waters China Division," Interfaces, INFORMS, vol. 48(6), pages 578-590, November.
    14. Feng Li & Zhou Xu & Zhi-Long Chen, 2020. "Production and Transportation Integration for Commit-to-Delivery Mode with General Shipping Costs," INFORMS Journal on Computing, INFORMS, vol. 32(4), pages 1012-1029, October.
    15. Li, Feng & Xu, Shifu & Xu, Zhou, 2023. "New exact and approximation algorithms for integrated production and transportation scheduling with committed delivery due dates and order acceptance," European Journal of Operational Research, Elsevier, vol. 306(1), pages 127-140.
    16. Nicholas G. Hall & 'Maseka Lesaoana & Chris N. Potts, 2001. "Scheduling with Fixed Delivery Dates," Operations Research, INFORMS, vol. 49(1), pages 134-144, February.
    17. Li, Kunpeng & Sivakumar, Appa Iyer & Ganesan, Viswanath Kumar, 2008. "Complexities and algorithms for synchronized scheduling of parallel machine assembly and air transportation in consumer electronics supply chain," European Journal of Operational Research, Elsevier, vol. 187(2), pages 442-455, June.
    18. Jacques Desrosiers & Marco E. Lübbecke, 2005. "A Primer in Column Generation," Springer Books, in: Guy Desaulniers & Jacques Desrosiers & Marius M. Solomon (ed.), Column Generation, chapter 0, pages 1-32, Springer.
    19. Alessandro Agnetis & Mohamed Ali Aloulou & Mikhail Y. Kovalyov, 2017. "Integrated production scheduling and batch delivery with fixed departure times and inventory holding costs," International Journal of Production Research, Taylor & Francis Journals, vol. 55(20), pages 6193-6206, October.
    20. Franca, Paulo M. & Gendreau, Michel & Laporte, Gilbert & Muller, Felipe M., 1996. "A tabu search heuristic for the multiprocessor scheduling problem with sequence dependent setup times," International Journal of Production Economics, Elsevier, vol. 43(2-3), pages 79-89, June.
    21. Jenn-Rong Lin & Linda Nozick & Mark Turnquist, 2006. "Strategic design of distribution systems with economies of scale in transportation," Annals of Operations Research, Springer, vol. 144(1), pages 161-180, April.
    22. Baker, Kenneth R., 2014. "Minimizing earliness and tardiness costs in stochastic scheduling," European Journal of Operational Research, Elsevier, vol. 236(2), pages 445-452.
    23. Bachtenkirch, David & Bock, Stefan, 2022. "Finding efficient make-to-order production and batch delivery schedules," European Journal of Operational Research, Elsevier, vol. 297(1), pages 133-152.
    24. Nicholas G. Hall & Wieslaw Kubiak & Suresh P. Sethi, 1991. "Earliness–Tardiness Scheduling Problems, II: Deviation of Completion Times About a Restrictive Common Due Date," Operations Research, INFORMS, vol. 39(5), pages 847-856, October.
    25. Quetschlich, Mathias & Moetz, André & Otto, Boris, 2021. "Optimisation model for multi-item multi-echelon supply chains with nested multi-level products," European Journal of Operational Research, Elsevier, vol. 290(1), pages 144-158.
    26. Goetschalckx, Marc & Vidal, Carlos J. & Dogan, Koray, 2002. "Modeling and design of global logistics systems: A review of integrated strategic and tactical models and design algorithms," European Journal of Operational Research, Elsevier, vol. 143(1), pages 1-18, November.
    27. Wan, Long & Mei, Jiajie & Du, Jiangze, 2021. "Two-agent scheduling of unit processing time jobs to minimize total weighted completion time and total weighted number of tardy jobs," European Journal of Operational Research, Elsevier, vol. 290(1), pages 26-35.
    28. Chhajed, Dilip, 1995. "A fixed interval due-date scheduling problem with earliness and due-date costs," European Journal of Operational Research, Elsevier, vol. 84(2), pages 385-401, July.
    29. H. Neil Geismar & Nagesh M. Murthy, 2015. "Balancing Production and Distribution in Paper Manufacturing," Production and Operations Management, Production and Operations Management Society, vol. 24(7), pages 1164-1178, July.
    30. Lap Mui Ann Chan & Ana Muriel & Zuo-Jun Shen & David Simchi-Levi, 2002. "On the Effectiveness of Zero-Inventory-Ordering Policies for the Economic Lot-Sizing Model with a Class of Piecewise Linear Cost Structures," Operations Research, INFORMS, vol. 50(6), pages 1058-1067, December.
    31. George B. Dantzig & Philip Wolfe, 1960. "Decomposition Principle for Linear Programs," Operations Research, INFORMS, vol. 8(1), pages 101-111, February.
    32. Kenneth R. Baker & Gary D. Scudder, 1990. "Sequencing with Earliness and Tardiness Penalties: A Review," Operations Research, INFORMS, vol. 38(1), pages 22-36, February.
    33. Jeffrey B. Sidney, 1977. "Optimal Single-Machine Scheduling with Earliness and Tardiness Penalties," Operations Research, INFORMS, vol. 25(1), pages 62-69, February.
    34. MELO, Rafael A. & WOLSEY, Laurence A., 2010. "Optimizing production and transportation in a commit-to-delivery business mode," LIDAM Reprints CORE 2193, Université catholique de Louvain, Center for Operations Research and Econometrics (CORE).
    35. Nicholas G. Hall & Marc E. Posner, 1991. "Earliness-Tardiness Scheduling Problems, I: Weighted Deviation of Completion Times About a Common Due Date," Operations Research, INFORMS, vol. 39(5), pages 836-846, October.
    36. Zhi-Long Chen, 2010. "Integrated Production and Outbound Distribution Scheduling: Review and Extensions," Operations Research, INFORMS, vol. 58(1), pages 130-148, February.
    37. Gerstl, Enrique & Mosheiov, Gur, 2013. "Due-window assignment with identical jobs on parallel uniform machines," European Journal of Operational Research, Elsevier, vol. 229(1), pages 41-47.
    38. Feng Li & Zhi-Long Chen & Zhi-Long Chen, 2017. "Integrated Production, Inventory and Delivery Problems: Complexity and Algorithms," INFORMS Journal on Computing, INFORMS, vol. 29(2), pages 232-250, May.
    39. Dennis Huisman & Raf Jans & Marc Peeters & Albert P.M. Wagelmans, 2005. "Combining Column Generation and Lagrangian Relaxation," Springer Books, in: Guy Desaulniers & Jacques Desrosiers & Marius M. Solomon (ed.), Column Generation, chapter 0, pages 247-270, Springer.
    40. Agnetis, Alessandro & Aloulou, Mohamed Ali & Fu, Liang-Liang & Kovalyov, Mikhail Y., 2015. "Two faster algorithms for coordination of production and batch delivery: A note," European Journal of Operational Research, Elsevier, vol. 241(3), pages 927-930.
    41. Allahverdi, Ali & Aydilek, Harun & Aydilek, Asiye, 2018. "No-wait flowshop scheduling problem with two criteria; total tardiness and makespan," European Journal of Operational Research, Elsevier, vol. 269(2), pages 590-601.
    42. Adam Fleischhacker & Bintong Chen & Hemant Kher & Mariano Mazal & Bob Pfender, 2015. "Practice Summary: Capacity Planning in the Presence of Sequence-Dependent Setups at AstraZeneca Pharmaceuticals," Interfaces, INFORMS, vol. 45(4), pages 358-362, August.
    43. Francis Sourd, 2009. "New Exact Algorithms for One-Machine Earliness-Tardiness Scheduling," INFORMS Journal on Computing, INFORMS, vol. 21(1), pages 167-175, February.
    44. Marshall L. Fisher, 2004. "Comments on ÜThe Lagrangian Relaxation Method for Solving Integer Programming ProblemsÝ," Management Science, INFORMS, vol. 50(12_supple), pages 1872-1874, December.
    45. Chung-Yee Lee & Sila Çetinkaya & Wikrom Jaruphongsa, 2003. "A Dynamic Model for Inventory Lot Sizing and Outbound Shipment Scheduling at a Third-Party Warehouse," Operations Research, INFORMS, vol. 51(5), pages 735-747, October.
    46. Han, Dongya & Yang, Yongjian & Wang, Dujuan & Cheng, T.C.E. & Yin, Yunqiang, 2019. "Integrated production, inventory, and outbound distribution operations with fixed departure times in a three-stage supply chain," Transportation Research Part E: Logistics and Transportation Review, Elsevier, vol. 125(C), pages 334-347.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Feng Li & Zhi-Long Chen & Zhi-Long Chen, 2017. "Integrated Production, Inventory and Delivery Problems: Complexity and Algorithms," INFORMS Journal on Computing, INFORMS, vol. 29(2), pages 232-250, May.
    2. Li, Feng & Xu, Shifu & Xu, Zhou, 2023. "New exact and approximation algorithms for integrated production and transportation scheduling with committed delivery due dates and order acceptance," European Journal of Operational Research, Elsevier, vol. 306(1), pages 127-140.
    3. Feng Li & Zhou Xu & Zhi-Long Chen, 2020. "Production and Transportation Integration for Commit-to-Delivery Mode with General Shipping Costs," INFORMS Journal on Computing, INFORMS, vol. 32(4), pages 1012-1029, October.
    4. Bachtenkirch, David & Bock, Stefan, 2022. "Finding efficient make-to-order production and batch delivery schedules," European Journal of Operational Research, Elsevier, vol. 297(1), pages 133-152.
    5. Han, Dongya & Yang, Yongjian & Wang, Dujuan & Cheng, T.C.E. & Yin, Yunqiang, 2019. "Integrated production, inventory, and outbound distribution operations with fixed departure times in a three-stage supply chain," Transportation Research Part E: Logistics and Transportation Review, Elsevier, vol. 125(C), pages 334-347.
    6. Azeddine Cheref & Alessandro Agnetis & Christian Artigues & Jean-Charles Billaut, 2017. "Complexity results for an integrated single machine scheduling and outbound delivery problem with fixed sequence," Journal of Scheduling, Springer, vol. 20(6), pages 681-693, December.
    7. Baker, Kenneth R., 2014. "Minimizing earliness and tardiness costs in stochastic scheduling," European Journal of Operational Research, Elsevier, vol. 236(2), pages 445-452.
    8. Azadian, Farshid & Murat, Alper & Chinnam, Ratna Babu, 2015. "Integrated production and logistics planning: Contract manufacturing and choice of air/surface transportation," European Journal of Operational Research, Elsevier, vol. 247(1), pages 113-123.
    9. Byung-Cheon Choi & Myoung-Ju Park, 2021. "Single-machine scheduling with periodic due dates to minimize the total earliness and tardy penalty," Journal of Combinatorial Optimization, Springer, vol. 41(4), pages 781-793, May.
    10. Lemos, R.F. & Ronconi, D.P., 2015. "Heuristics for the stochastic single-machine problem with E/T costs," International Journal of Production Economics, Elsevier, vol. 168(C), pages 131-142.
    11. Ling Liu & Sen Liu, 2020. "Integrated Production and Distribution Problem of Perishable Products with a Minimum Total Order Weighted Delivery Time," Mathematics, MDPI, vol. 8(2), pages 1-18, January.
    12. Lin, Shih-Wei & Chou, Shuo-Yan & Ying, Kuo-Ching, 2007. "A sequential exchange approach for minimizing earliness-tardiness penalties of single-machine scheduling with a common due date," European Journal of Operational Research, Elsevier, vol. 177(2), pages 1294-1301, March.
    13. Archetti, Claudia & Bertazzi, Luca & Grazia Speranza, M., 2014. "Polynomial cases of the economic lot sizing problem with cost discounts," European Journal of Operational Research, Elsevier, vol. 237(2), pages 519-527.
    14. Simon Thevenin & Nicolas Zufferey & Rémy Glardon, 2017. "Model and metaheuristics for a scheduling problem integrating procurement, sale and distribution decisions," Annals of Operations Research, Springer, vol. 259(1), pages 437-460, December.
    15. Li, Kai & Jia, Zhao-hong & Leung, Joseph Y.-T., 2015. "Integrated production and delivery on parallel batching machines," European Journal of Operational Research, Elsevier, vol. 247(3), pages 755-763.
    16. Biskup, Dirk & Feldmann, Martin, 2005. "On scheduling around large restrictive common due windows," European Journal of Operational Research, Elsevier, vol. 162(3), pages 740-761, May.
    17. Koulamas, Christos & Kyparisis, George J., 2023. "A classification of dynamic programming formulations for offline deterministic single-machine scheduling problems," European Journal of Operational Research, Elsevier, vol. 305(3), pages 999-1017.
    18. Hoogeveen, Han, 2005. "Multicriteria scheduling," European Journal of Operational Research, Elsevier, vol. 167(3), pages 592-623, December.
    19. Li, Chung-Lun & Li, Feng, 2020. "Rescheduling production and outbound deliveries when transportation service is disrupted," European Journal of Operational Research, Elsevier, vol. 286(1), pages 138-148.
    20. Hino, Celso M. & Ronconi, Debora P. & Mendes, Andre B., 2005. "Minimizing earliness and tardiness penalties in a single-machine problem with a common due date," European Journal of Operational Research, Elsevier, vol. 160(1), pages 190-201, January.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:ejores:v:313:y:2024:i:3:p:883-904. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/locate/eor .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.