Performance Prediction of Construction Projects Based on the Causes of Claims: A System Dynamics Approach

Author

Listed:
  • Ramin Ansari

    (Department of Civil Engineering, Imam Khomeini International University, Qazvin 3414896818, Iran)

  • Mohammad Khalilzadeh

    (CENTRUM Católica Graduate Business School, Pontificia Universidad Católica del Perú, Lima 15023, Peru)

  • Roohollah Taherkhani

    (Department of Civil Engineering, Imam Khomeini International University, Qazvin 3414896818, Iran)

  • Jurgita Antucheviciene

    (Department of Construction Management and Real Estate, Vilnius Gediminas Technical University, LT-10223 Vilnius, Lithuania)

  • Darius Migilinskas

    (Department of Construction Management and Real Estate, Vilnius Gediminas Technical University, LT-10223 Vilnius, Lithuania)

  • Shohreh Moradi

    (Department of Civil Engineering, Imam Khomeini International University, Qazvin 3414896818, Iran)

Abstract

Conflict in human relations is unavoidable; therefore, it can occur in construction projects that are full of many human relationships. These conflicts can lead to claims if interlocutors do not agree. The main result of the claims is the delay and overrun of costs in construction projects. Additionally, poor management of claims affects the success of construction projects and their budget and schedule. Moreover, controlling claims ensures the successful completion of construction projects and minimizes delays and disputes. This study sought to improve the project performance by ranking the causes of claims and examining their impacts on Key Performance Indicators (KPI) using the combined AHP-TOPSIS (Analytic Hierarchy Process-Technique for Order of Preference by Similarity to Ideal Solution) method. Given that construction projects are constantly evolving and becoming more complex and have many linear and nonlinear relationships and structures, these projects can be considered as a kind of system dynamics. The system dynamics have been used for nearly four decades to analyze and improve the performance of construction projects. This study attempted to provide a model with a system dynamics approach to predict the performance of construction projects based on the reasons for the claim. In this model, the most important performance indicators, interactions between them, and the relationship of these indicators with the reasons for claiming were simulated. The results showed that delays are the most important reasons for making claims, and they have a great impact on the KPIs such as scheduling, sustainability, customer satisfaction, quality, and team satisfaction, respectively. In the modeling and simulation discussion in this study, the proposed model simulated the dependencies between the KPIs of construction projects and their changes over time and provides a better understanding of how performance indicators interact with each other. Additionally, it can be used as a basis for simulating different management policies to find the best solution to prevent and correct the negative effects of poor performance.

Suggested Citation

  • Ramin Ansari & Mohammad Khalilzadeh & Roohollah Taherkhani & Jurgita Antucheviciene & Darius Migilinskas & Shohreh Moradi, 2022. "Performance Prediction of Construction Projects Based on the Causes of Claims: A System Dynamics Approach," Sustainability, MDPI, vol. 14(7), pages 1-19, March.
  • Handle: RePEc:gam:jsusta:v:14:y:2022:i:7:p:4138-:d:783801
    as

    Download full text from publisher

    File URL: https://www.mdpi.com/2071-1050/14/7/4138/pdf
    Download Restriction: no

    File URL: https://www.mdpi.com/2071-1050/14/7/4138/
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. P. E. D. Love & P. Mandal & H. Li, 1999. "Determining the causal structure of rework influences in construction," Construction Management and Economics, Taylor & Francis Journals, vol. 17(4), pages 505-517.
    2. C Eden & T Williams & F Ackermann & S Howick, 2000. "The role of feedback dynamics in disruption and delay on the nature of disruption and delay (D&D) in major projects," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 51(3), pages 291-300, March.
    3. Sayyid Ali Banihashemi & Mohammad Khalilzadeh & Edmundas Kazimieras Zavadskas & Jurgita Antucheviciene, 2021. "Investigating the Environmental Impacts of Construction Projects in Time-Cost Trade-Off Project Scheduling Problems with CoCoSo Multi-Criteria Decision-Making Method," Sustainability, MDPI, vol. 13(19), pages 1-17, September.
    4. Aziz Naghizadeh Vardin & Ramin Ansari & Mohammad Khalilzadeh & Jurgita Antucheviciene & Romualdas Bausys, 2021. "An Integrated Decision Support Model Based on BWM and Fuzzy-VIKOR Techniques for Contractor Selection in Construction Projects," Sustainability, MDPI, vol. 13(12), pages 1-28, June.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Peipei Wang & Yunhan Huang & Jianguo Zhu & Ming Shan, 2022. "Construction Dispute Potentials: Mechanism versus Empiricism in Artificial Neural Networks," Sustainability, MDPI, vol. 14(22), pages 1-23, November.
    2. Noori Adel, 2023. "Assessment of interorganisational conflict in building refurbishment projects using EFA and PLS-SEM," Organization, Technology and Management in Construction, Sciendo, vol. 15(1), pages 178-191, January.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Hossein Kiani & Seyed Hossein Hosseini & Farshid Abdi, 2018. "A Model to Investigate the Effect of Work Ethic Culture on Dynamics of Rework in Management of Projects," Interdisciplinary Description of Complex Systems - scientific journal, Croatian Interdisciplinary Society Provider Homepage: http://indecs.eu, vol. 16(1), pages 40-59.
    2. Hosang Hyun & Hyunsoo Kim & Hyun-Soo Lee & Moonseo Park & Jeonghoon Lee, 2020. "Integrated Design Process for Modular Construction Projects to Reduce Rework," Sustainability, MDPI, vol. 12(2), pages 1-19, January.
    3. F Ackermann & C Eden & T Williams & S Howick, 2007. "Systemic risk assessment: a case study," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 58(1), pages 39-51, January.
    4. Yehiel Rosenfeld, 2009. "Cost of quality versus cost of non-quality in construction: the crucial balance," Construction Management and Economics, Taylor & Francis Journals, vol. 27(2), pages 107-117.
    5. D F Cioffi & H Khamooshi, 2009. "A practical method of determining project risk contingency budgets," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 60(4), pages 565-571, April.
    6. Fatemeh Mostofi & Vedat Toğan & Yunus Emre Ayözen & Onur Behzat Tokdemir, 2022. "Predicting the Impact of Construction Rework Cost Using an Ensemble Classifier," Sustainability, MDPI, vol. 14(22), pages 1-19, November.
    7. Bloomfield, Katherine & Williams, Terry & Bovis, Chris & Merali, Yasmin, 2019. "Systemic risk in major public contracts," International Journal of Forecasting, Elsevier, vol. 35(2), pages 667-676.
    8. Luz Stella Cardona-Meza & Gerard Olivar-Tost, 2017. "Modeling and Simulation of Project Management through the PMBOK® Standard Using Complex Networks," Complexity, Hindawi, vol. 2017, pages 1-12, December.
    9. Eze Emmanuel Chidiebere & Idiake John Ebhohimen & Ganiyu Bashir Olanrewaju, 2018. "Analysis of Rework Risk Triggers in the Nigerian Construction Industry," Organization, Technology and Management in Construction, Sciendo, vol. 10(1), pages 1778-1793, August.
    10. Henao, Felipe & Franco, L. Alberto, 2016. "Unpacking multimethodology: Impacts of a community development intervention," European Journal of Operational Research, Elsevier, vol. 253(3), pages 681-696.
    11. Comi, Alice & Eppler, Martin J., 2014. "Diagnosing capabilities in family firms: An overview of visual research methods and suggestions for future applications," Journal of Family Business Strategy, Elsevier, vol. 5(1), pages 41-51.
    12. Jahangirian, Mohsen & Eldabi, Tillal & Naseer, Aisha & Stergioulas, Lampros K. & Young, Terry, 2010. "Simulation in manufacturing and business: A review," European Journal of Operational Research, Elsevier, vol. 203(1), pages 1-13, May.
    13. Zezhou Wu & Kaijie Yang & Xiaofan Lai & Maxwell Fordjour Antwi-Afari, 2020. "A Scientometric Review of System Dynamics Applications in Construction Management Research," Sustainability, MDPI, vol. 12(18), pages 1-16, September.
    14. Georgiou, Ion, 2012. "Messing about in transformations: Structured systemic planning for systemic solutions to systemic problems," European Journal of Operational Research, Elsevier, vol. 223(2), pages 392-406.
    15. Iyer K. Chandrashekhar & Banerjee Partha S., 2016. "Project ambidexterity: case of recovering schedule delay in a brownfield airport project in India," Organization, Technology and Management in Construction, Sciendo, vol. 8(1), pages 1464-1481, December.
    16. J Davis & A MacDonald & L White, 2010. "Problem-structuring methods and project management: an example of stakeholder involvement using Hierarchical Process Modelling methodology," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 61(6), pages 893-904, June.
    17. Nigel Wadeson, 2013. "The Division of Labour under Uncertainty," Journal of Institutional and Theoretical Economics (JITE), Mohr Siebeck, Tübingen, vol. 169(2), pages 253-274, June.
    18. Yu, Yang & Wu, Shibo & Yu, Jianxing & Xu, Ya & Song, Lin & Xu, Weipeng, 2022. "A hybrid multi-criteria decision-making framework for offshore wind turbine selection: A case study in China," Applied Energy, Elsevier, vol. 328(C).
    19. Woong-Gi Kim & Namhyuk Ham & Jae-Jun Kim, 2021. "Enhanced Subcontractors Allocation for Apartment Construction Project Applying Conceptual 4D Digital Twin Framework," Sustainability, MDPI, vol. 13(21), pages 1-21, October.
    20. G Zhu & J F Bard & G Yu, 2005. "Disruption management for resource-constrained project scheduling," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 56(4), pages 365-381, April.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jsusta:v:14:y:2022:i:7:p:4138-:d:783801. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.