Optimizing Plant-Line Schedules and an Application at Hidden Valley Manufacturing Company

Author

Listed:
  • Gerald G. Brown

    (Operations Research Department, Naval Postgraduate School, Monterey, California 93943–5000)

  • Robert F. Dell

    (Operations Research Department, Naval Postgraduate School, Monterey, California 93943–5000)

  • Ray L. Davis

    (Hidden Valley Manufacturing Company, 1221 Broadway, Oakland, California 94612–1888)

  • Richard H. Duff

    (INSIGHT, Inc., Sudley North Business Center, 7960 Oonegan Drive, Suite 233, Manassas, Virginia 20109–8236)

Abstract

A plant line schedule specifies a plant's sustained batch operations over time with detail sufficient to manage all activities. Plantwide considerations include restrictions on how production centers can be formed from production lines, packaging lines, conveyers, and so forth; the cost and time of product-package item setups, changeovers, and shutdowns; honoring instock service levels, minimum inventory, and committed shipments; recognizing efficiency gains with longer batch runs; respecting crew constraints; and the costs of materials, labor, and carrying inventory. We developed a cost-minimizing optimization model, PROFITS, that features multiple independent time streams for various categories of events that mimic existing periodic reviews of operations. PROFITS is embedded in a graphical user interface that eases the grueling aspects of scheduling: preparing data, controlling scenarios, and visualizing results. At Hidden Valley Manufacturing Company, completing an eight-week plant-line schedule takes about an hour. This is much faster than manual scheduling was—and the schedules are better.

Suggested Citation

  • Gerald G. Brown & Robert F. Dell & Ray L. Davis & Richard H. Duff, 2002. "Optimizing Plant-Line Schedules and an Application at Hidden Valley Manufacturing Company," Interfaces, INFORMS, vol. 32(3), pages 1-14, June.
  • Handle: RePEc:inm:orinte:v:32:y:2002:i:3:p:1-14
    DOI: 10.1287/inte.32.3.1.44
    as

    Download full text from publisher

    File URL: http://dx.doi.org/10.1287/inte.32.3.1.44
    Download Restriction: no

    File URL: https://libkey.io/10.1287/inte.32.3.1.44?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Gerald G. Brown & Arthur M. Geoffrion & Gordon H. Bradley, 1981. "Production and Sales Planning with Limited Shared Tooling at the Key Operation," Management Science, INFORMS, vol. 27(3), pages 247-259, March.
    2. Kuik, R. & Salomon, M., 1990. "Multi-level lot-sizing problem: Evaluation of a simulated-annealing heuristic," European Journal of Operational Research, Elsevier, vol. 45(1), pages 25-37, March.
    3. Gerald G. Brown & Robert F. Dell & R. Kevin Wood, 1997. "Optimization and Persistence," Interfaces, INFORMS, vol. 27(5), pages 15-37, October.
    4. Karla L. Hoffman & Manfred Padberg, 1993. "Solving Airline Crew Scheduling Problems by Branch-and-Cut," Management Science, INFORMS, vol. 39(6), pages 657-682, June.
    5. Sungmin Kang & Kavindra Malik & L. Joseph Thomas, 1999. "Lotsizing and Scheduling on Parallel Machines with Sequence-Dependent Setup Costs," Management Science, INFORMS, vol. 45(2), pages 273-289, February.
    6. A. M. Geoffrion & G. W. Graves, 1976. "Scheduling Parallel Production Lines with Changeover Costs: Practical Application of a Quadratic Assignment/ LP Approach," Operations Research, INFORMS, vol. 24(4), pages 595-610, August.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Casey Chung & Milind Dawande & Divakar Rajamani & Chelliah Sriskandarajah, 2011. "A Short-Range Scheduling Model for Blockbuster's Order-Processing Operation," Interfaces, INFORMS, vol. 41(5), pages 466-484, October.
    2. Kusumastuti, Ratih Dyah & Donk, Dirk Pieter van & Teunter, Ruud, 2016. "Crop-related harvesting and processing planning: a review," International Journal of Production Economics, Elsevier, vol. 174(C), pages 76-92.
    3. Patrick Hew, 2007. "ASP, The Art and Science of Practice: Direct Advisors vs. Tool Developers---Implications for Practice," Interfaces, INFORMS, vol. 37(3), pages 279-284, June.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Maenhout, Broos & Vanhoucke, Mario, 2010. "A hybrid scatter search heuristic for personalized crew rostering in the airline industry," European Journal of Operational Research, Elsevier, vol. 206(1), pages 155-167, October.
    2. Torki, Abdolhamid & Yajima, Yatsutoshi & Enkawa, Takao, 1996. "A low-rank bilinear programming approach for sub-optimal solution of the quadratic assignment problem," European Journal of Operational Research, Elsevier, vol. 94(2), pages 384-391, October.
    3. Michael R. Miller & Robert J. Alexander & Vincent A. Arbige & Robert F. Dell & Steven R. Kremer & Brian P. McClune & Jane E. Oppenlander & Joshua P. Tomlin, 2017. "Optimal Allocation of Students to Naval Nuclear-Power Training Units," Interfaces, INFORMS, vol. 47(4), pages 320-335, August.
    4. Becker, Christian & Scholl, Armin, 2006. "A survey on problems and methods in generalized assembly line balancing," European Journal of Operational Research, Elsevier, vol. 168(3), pages 694-715, February.
    5. Sriram, Chellappan & Haghani, Ali, 2003. "An optimization model for aircraft maintenance scheduling and re-assignment," Transportation Research Part A: Policy and Practice, Elsevier, vol. 37(1), pages 29-48, January.
    6. Haase, Knut, 1999. "Retail business staff scheduling under complex labor relations," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 511, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    7. Fischetti, M. & Kroon, L.G. & Timmer, G. & Vromans, M.J.C.M. & Abbink, E.J.W., 2004. "Reinventing Crew Scheduling at Netherlands Railways," ERIM Report Series Research in Management ERS-2004-046-LIS, Erasmus Research Institute of Management (ERIM), ERIM is the joint research institute of the Rotterdam School of Management, Erasmus University and the Erasmus School of Economics (ESE) at Erasmus University Rotterdam.
    8. Avella, Pasquale & D'Auria, Bernardo & Salerno, Saverio, 2006. "A LP-based heuristic for a time-constrained routing problem," European Journal of Operational Research, Elsevier, vol. 173(1), pages 120-124, August.
    9. Gang Yu & Michael Argüello & Gao Song & Sandra M. McCowan & Anna White, 2003. "A New Era for Crew Recovery at Continental Airlines," Interfaces, INFORMS, vol. 33(1), pages 5-22, February.
    10. Hungerländer, Philipp & Anjos, Miguel F., 2015. "A semidefinite optimization-based approach for global optimization of multi-row facility layout," European Journal of Operational Research, Elsevier, vol. 245(1), pages 46-61.
    11. Rossi, Fabrizio & Smriglio, Stefano, 2001. "A set packing model for the ground holding problem in congested networks," European Journal of Operational Research, Elsevier, vol. 131(2), pages 400-416, June.
    12. Erwin Abbink & Matteo Fischetti & Leo Kroon & Gerrit Timmer & Michiel Vromans, 2005. "Reinventing Crew Scheduling at Netherlands Railways," Interfaces, INFORMS, vol. 35(5), pages 393-401, October.
    13. Guo, Yufeng & Mellouli, Taieb & Suhl, Leena & Thiel, Markus P., 2006. "A partially integrated airline crew scheduling approach with time-dependent crew capacities and multiple home bases," European Journal of Operational Research, Elsevier, vol. 171(3), pages 1169-1181, June.
    14. Herrán, Alberto & Manuel Colmenar, J. & Duarte, Abraham, 2021. "An efficient variable neighborhood search for the Space-Free Multi-Row Facility Layout problem," European Journal of Operational Research, Elsevier, vol. 295(3), pages 893-907.
    15. İbrahim Muter & Ş. İlker Birbil & Güvenç Şahin, 2010. "Combination of Metaheuristic and Exact Algorithms for Solving Set Covering-Type Optimization Problems," INFORMS Journal on Computing, INFORMS, vol. 22(4), pages 603-619, November.
    16. Elena Katok & Holly S. Lewis & Terry P. Harrison, 1998. "Lot Sizing in General Assembly Systems with Setup Costs, Setup Times, and Multiple Constrained Resources," Management Science, INFORMS, vol. 44(6), pages 859-877, June.
    17. Drexl, A. & Kimms, A., 1997. "Lot sizing and scheduling -- Survey and extensions," European Journal of Operational Research, Elsevier, vol. 99(2), pages 221-235, June.
    18. Xia, Mu & Koehler, Gary J. & Whinston, Andrew B., 2004. "Pricing combinatorial auctions," European Journal of Operational Research, Elsevier, vol. 154(1), pages 251-270, April.
    19. Drexl, Andreas & Nissen, Rudiger & Patterson, James H. & Salewski, Frank, 2000. "ProGen/[pi]x - An instance generator for resource-constrained project scheduling problems with partially renewable resources and further extensions," European Journal of Operational Research, Elsevier, vol. 125(1), pages 59-72, August.
    20. Andrew G. Clark & Susan Cholette & Ozgur Ozluk, 2011. "UCSF Increases Consumer Value Through Optimal Vendor-Show Scheduling," Interfaces, INFORMS, vol. 41(4), pages 327-337, August.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:inm:orinte:v:32:y:2002:i:3:p:1-14. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Asher (email available below). General contact details of provider: https://edirc.repec.org/data/inforea.html .