Work Package Sizing and Project Performance

Author

Listed:
  • Chung-Lun Li

    (Department of Logistics and Maritime Studies, Faculty of Business, The Hong Kong Polytechnic University, Hung Hom, Hong Kong)

  • Nicholas G. Hall

    (Fisher College of Business, The Ohio State University, Columbus, Ohio 43210)

Abstract

We study how design decisions in project planning affect the cost of execution. In organizing a project’s tasks into work packages, trade-offs arise. Defining small work packages increases project complexity and workload, and reduces economies of scale, whereas defining large work packages reduces concurrent processing and adversely affects cash flow. Our work is apparently the first to study this trade-off. We consider the objective of minimizing total project cost, subject to a deadline on project makespan. For serial task networks, we describe an efficient algorithm that finds optimal work package sizes. For acyclic task networks, we develop a heuristic method and a lower bound for the unary NP -hard problem. A computational study shows that our heuristic routinely delivers near-optimal solutions that substantially improve on those found by benchmark procedures. Our results demonstrate the value of deliberately varying work package sizes within a project, in contrast to typical project management practice. Related issues including multiple serial paths in parallel, task incompatibility, and generalized precedence constrained work packages are also discussed. Our work enables more precise planning of work packages to improve performance, documents the value of integrating the planning of work packages and schedules, and provides insights that guide resource allocation decisions.

Suggested Citation

  • Chung-Lun Li & Nicholas G. Hall, 2019. "Work Package Sizing and Project Performance," Operations Research, INFORMS, vol. 67(1), pages 123-142, January.
  • Handle: RePEc:inm:oropre:v:67:y:2019:i:1:p:123-142
    DOI: 10.1287/opre.2018.1767
    as

    Download full text from publisher

    File URL: https://doi.org/10.1287/opre.2018.1767
    Download Restriction: no

    File URL: https://libkey.io/10.1287/opre.2018.1767?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Nicholas G. Hall, 2015. "Further Research Opportunities in Project Management," International Handbooks on Information Systems, in: Christoph Schwindt & Jürgen Zimmermann (ed.), Handbook on Project Management and Scheduling Vol. 2, edition 127, chapter 0, pages 945-970, Springer.
    2. Salah E. Elmaghraby & Jerzy Kamburowski, 1992. "The Analysis of Activity Networks Under Generalized Precedence Relations (GPRs)," Management Science, INFORMS, vol. 38(9), pages 1245-1263, September.
    3. Prabuddha De & E. James Dunne & Jay B. Ghosh & Charles E. Wells, 1997. "Complexity of the Discrete Time-Cost Tradeoff Problem for Project Networks," Operations Research, INFORMS, vol. 45(2), pages 302-306, April.
    4. Nalini Dayanand & Rema Padman, 2001. "Project Contracts and Payment Schedules: The Client's Problem," Management Science, INFORMS, vol. 47(12), pages 1654-1667, December.
    5. Vanhoucke, Mario & Coelho, Jose & Debels, Dieter & Maenhout, Broos & Tavares, Luis V., 2008. "An evaluation of the adequacy of project network generators with systematically sampled networks," European Journal of Operational Research, Elsevier, vol. 187(2), pages 511-524, June.
    6. Dan Trietsch & Kenneth R. Baker, 1993. "Basic Techniques for Lot Streaming," Operations Research, INFORMS, vol. 41(6), pages 1065-1076, December.
    7. Deckro, RF & Hebert, JE & Verdini, WA, 1992. "Project scheduling with work packages," Omega, Elsevier, vol. 20(2), pages 169-182, March.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Hongbo Li & Zhe Xu & Wenchao Wei, 2018. "Bi-Objective Scheduling Optimization for Discrete Time/Cost Trade-Off in Projects," Sustainability, MDPI, vol. 10(8), pages 1-15, August.
    2. Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
    3. Nicole Megow & Rolf H. Möhring & Jens Schulz, 2011. "Decision Support and Optimization in Shutdown and Turnaround Scheduling," INFORMS Journal on Computing, INFORMS, vol. 23(2), pages 189-204, May.
    4. Hartmann, Sönke & Briskorn, Dirk, 2008. "A survey of variants and extensions of the resource-constrained project scheduling problem," Working Paper Series 02/2008, Hamburg School of Business Administration (HSBA).
    5. He, Zhengwen & Wang, Nengmin & Jia, Tao & Xu, Yu, 2009. "Simulated annealing and tabu search for multi-mode project payment scheduling," European Journal of Operational Research, Elsevier, vol. 198(3), pages 688-696, November.
    6. Zhengwen He & Nengmin Wang & Pengxiang Li, 2014. "Simulated annealing for financing cost distribution based project payment scheduling from a joint perspective," Annals of Operations Research, Springer, vol. 213(1), pages 203-220, February.
    7. Estévez-Fernández, Arantza, 2012. "A game theoretical approach to sharing penalties and rewards in projects," European Journal of Operational Research, Elsevier, vol. 216(3), pages 647-657.
    8. George L. Vairaktarakis, 2003. "The Value of Resource Flexibility in the Resource-Constrained Job Assignment Problem," Management Science, INFORMS, vol. 49(6), pages 718-732, June.
    9. Len Vandenheede & Mario Vanhoucke & Broos Maenhout, 2016. "A scatter search for the extended resource renting problem," International Journal of Production Research, Taylor & Francis Journals, vol. 54(16), pages 4723-4743, August.
    10. Niloy J. Mukherjee & Subhash C. Sarin & Daniel A. Neira, 2023. "Lot streaming for a two-stage assembly system in the presence of handling costs," Journal of Scheduling, Springer, vol. 26(4), pages 335-351, August.
    11. Minhyuk Jung & Shira You & Seokho Chi & Ilhan Yu & Bon-Gang Hwang, 2018. "The Relationship between Unbilled Accounts Receivable and Financial Performance of Construction Contractors," Sustainability, MDPI, vol. 10(8), pages 1-14, July.
    12. Vanhoucke, Mario & Maenhout, Broos, 2009. "On the characterization and generation of nurse scheduling problem instances," European Journal of Operational Research, Elsevier, vol. 196(2), pages 457-467, July.
    13. Chiu, Huan Neng & Chang, Jen Huei, 2005. "Cost models for lot streaming in a multistage flow shop," Omega, Elsevier, vol. 33(5), pages 435-450, October.
    14. Van Nieuwenhuyse, Inneke & Vandaele, Nico, 2004. "Determining the optimal number of sublots in a single-product, deterministic flow shop with overlapping operations," International Journal of Production Economics, Elsevier, vol. 92(3), pages 221-239, December.
    15. Antonio J. Conejo & Nicholas G. Hall & Daniel Zhuoyu Long & Runhao Zhang, 2021. "Robust Capacity Planning for Project Management," INFORMS Journal on Computing, INFORMS, vol. 33(4), pages 1533-1550, October.
    16. A B Hafızoğlu & M Azizoğlu, 2010. "Linear programming based approaches for the discrete time/cost trade-off problem in project networks," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 61(4), pages 676-685, April.
    17. Shi Chen & Hau Lee, 2017. "Incentive Alignment and Coordination of Project Supply Chains," Management Science, INFORMS, vol. 63(4), pages 1011-1025, April.
    18. Geng, Zhichao & Yuan, Jinjiang, 2023. "Single-machine scheduling of multiple projects with controllable processing times," European Journal of Operational Research, Elsevier, vol. 308(3), pages 1074-1090.
    19. D Biskup & M Feldmann, 2006. "Lot streaming with variable sublots: an integer programming formulation," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 57(3), pages 296-303, March.
    20. Selcuk Karabati & Panagiotis Kouvelis & Gang Yu, 2001. "A Min-Max-Sum Resource Allocation Problem and Its Applications," Operations Research, INFORMS, vol. 49(6), pages 913-922, December.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:inm:oropre:v:67:y:2019:i:1:p:123-142. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Asher (email available below). General contact details of provider: https://edirc.repec.org/data/inforea.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.