The impact of a limited budget on the corrective action taking process

Author

Listed:
  • Song, Jie
  • Martens, Annelies
  • Vanhoucke, Mario

Abstract

The main goal of project control is to identify the deviations between the baseline schedule and the actual progress of the project by measuring the project performance in progress and using the project control methodologies to generate warning signals that act as triggers for corrective actions to bring the project back on track. To that purpose, tolerance limits are set on the required project performance, such that if the warning signals exceed these limits, they should result in appropriate corrective actions.

Suggested Citation

  • Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2020. "The impact of a limited budget on the corrective action taking process," European Journal of Operational Research, Elsevier, vol. 286(3), pages 1070-1086.
  • Handle: RePEc:eee:ejores:v:286:y:2020:i:3:p:1070-1086
    DOI: 10.1016/j.ejor.2020.03.069
    as

    Download full text from publisher

    File URL: http://www.sciencedirect.com/science/article/pii/S0377221720303027
    Download Restriction: Full text for ScienceDirect subscribers only

    File URL: https://libkey.io/10.1016/j.ejor.2020.03.069?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Cui, Nanfang & Demeulemeester, Erik & Bie, Li, 2016. "Incorporation of activity sensitivity measures into buffer management to manage project schedule riskAuthor-Name: Hu, Xuejun," European Journal of Operational Research, Elsevier, vol. 249(2), pages 717-727.
    2. Mario Vanhoucke, 2014. "Earned Value Management," Management for Professionals, in: Integrated Project Management and Control, edition 127, chapter 0, pages 17-31, Springer.
    3. Bowman, R. Alan, 2006. "Developing activity duration specification limits for effective project control," European Journal of Operational Research, Elsevier, vol. 174(2), pages 1191-1204, October.
    4. Junguang Zhang & Saike Jia & Estrella Diaz, 2018. "Dynamic monitoring and control of a critical chain project based on phase buffer allocation," Journal of the Operational Research Society, Taylor & Francis Journals, vol. 69(12), pages 1966-1977, December.
    5. Martens, Annelies & Vanhoucke, Mario, 2019. "The impact of applying effort to reduce activity variability on the project time and cost performance," European Journal of Operational Research, Elsevier, vol. 277(2), pages 442-453.
    6. Vanhoucke, Mario & Coelho, Jose & Debels, Dieter & Maenhout, Broos & Tavares, Luis V., 2008. "An evaluation of the adequacy of project network generators with systematically sampled networks," European Journal of Operational Research, Elsevier, vol. 187(2), pages 511-524, June.
    7. Colin, Jeroen & Vanhoucke, Mario, 2014. "Setting tolerance limits for statistical project control using earned value management," Omega, Elsevier, vol. 49(C), pages 107-122.
    8. M Vanhoucke & S Vandevoorde, 2007. "A simulation and evaluation of earned value metrics to forecast the project duration," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 58(10), pages 1361-1374, October.
    9. Vanhoucke, Mario, 2010. "Using activity sensitivity and network topology information to monitor project time performance," Omega, Elsevier, vol. 38(5), pages 359-370, October.
    10. Martens, Annelies & Vanhoucke, Mario, 2017. "A buffer control method for top-down project control," European Journal of Operational Research, Elsevier, vol. 262(1), pages 274-286.
    11. T. C. T. Kotiah & N. D. Wallace, 1973. "Another Look at the PERT Assumptions," Management Science, INFORMS, vol. 20(1), pages 44-49, September.
    12. Vanhoucke, Mario, 2011. "On the dynamic use of project performance and schedule risk information during projecttracking," Omega, Elsevier, vol. 39(4), pages 416-426, August.
    13. Madadi, M. & Iranmanesh, H., 2012. "A management oriented approach to reduce a project duration and its risk (variability)," European Journal of Operational Research, Elsevier, vol. 219(3), pages 751-761.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2022. "Using Earned Value Management and Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 297(2), pages 451-466.
    2. Vaseghi, Forough & Martens, Annelies & Vanhoucke, Mario, 2024. "Analysis of the impact of corrective actions for stochastic project networks," European Journal of Operational Research, Elsevier, vol. 316(2), pages 503-518.
    3. Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2021. "Using Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 288(3), pages 736-752.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2022. "Using Earned Value Management and Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 297(2), pages 451-466.
    2. Martens, Annelies & Vanhoucke, Mario, 2019. "The impact of applying effort to reduce activity variability on the project time and cost performance," European Journal of Operational Research, Elsevier, vol. 277(2), pages 442-453.
    3. Wauters, Mathieu & Vanhoucke, Mario, 2017. "A Nearest Neighbour extension to project duration forecasting with Artificial Intelligence," European Journal of Operational Research, Elsevier, vol. 259(3), pages 1097-1111.
    4. Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2021. "Using Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 288(3), pages 736-752.
    5. Colin, Jeroen & Vanhoucke, Mario, 2014. "Setting tolerance limits for statistical project control using earned value management," Omega, Elsevier, vol. 49(C), pages 107-122.
    6. Martens, Annelies & Vanhoucke, Mario, 2017. "A buffer control method for top-down project control," European Journal of Operational Research, Elsevier, vol. 262(1), pages 274-286.
    7. Vaseghi, Forough & Martens, Annelies & Vanhoucke, Mario, 2024. "Analysis of the impact of corrective actions for stochastic project networks," European Journal of Operational Research, Elsevier, vol. 316(2), pages 503-518.
    8. Plaza, Malgorzata, 2016. "Balancing the costs of human resources on an ERP project," Omega, Elsevier, vol. 59(PB), pages 171-183.
    9. Cui, Nanfang & Demeulemeester, Erik & Bie, Li, 2016. "Incorporation of activity sensitivity measures into buffer management to manage project schedule riskAuthor-Name: Hu, Xuejun," European Journal of Operational Research, Elsevier, vol. 249(2), pages 717-727.
    10. Tao, Liangyan & Wu, Desheng & Liu, Sifeng & Lambert, James H., 2017. "Schedule risk analysis for new-product development: The GERT method extended by a characteristic function," Reliability Engineering and System Safety, Elsevier, vol. 167(C), pages 464-473.
    11. Ünsal-Altuncan, Izel & Vanhoucke, Mario, 2024. "A hybrid forecasting model to predict the duration and cost performance of projects with Bayesian Networks," European Journal of Operational Research, Elsevier, vol. 315(2), pages 511-527.
    12. She, Bingling & Chen, Bo & Hall, Nicholas G., 2021. "Buffer sizing in critical chain project management by network decomposition," Omega, Elsevier, vol. 102(C).
    13. Mohammadreza Sharifi Ghazvini & Vahidreza Ghezavati & Sadigh Raissi & Ahmad Makui, 2017. "An Integrated Efficiency–Risk Approach in Sustainable Project Control," Sustainability, MDPI, vol. 9(9), pages 1-20, September.
    14. Cohen, Izack & Iluz, Michal, 2015. "When cost–effective design strategies are not enough: Evidence from an experimental study on the role of redundant goals," Omega, Elsevier, vol. 56(C), pages 99-111.
    15. Vanhoucke, Mario & Colin, Jeroen, 2016. "On the use of multivariate regression methods for longest path calculations from earned value management observations," Omega, Elsevier, vol. 61(C), pages 127-140.
    16. Fernando Acebes & Javier Pajares & Jose M Gonzalez-Varona & Adolfo Lopez-Paredes, 2024. "Project Risk Management from the bottom-up: Activity Risk Index," Papers 2406.00078, arXiv.org.
    17. Vanhoucke, Mario, 2011. "On the dynamic use of project performance and schedule risk information during projecttracking," Omega, Elsevier, vol. 39(4), pages 416-426, August.
    18. Servranckx, Tom & Vanhoucke, Mario & Aouam, Tarik, 2021. "Practical application of reference class forecasting for cost and time estimations: Identifying the properties of similarity," European Journal of Operational Research, Elsevier, vol. 295(3), pages 1161-1179.
    19. Fernando Acebes & Javier Pajares & José M. González-Varona & Adolfo López-Paredes, 2021. "Project risk management from the bottom-up: Activity Risk Index," Central European Journal of Operations Research, Springer;Slovak Society for Operations Research;Hungarian Operational Research Society;Czech Society for Operations Research;Österr. Gesellschaft für Operations Research (ÖGOR);Slovenian Society Informatika - Section for Operational Research;Croatian Operational Research Society, vol. 29(4), pages 1375-1396, December.
    20. Richard E. Wendell & Timothy J. Lowe & Mike M. Gordon, 2023. "Dangers in using earned duration and other earned value metrics to measure a project’s schedule performance," Central European Journal of Operations Research, Springer;Slovak Society for Operations Research;Hungarian Operational Research Society;Czech Society for Operations Research;Österr. Gesellschaft für Operations Research (ÖGOR);Slovenian Society Informatika - Section for Operational Research;Croatian Operational Research Society, vol. 31(2), pages 665-680, June.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:ejores:v:286:y:2020:i:3:p:1070-1086. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/locate/eor .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.