Selection of technical risk responses for efficient contingencies

Author

Listed:
  • Edouard Kujawski

Abstract

The primary goal of good project risk management should be to successfully deliver projects for the lowest cost at an acceptable level of risk. This requires the systematic development and implementation of a set of Risk Response Actions (RRAs) that achieves the lowest total project cost for a given probability of success while meeting technical performance and schedule. We refer to this set as the “efficient RRA set.” This work presents a practical and mathematically sound approach for determining the efficient RRA set. It builds on some of Markowitz's portfolio selection principles and introduces several conceptual and modeling differences to properly treat project technical risks. The set of RRAs is treated as whole and not just individual risks. The efficient RRA set is determined based on “Outcome Cost vs. Probability of Success.” The risks and RRAs are characterized using scenarios, decision trees, and cumulative probability distributions. The analysis provides information that enables decision‐makers to select the efficient RRA set that explicitly takes their attitude toward project risk into account. Decision‐makers should find it both useful and practical for sound decision‐making under uncertainty/risk and efficiently optimizing project success. The computations are readily performed using commercially available Monte Carlo simulation tools. The approach is detailed using a realistic but simplified case of a project with two technical risks. © 2002 Wiley Periodicals, Inc. Syst Eng 5, 194–212, 2002

Suggested Citation

  • Edouard Kujawski, 2002. "Selection of technical risk responses for efficient contingencies," Systems Engineering, John Wiley & Sons, vol. 5(3), pages 194-212.
  • Handle: RePEc:wly:syseng:v:5:y:2002:i:3:p:194-212
    DOI: 10.1002/sys.10025
    as

    Download full text from publisher

    File URL: https://doi.org/10.1002/sys.10025
    Download Restriction: no

    File URL: https://libkey.io/10.1002/sys.10025?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Muzaffar A. Shaikh, 1998. "Project schedule recomputation after risk inclusion," Systems Engineering, John Wiley & Sons, vol. 1(3), pages 242-249.
    2. Stanley Kaplan, 1981. "On The Method of Discrete Probability Distributions in Risk and Reliability Calculations–Application to Seismic Risk Assessment," Risk Analysis, John Wiley & Sons, vol. 1(3), pages 189-196, September.
    3. Edouard Kujawski, 2002. "Why projects often fail, even with high cost‐contingencies," Systems Engineering, John Wiley & Sons, vol. 5(2), pages 151-155.
    4. Charles N. Haas, 1999. "On Modeling Correlated Random Variables in Risk Assessment," Risk Analysis, John Wiley & Sons, vol. 19(6), pages 1205-1214, December.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Edouard Kujawski, 2016. "A Probabilistic Game‐Theoretic Method to Assess Deterrence and Defense Benefits of Security Systems," Systems Engineering, John Wiley & Sons, vol. 19(6), pages 549-566, November.
    2. Edouard Kujawski & Gregory A. Miller, 2007. "Quantitative risk‐based analysis for military counterterrorism systems," Systems Engineering, John Wiley & Sons, vol. 10(4), pages 273-289, December.
    3. Dengsheng Wu & Xiaoqian Zhu & Jie Wan & Chunbing Bao & Jianping Li, 2019. "A Multiobjective Optimization Approach for Selecting Risk Response Strategies of Software Project: From the Perspective of Risk Correlations," International Journal of Information Technology & Decision Making (IJITDM), World Scientific Publishing Co. Pte. Ltd., vol. 18(01), pages 339-364, January.
    4. Mahsa Parsaei Motamed & Shahrooz Bamdad, 2022. "A multi-objective optimization approach for selecting risk response actions: considering environmental and secondary risks," OPSEARCH, Springer;Operational Research Society of India, vol. 59(1), pages 266-303, March.
    5. Zhang, Yao & Zuo, Fei & Guan, Xin, 2020. "Integrating case-based analysis and fuzzy optimization for selecting project risk response actions," Physica A: Statistical Mechanics and its Applications, Elsevier, vol. 545(C).
    6. Edouard Kujawski & Diana Angelis, 2010. "Monitoring risk response actions for effective project risk management," Systems Engineering, John Wiley & Sons, vol. 13(4), pages 353-368, December.
    7. Ruth Y. Dicdican & Yacov Y. Haimes, 2005. "Relating multiobjective decision trees to the multiobjective risk impact analysis method," Systems Engineering, John Wiley & Sons, vol. 8(2), pages 95-108.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Y. Malevergne & D. Sornette, 2003. "Testing the Gaussian copula hypothesis for financial assets dependences," Quantitative Finance, Taylor & Francis Journals, vol. 3(4), pages 231-250.
    2. Alan B. Marchant, 2010. "Obstacles to the flow of requirements verification," Systems Engineering, John Wiley & Sons, vol. 13(1), pages 1-13, March.
    3. Jorge A. Sefair & Oscar Guaje & Andrés L. Medaglia, 2021. "A column-oriented optimization approach for the generation of correlated random vectors," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 43(3), pages 777-808, September.
    4. Lester B. Lave & Joshua Menkes, 1985. "Managing Risk: A Joint U.S.‐German Perspective," Risk Analysis, John Wiley & Sons, vol. 5(1), pages 17-23, March.
    5. Robert E. Kurth & David C. Cox, 1985. "Discrete Probability Distributions for Probabilistic Fracture Mechanics," Risk Analysis, John Wiley & Sons, vol. 5(3), pages 235-240, September.
    6. Raymond F. Boykin & Mardyros Kazarians & Raymond A. Freeman, 1986. "Comparative Fire Risk Study of PCB Transformers," Risk Analysis, John Wiley & Sons, vol. 6(4), pages 477-488, December.
    7. Xu, Shiyun & Shao, Menglin & Qiao, Wenxuan & Shang, Pengjian, 2018. "Generalized AIC method based on higher-order moments and entropy of financial time series," Physica A: Statistical Mechanics and its Applications, Elsevier, vol. 505(C), pages 1127-1138.
    8. David Corredor-Montenegro & Nicolás Cabrera & Raha Akhavan-Tabatabaei & Andrés L. Medaglia, 2021. "On the shortest $$\alpha$$ α -reliable path problem," TOP: An Official Journal of the Spanish Society of Statistics and Operations Research, Springer;Sociedad de Estadística e Investigación Operativa, vol. 29(1), pages 287-318, April.
    9. Kwag, Shinyoung & Park, Junhee & Choi, In-Kil, 2020. "Development of efficient complete-sampling-based seismic PSA method for nuclear power plant," Reliability Engineering and System Safety, Elsevier, vol. 197(C).
    10. Edouard Kujawski & Gregory A. Miller, 2007. "Quantitative risk‐based analysis for military counterterrorism systems," Systems Engineering, John Wiley & Sons, vol. 10(4), pages 273-289, December.
    11. A. E. Ades & G. Lu, 2003. "Correlations Between Parameters in Risk Models: Estimation and Propagation of Uncertainty by Markov Chain Monte Carlo," Risk Analysis, John Wiley & Sons, vol. 23(6), pages 1165-1172, December.
    12. Carolyn D. Heising & Virgilio Lopes de Oliveira, 1995. "A Unified Approach for Calculating Core Melt Frequency Caused by Internal and External Initiating Events," Risk Analysis, John Wiley & Sons, vol. 15(1), pages 41-47, February.
    13. Stan Kaplan & James C. Lin, 1987. "An Improved Condensation Procedure in Discrete Probability Distribution Calculations," Risk Analysis, John Wiley & Sons, vol. 7(1), pages 15-19, March.
    14. Gyun Seob Song & Man Cheol Kim, 2021. "Mathematical Formulation and Analytic Solutions for Uncertainty Analysis in Probabilistic Safety Assessment of Nuclear Power Plants," Energies, MDPI, vol. 14(4), pages 1-15, February.
    15. Stephen D. Unwin, 1986. "A Fuzzy Set Theoretic Foundation for Vagueness in Uncertainty Analysis," Risk Analysis, John Wiley & Sons, vol. 6(1), pages 27-34, March.
    16. M. L. Murray & D. B. Chambers & R. A. Knapp & S. Kaplan, 1987. "Estimation of Long‐Term Risk from Canadian Uranium Mill Tailings," Risk Analysis, John Wiley & Sons, vol. 7(3), pages 287-298, September.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:wly:syseng:v:5:y:2002:i:3:p:194-212. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Wiley Content Delivery (email available below). General contact details of provider: https://doi.org/10.1002/(ISSN)1520-6858 .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.