IDEAS home Printed from https://ideas.repec.org/a/eee/proeco/v180y2016icp198-207.html
   My bibliography  Save this article

A two-stage stochastic programming model for lot-sizing and scheduling under uncertainty

Author

Listed:
  • Hu, Zhengyang
  • Hu, Guiping

Abstract

A lot-sizing and scheduling problem with sequence-dependent setups is addressed in this paper. In the production system, manufactories receive raw materials from upstream sites, and after production, the final products are shipped to downstream sites and customers. The key is to find a good production planning so that their cost is minimized. A two-stage stochastic programming model is formulated to minimize the total production, inventory and backorder costs. The first stage decides the baseline production including the production quantity of each product and the sequence of production while the second stage focuses on the possible updates of baseline production such as overtime production. The goal is to find the best sequence of production quantities under random demand with backorders allowed. Uncertainty is explicitly represented with a scenario tree then selecting the most representative scenarios in order to obtain a smaller subset while preserving essential properties. Both setup time and setup cost are product dependent. A case study for a manufacturing company producing braking equipment has been conducted to illustrate and validate the model. The results show that the stochastic model outperforms the deterministic model, especially when there are sufficient production resources.

Suggested Citation

  • Hu, Zhengyang & Hu, Guiping, 2016. "A two-stage stochastic programming model for lot-sizing and scheduling under uncertainty," International Journal of Production Economics, Elsevier, vol. 180(C), pages 198-207.
  • Handle: RePEc:eee:proeco:v:180:y:2016:i:c:p:198-207
    DOI: 10.1016/j.ijpe.2016.07.027
    as

    Download full text from publisher

    File URL: http://www.sciencedirect.com/science/article/pii/S0925527316301797
    Download Restriction: Full text for ScienceDirect subscribers only

    File URL: https://libkey.io/10.1016/j.ijpe.2016.07.027?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Ford W. Harris, 1990. "How Many Parts to Make at Once," Operations Research, INFORMS, vol. 38(6), pages 947-950, December.
    2. Kjetil Høyland & Stein W. Wallace, 2001. "Generating Scenario Trees for Multistage Decision Problems," Management Science, INFORMS, vol. 47(2), pages 295-307, February.
    3. L. Escudero & P. Kamesam, 1995. "On solving stochastic production planning problems via scenario modelling," TOP: An Official Journal of the Spanish Society of Statistics and Operations Research, Springer;Sociedad de Estadística e Investigación Operativa, vol. 3(1), pages 69-95, June.
    4. Guimarães, Luis & Klabjan, Diego & Almada-Lobo, Bernardo, 2014. "Modeling lotsizing and scheduling problems with sequence dependent setups," European Journal of Operational Research, Elsevier, vol. 239(3), pages 644-662.
    5. Y. Bassok & R. Akella, 1991. "Ordering and Production Decisions with Supply Quality and Demand Uncertainty," Management Science, INFORMS, vol. 37(12), pages 1556-1574, December.
    6. Harvey M. Wagner & Thomson M. Whitin, 1958. "Dynamic Version of the Economic Lot Size Model," Management Science, INFORMS, vol. 5(1), pages 89-96, October.
    7. Fabrizio Marinelli & Maria Nenni & Antonio Sforza, 2007. "Capacitated lot sizing and scheduling with parallel machines and shared buffers: A case study in a packaging company," Annals of Operations Research, Springer, vol. 150(1), pages 177-192, March.
    8. Ferreira, Deisemara & Morabito, Reinaldo & Rangel, Socorro, 2009. "Solution approaches for the soft drink integrated production lot sizing and scheduling problem," European Journal of Operational Research, Elsevier, vol. 196(2), pages 697-706, July.
    9. Drexl, A. & Kimms, A., 1997. "Lot sizing and scheduling -- Survey and extensions," European Journal of Operational Research, Elsevier, vol. 99(2), pages 221-235, June.
    10. Mula, J. & Poler, R. & Garcia-Sabater, J.P. & Lario, F.C., 2006. "Models for production planning under uncertainty: A review," International Journal of Production Economics, Elsevier, vol. 103(1), pages 271-285, September.
    11. Diaby, M. & Bahl, H. C. & Karwan, M. H. & Zionts, S., 1992. "Capacitated lot-sizing and scheduling by Lagrangean relaxation," European Journal of Operational Research, Elsevier, vol. 59(3), pages 444-458, June.
    12. Xie, Jinxing & Zhao, Xiande & Lee, T. S., 2003. "Freezing the master production schedule under single resource constraint and demand uncertainty," International Journal of Production Economics, Elsevier, vol. 83(1), pages 65-84, January.
    13. Karimi, B. & Fatemi Ghomi, S. M. T. & Wilson, J. M., 2003. "The capacitated lot sizing problem: a review of models and algorithms," Omega, Elsevier, vol. 31(5), pages 365-378, October.
    14. Donald Erlenkotter, 1990. "Ford Whitman Harris and the Economic Order Quantity Model," Operations Research, INFORMS, vol. 38(6), pages 937-946, December.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Hu, Zhengyang & Hu, Guiping, 2020. "Hybrid stochastic and robust optimization model for lot-sizing and scheduling problems under uncertainties," European Journal of Operational Research, Elsevier, vol. 284(2), pages 485-497.
    2. Li, Xinchao & Lu, Shan & Li, Zhe & Wang, Yue & Zhu, Li, 2022. "Modeling and optimization of bioethanol production planning under hybrid uncertainty: A heuristic multi-stage stochastic programming approach," Energy, Elsevier, vol. 245(C).
    3. Zeiträg, Yannik & Figueira, José Rui & Pereira, Miguel Alves, 2024. "A web-based interactive decision support system for a multi-objective lot-sizing and production scheduling model," International Journal of Production Economics, Elsevier, vol. 271(C).
    4. Zhengyang Hu & Viren Parwani & Guiping Hu, 2021. "Closed-Loop Supply Chain Network Design under Uncertainties Using Fuzzy Decision Making," Logistics, MDPI, vol. 5(1), pages 1-16, March.
    5. Máté Hegyháti & Krisztián Attila Bakon & Tibor Holczinger, 2023. "Optimization with uncertainties: a scheduling example," Central European Journal of Operations Research, Springer;Slovak Society for Operations Research;Hungarian Operational Research Society;Czech Society for Operations Research;Österr. Gesellschaft für Operations Research (ÖGOR);Slovenian Society Informatika - Section for Operational Research;Croatian Operational Research Society, vol. 31(4), pages 1239-1263, December.
    6. Sheng-I Chen & Delvinia Su, 2022. "A multi-stage stochastic programming model of lot-sizing and scheduling problems with machine eligibilities and sequence-dependent setups," Annals of Operations Research, Springer, vol. 311(1), pages 35-50, April.
    7. Li, Jianbin & Liu, Lang & Luo, Xiaomeng & Zhu, Stuart X., 2023. "Interactive bundle pricing strategy for online pharmacies," Transportation Research Part E: Logistics and Transportation Review, Elsevier, vol. 177(C).
    8. Curcio, Eduardo & Amorim, Pedro & Zhang, Qi & Almada-Lobo, Bernardo, 2018. "Adaptation and approximate strategies for solving the lot-sizing and scheduling problem under multistage demand uncertainty," International Journal of Production Economics, Elsevier, vol. 202(C), pages 81-96.
    9. Franco Quezada & Céline Gicquel & Safia Kedad-Sidhoum, 2022. "Combining Polyhedral Approaches and Stochastic Dual Dynamic Integer Programming for Solving the Uncapacitated Lot-Sizing Problem Under Uncertainty," INFORMS Journal on Computing, INFORMS, vol. 34(2), pages 1024-1041, March.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Carvalho, Desiree M. & Nascimento, Mariá C.V., 2022. "Hybrid matheuristics to solve the integrated lot sizing and scheduling problem on parallel machines with sequence-dependent and non-triangular setup," European Journal of Operational Research, Elsevier, vol. 296(1), pages 158-173.
    2. Melega, Gislaine Mara & de Araujo, Silvio Alexandre & Jans, Raf, 2018. "Classification and literature review of integrated lot-sizing and cutting stock problems," European Journal of Operational Research, Elsevier, vol. 271(1), pages 1-19.
    3. Karina Copil & Martin Wörbelauer & Herbert Meyr & Horst Tempelmeier, 2017. "Simultaneous lotsizing and scheduling problems: a classification and review of models," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 39(1), pages 1-64, January.
    4. Ferreira, Deisemara & Clark, Alistair R. & Almada-Lobo, Bernardo & Morabito, Reinaldo, 2012. "Single-stage formulations for synchronised two-stage lot sizing and scheduling in soft drink production," International Journal of Production Economics, Elsevier, vol. 136(2), pages 255-265.
    5. Toledo, Franklina Maria Bragion & Armentano, Vinicius Amaral, 2006. "A Lagrangian-based heuristic for the capacitated lot-sizing problem in parallel machines," European Journal of Operational Research, Elsevier, vol. 175(2), pages 1070-1083, December.
    6. Abdolreza Roshani & Massimo Paolucci & Davide Giglio & Melissa Demartini & Flavio Tonelli & Maxim A. Dulebenets, 2023. "The capacitated lot-sizing and energy efficient single machine scheduling problem with sequence dependent setup times and costs in a closed-loop supply chain network," Annals of Operations Research, Springer, vol. 321(1), pages 469-505, February.
    7. Jing Wu & Dan Zhang & Yang Yang & Gongshu Wang & Lijie Su, 2022. "Multi-Stage Multi-Product Production and Inventory Planning for Cold Rolling under Random Yield," Mathematics, MDPI, vol. 10(4), pages 1-21, February.
    8. Martínez, Karim Pérez & Morabito, Reinaldo & Toso, Eli Angela Vitor, 2018. "A coupled process configuration, lot-sizing and scheduling model for production planning in the molded pulp industry," International Journal of Production Economics, Elsevier, vol. 204(C), pages 227-243.
    9. Wolosewicz, Cathy & Dauzère-Pérès, Stéphane & Aggoune, Riad, 2015. "A Lagrangian heuristic for an integrated lot-sizing and fixed scheduling problem," European Journal of Operational Research, Elsevier, vol. 244(1), pages 3-12.
    10. Rossi, Tommaso & Pozzi, Rossella & Testa, Mariapaola, 2017. "EOQ-based inventory management in single-machine multi-item systems," Omega, Elsevier, vol. 71(C), pages 106-113.
    11. Helber, Stefan & Sahling, Florian, 2010. "A fix-and-optimize approach for the multi-level capacitated lot sizing problem," International Journal of Production Economics, Elsevier, vol. 123(2), pages 247-256, February.
    12. Boonmee, Atiwat & Sethanan, Kanchana, 2016. "A GLNPSO for multi-level capacitated lot-sizing and scheduling problem in the poultry industry," European Journal of Operational Research, Elsevier, vol. 250(2), pages 652-665.
    13. Bruno, Giuseppe & Genovese, Andrea & Piccolo, Carmela, 2014. "The capacitated Lot Sizing model: A powerful tool for logistics decision making," International Journal of Production Economics, Elsevier, vol. 155(C), pages 380-390.
    14. Fink, Jiří & Hurink, Johann L., 2015. "Minimizing costs is easier than minimizing peaks when supplying the heat demand of a group of houses," European Journal of Operational Research, Elsevier, vol. 242(2), pages 644-650.
    15. Robinson, Powell & Narayanan, Arunachalam & Sahin, Funda, 2009. "Coordinated deterministic dynamic demand lot-sizing problem: A review of models and algorithms," Omega, Elsevier, vol. 37(1), pages 3-15, February.
    16. Mac Cawley, Alejandro & Maturana, Sergio & Pascual, Rodrigo & Tortorella, Guilherme Luz, 2022. "Scheduling wine bottling operations with multiple lines and sequence-dependent set-up times: Robust formulation and a decomposition solution approach," European Journal of Operational Research, Elsevier, vol. 303(2), pages 819-839.
    17. Brahimi, Nadjib & Absi, Nabil & Dauzère-Pérès, Stéphane & Nordli, Atle, 2017. "Single-item dynamic lot-sizing problems: An updated survey," European Journal of Operational Research, Elsevier, vol. 263(3), pages 838-863.
    18. Miloš Milenković & Susana Val & Nebojša Bojović, 2023. "Simultaneous lot sizing and scheduling in the animal feed premix industry," Operational Research, Springer, vol. 23(2), pages 1-40, June.
    19. Gislaine Mara Melega & Silvio Alexandre de Araujo & Reinaldo Morabito, 2020. "Mathematical model and solution approaches for integrated lot-sizing, scheduling and cutting stock problems," Annals of Operations Research, Springer, vol. 295(2), pages 695-736, December.
    20. Folarin B. Oyebolu & Jeroen Lidth de Jeude & Cyrus Siganporia & Suzanne S. Farid & Richard Allmendinger & Juergen Branke, 2017. "A new lot sizing and scheduling heuristic for multi-site biopharmaceutical production," Journal of Heuristics, Springer, vol. 23(4), pages 231-256, August.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:proeco:v:180:y:2016:i:c:p:198-207. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/locate/ijpe .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.