Influence of Technical Reasons on Cost Overruns of Infrastructural Projects: A Sustainable Development Perspective

Author

Listed:
  • Marijo Lovrinčević

    (Ariozo d.o.o., Put Meja 16, 21000 Split, Croatia)

  • Mladen Vukomanović

    (Department for Construction Management and Economics, Faculty of Civil Engineering, University of Zagreb, Fra Andrije Kačića-Miošića 26, 10000 Zagreb, Croatia)

  • Romano Perić

    (BIM Projekt d.o.o., Kupska 2, 10000 Zagreb, Croatia)

Abstract

Cost overruns are a significant issue in infrastructure projects, adversely affecting not only economic performance but also sustainability goals by straining resources and extending project timelines. There is consensus among researchers about the persistence of cost overruns and the importance of accurate estimates. However, there are significant differences in the explanation of the reasons for the overruns. While we recognize the importance of understanding the reasons for cost overruns at all stages of project development, we have focused on the reasons for cost overruns after contract award due to the rarely available real and valid data collected at the source of the information. We analyze the deviations between actual and contracted costs, as well as the dependence of cost deviations of individual project types on the size of the contract. For example, the size of the tunnel significantly affects relative cost deviations, while for standard viaducts or road sections this effect is minimal. The results confirmed that cost overruns are less frequent in standard facilities than in those where the experience factor has little influence on the final cost estimate. For example, deviations in the average value of the contracted costs for highway sections range between −12.1% and 27.9% of the contracted value, and for standardized viaduct projects they range between −16.73% and 6.27% of the contracted value. The type of distribution function of deviations between actual and contractually agreed costs was investigated, and a predictive model for estimating future cost deviations of project programs was presented. The goal is to improve economic sustainability and the related optimization of resources in the development of infrastructure, which contributes to the broader agenda of sustainable development. The results encourage the adoption of improved project documentation and forecasting tools, which are essential for sustainable project management.

Suggested Citation

  • Marijo Lovrinčević & Mladen Vukomanović & Romano Perić, 2024. "Influence of Technical Reasons on Cost Overruns of Infrastructural Projects: A Sustainable Development Perspective," Sustainability, MDPI, vol. 16(21), pages 1-20, October.
  • Handle: RePEc:gam:jsusta:v:16:y:2024:i:21:p:9413-:d:1509810
    as

    Download full text from publisher

    File URL: https://www.mdpi.com/2071-1050/16/21/9413/pdf
    Download Restriction: no

    File URL: https://www.mdpi.com/2071-1050/16/21/9413/
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Cantarelli, C.C. & Molin, E.J.E. & van Wee, B. & Flyvbjerg, B., 2012. "Characteristics of cost overruns for Dutch transport infrastructure projects and the importance of the decision to build and project phases," Transport Policy, Elsevier, vol. 22(C), pages 49-56.
    2. Odeck, James, 2014. "Do reforms reduce the magnitudes of cost overruns in road projects? Statistical evidence from Norway," Transportation Research Part A: Policy and Practice, Elsevier, vol. 65(C), pages 68-79.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Chong, Uven & Hopkins, Omar, 2016. "An international experience on the evolution of road costs during the project life cycle," Transport Policy, Elsevier, vol. 48(C), pages 60-66.
    2. Abeysekara, Baudhi & Perera, Piyaruwan & Chhipi Shrestha, Gyan Kumar & Gunaruwan, Lalithasiri & Kumarage, Amal & Sadiq, Rehan & Hewage, Kasun, 2021. "Improving the capital deployment efficiency: An infrastructure investment planning process in transportation project," Research in Transportation Economics, Elsevier, vol. 88(C).
    3. Cavalieri, Marina & Cristaudo, Rossana & Guccio, Calogero, 2019. "On the magnitude of cost overruns throughout the project life-cycle: An assessment for the Italian transport infrastructure projects," Transport Policy, Elsevier, vol. 79(C), pages 21-36.
    4. Bartlomiej Rokicki, 2022. "Cost Underruns in Major Road Transport Infrastructure Projects—The Surprising Experience of Poland," Sustainability, MDPI, vol. 14(21), pages 1-18, November.
    5. Miranda Sarmento, J.J., 2014. "Public private partnerships," Other publications TiSEM c7d4c978-234c-4f88-83ed-1, Tilburg University, School of Economics and Management.
    6. Yarmukhamedov, Sherzod & Smith, Andrew S.J. & Thiebaud, Jean-Christophe, 2020. "Competitive tendering, ownership and cost efficiency in road maintenance services in Sweden: A panel data analysis," Transportation Research Part A: Policy and Practice, Elsevier, vol. 136(C), pages 194-204.
    7. Asplund, Disa & Eliasson, Jonas, 2016. "Does uncertainty make cost-benefit analyses pointless?," Transportation Research Part A: Policy and Practice, Elsevier, vol. 92(C), pages 195-205.
    8. Adriana Gómez-Cabrera & Amalia Sanz-Benlloch & Laura Montalban-Domingo & Jose Luis Ponz-Tienda & Eugenio Pellicer, 2020. "Identification of Factors Affecting the Performance of Rural Road Projects in Colombia," Sustainability, MDPI, vol. 12(18), pages 1-18, September.
    9. Edyta Plebankiewicz & Damian Wieczorek, 2020. "Prediction of Cost Overrun Risk in Construction Projects," Sustainability, MDPI, vol. 12(22), pages 1-15, November.
    10. Petr Halámek & Radka Matuszková & Michal Radimský, 2021. "Modernisation of Regional Roads Evaluated Using Ex-Post CBA," Sustainability, MDPI, vol. 13(4), pages 1-20, February.
    11. Verweij, Stefan & van Meerkerk, Ingmar & Korthagen, Iris A., 2015. "Reasons for contract changes in implementing Dutch transportation infrastructure projects: An empirical exploration," Transport Policy, Elsevier, vol. 37(C), pages 195-202.
    12. Love, Peter E.D. & Zhou, Jingyang & Edwards, David J. & Irani, Zahir & Sing, Chun-Pong, 2017. "Off the rails: The cost performance of infrastructure rail projects," Transportation Research Part A: Policy and Practice, Elsevier, vol. 99(C), pages 14-29.
    13. Awojobi, Omotola & Jenkins, Glenn P., 2016. "Managing the cost overrun risks of hydroelectric dams: An application of reference class forecasting techniques," Renewable and Sustainable Energy Reviews, Elsevier, vol. 63(C), pages 19-32.
    14. Jarosław Górecki & Manuel Díaz-Madroñero, 2020. "Who Risks and Wins?—Simulated Cost Variance in Sustainable Construction Projects," Sustainability, MDPI, vol. 12(8), pages 1-31, April.
    15. Ihsan Issa Ahmad Hosani & Fikri T. Dweiri & Udechukwu Ojiako, 0. "A study of cost overruns in complex multi-stakeholder road projects in the United Arab Emirates," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 0, pages 1-10.
    16. Locatelli, Giorgio & Invernizzi, Diletta Colette & Brookes, Naomi J., 2017. "Project characteristics and performance in Europe: An empirical analysis for large transport infrastructure projects," Transportation Research Part A: Policy and Practice, Elsevier, vol. 98(C), pages 108-122.
    17. Miller, Michael & Szimba, Eckhard, 2015. "How to avoid unrealistic appraisal results? A concept to reflect the occurrence of risk in the appraisal of transport infrastructure projects," Research in Transportation Economics, Elsevier, vol. 49(C), pages 65-75.
    18. Miranda Sarmento, J.J. & Renneboog, Luc, 2017. "Cost overruns in public sector investment projects," Other publications TiSEM 51799a3e-4c78-4dbd-b330-b, Tilburg University, School of Economics and Management.
    19. Flyvbjerg, Bent & Ansar, Atif & Budzier, Alexander & Buhl, Søren & Cantarelli, Chantal & Garbuio, Massimo & Glenting, Carsten & Holm, Mette Skamris & Lovallo, Dan & Lunn, Daniel & Molin, Eric & Rønnes, 2018. "Five things you should know about cost overrun," Transportation Research Part A: Policy and Practice, Elsevier, vol. 118(C), pages 174-190.
    20. James Odeck, 2019. "Variation in cost overruns of transportation projects: an econometric meta-regression analysis of studies reported in the literature," Transportation, Springer, vol. 46(4), pages 1345-1368, August.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jsusta:v:16:y:2024:i:21:p:9413-:d:1509810. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.