Resource allocation in multi-class dynamic PERT networks with finite capacity

Author

Listed:
  • Yaghoubi, Saeed
  • Noori, Siamak
  • Azaron, Amir
  • Fynes, Brian

Abstract

In this paper, the resource allocation problem in multi-class dynamic PERT networks with finite capacity of concurrent projects (COnstant Number of Projects In Process (CONPIP)) is studied. The dynamic PERT network is modeled as a queuing network, where new projects from different classes (types) are generated according to independent Poisson processes with different rates over the time horizon. Each activity of a project is performed at a devoted service station with one server located in a node of the network, whereas activity durations for different classes in each service station are independent and exponentially distributed random variables with different service rates. Indeed, the projects from different classes may be different in their precedence networks and also the durations of the activities. For modeling the multi-class dynamic PERT networks with CONPIP, we first consider every class separately and convert the queueing network of every class into a proper stochastic network. Then, by constructing a proper finite-state continuous-time Markov model, a system of differential equations is created to compute the project completion time distribution for any particular project. The problem is formulated as a multi-objective model with three objectives to optimally control the resources allocated to the service stations. Finally, we develop a simulated annealing (SA) algorithm to solve this multi-objective problem, using the goal attainment formulation. We also compare the SA results against the results of a discrete-time approximation of the original optimal control problem, to show the effectiveness of the proposed solution technique.

Suggested Citation

  • Yaghoubi, Saeed & Noori, Siamak & Azaron, Amir & Fynes, Brian, 2015. "Resource allocation in multi-class dynamic PERT networks with finite capacity," European Journal of Operational Research, Elsevier, vol. 247(3), pages 879-894.
  • Handle: RePEc:eee:ejores:v:247:y:2015:i:3:p:879-894
    DOI: 10.1016/j.ejor.2015.06.038
    as

    Download full text from publisher

    File URL: http://www.sciencedirect.com/science/article/pii/S0377221715005524
    Download Restriction: Full text for ScienceDirect subscribers only

    File URL: https://libkey.io/10.1016/j.ejor.2015.06.038?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Chen, Vincent Y. X., 1994. "A 0-1 goal programming model for scheduling multiple maintenance projects at a copper mine," European Journal of Operational Research, Elsevier, vol. 76(1), pages 176-191, July.
    2. Linda Nozick & Mark Turnquist & Ningxiong Xu, 2004. "Managing Portfolios of Projects under Uncertainty," Annals of Operations Research, Springer, vol. 132(1), pages 243-256, November.
    3. Azaron, Amir & Tavakkoli-Moghaddam, Reza, 2007. "Multi-objective time-cost trade-off in dynamic PERT networks using an interactive approach," European Journal of Operational Research, Elsevier, vol. 180(3), pages 1186-1200, August.
    4. A. Alan B. Pritsker & Lawrence J. Waiters & Philip M. Wolfe, 1969. "Multiproject Scheduling with Limited Resources: A Zero-One Programming Approach," Management Science, INFORMS, vol. 16(1), pages 93-108, September.
    5. Balasubramanian Kanagasabapathi & Chandrasekharan Rajendran & Kuppuswamy Ananthanarayanan, 2009. "Performance analysis of scheduling rules in resource-constrained multiple projects," International Journal of Industrial and Systems Engineering, Inderscience Enterprises Ltd, vol. 4(5), pages 502-535.
    6. Gonçalves, J.F. & Mendes, J.J.M. & Resende, M.G.C., 2008. "A genetic algorithm for the resource constrained multi-project scheduling problem," European Journal of Operational Research, Elsevier, vol. 189(3), pages 1171-1190, September.
    7. Papadopoulos, H. T. & Heavey, C., 1996. "Queueing theory in manufacturing systems analysis and design: A classification of models for production and transfer lines," European Journal of Operational Research, Elsevier, vol. 92(1), pages 1-27, July.
    8. Tan, BarIs & Gershwin, Stanley B., 2009. "Analysis of a general Markovian two-stage continuous-flow production system with a finite buffer," International Journal of Production Economics, Elsevier, vol. 120(2), pages 327-339, August.
    9. Antonio Lova & Pilar Tormos, 2001. "Analysis of Scheduling Schemes and Heuristic Rules Performance in Resource-Constrained Multiproject Scheduling," Annals of Operations Research, Springer, vol. 102(1), pages 263-286, February.
    10. D. R. Fulkerson, 1961. "A Network Flow Computation for Project Cost Curves," Management Science, INFORMS, vol. 7(2), pages 167-178, January.
    11. Azaron, Amir & Fynes, Brian & Modarres, Mohammad, 2011. "Due date assignment in repetitive projects," International Journal of Production Economics, Elsevier, vol. 129(1), pages 79-85, January.
    12. Izack Cohen & Boaz Golany & Avraham Shtub, 2005. "Managing Stochastic, Finite Capacity, Multi-Project Systems through the Cross-Entropy Methodology," Annals of Operations Research, Springer, vol. 134(1), pages 183-199, February.
    13. L. R. Lamberson & R. R. Hocking, 1970. "Optimum Time Compression in Project Scheduling," Management Science, INFORMS, vol. 16(10), pages 597-606, June.
    14. Paul S. Adler & Avi Mandelbaum & Viên Nguyen & Elizabeth Schwerer, 1995. "From Project to Process Management: An Empirically-Based Framework for Analyzing Product Development Time," Management Science, INFORMS, vol. 41(3), pages 458-484, March.
    15. V. G. Kulkarni & V. G. Adlakha, 1986. "Markov and Markov-Regenerative pert Networks," Operations Research, INFORMS, vol. 34(5), pages 769-781, October.
    16. B Suman & P Kumar, 2006. "A survey of simulated annealing as a tool for single and multiobjective optimization," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 57(10), pages 1143-1160, October.
    17. James E. Falk & Joel L. Horowitz, 1972. "Critical Path Problems with Concave Cost-Time Curves," Management Science, INFORMS, vol. 19(4-Part-1), pages 446-455, December.
    18. Oualid Jouini & Yves Dallery & Zeynep Aksin, 2009. "Queueing models for full-flexible multi-class call centers with real-time anticipated delays," Post-Print hal-00565481, HAL.
    19. I. Kurtulus & E. W. Davis, 1982. "Multi-Project Scheduling: Categorization of Heuristic Rules Performance," Management Science, INFORMS, vol. 28(2), pages 161-172, February.
    20. Azaron, Amir & Katagiri, Hideki & Sakawa, Masatoshi & Kato, Kosuke & Memariani, Azizollah, 2006. "A multi-objective resource allocation problem in PERT networks," European Journal of Operational Research, Elsevier, vol. 172(3), pages 838-854, August.
    21. Yaghoubi, Saeed & Noori, Siamak & Azaron, Amir & Tavakkoli-Moghaddam, Reza, 2011. "Resource allocation in dynamic PERT networks with finite capacity," European Journal of Operational Research, Elsevier, vol. 215(3), pages 670-678, December.
    22. Amir Azaron & Hideki Katagiri & Masatoshi Sakawa, 2007. "Time-cost trade-off via optimal control theory in Markov PERT networks," Annals of Operations Research, Springer, vol. 150(1), pages 47-64, March.
    23. Jerome D. Wiest, 1967. "A Heuristic Model for Scheduling Large Projects with Limited Resources," Management Science, INFORMS, vol. 13(6), pages 359-377, February.
    24. Osorio, Carolina & Bierlaire, Michel, 2009. "An analytic finite capacity queueing network model capturing the propagation of congestion and blocking," European Journal of Operational Research, Elsevier, vol. 196(3), pages 996-1007, August.
    25. Jouini, Oualid & Dallery, Yves & Aksin, Zeynep, 2009. "Queueing models for full-flexible multi-class call centers with real-time anticipated delays," International Journal of Production Economics, Elsevier, vol. 120(2), pages 389-399, August.
    26. Lova, Antonio & Maroto, Concepcion & Tormos, Pilar, 2000. "A multicriteria heuristic method to improve resource allocation in multiproject scheduling," European Journal of Operational Research, Elsevier, vol. 127(2), pages 408-424, December.
    27. Tsubakitani, Shigeru & Deckro, Richard F., 1990. "A heuristic for multi-project scheduling with limited resources in the housing industry," European Journal of Operational Research, Elsevier, vol. 49(1), pages 80-91, November.
    28. E. B. Berman, 1964. "Resource Allocation in a PERT Network Under Continuous Activity Time-Cost Functions," Management Science, INFORMS, vol. 10(4), pages 734-745, July.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. He-Yau Kang & Amy H. I. Lee & Tzu-Ting Huang, 2016. "Project Management for a Wind Turbine Construction by Applying Fuzzy Multiple Objective Linear Programming Models," Energies, MDPI, vol. 9(12), pages 1-15, December.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Yaghoubi, Saeed & Noori, Siamak & Azaron, Amir & Tavakkoli-Moghaddam, Reza, 2011. "Resource allocation in dynamic PERT networks with finite capacity," European Journal of Operational Research, Elsevier, vol. 215(3), pages 670-678, December.
    2. Ben Issa, Samer & Patterson, Raymond A. & Tu, Yiliu, 2021. "Solving resource-constrained multi-project environment under different activity assumptions," International Journal of Production Economics, Elsevier, vol. 232(C).
    3. Browning, Tyson R. & Yassine, Ali A., 2010. "Resource-constrained multi-project scheduling: Priority rule performance revisited," International Journal of Production Economics, Elsevier, vol. 126(2), pages 212-228, August.
    4. Azaron, Amir & Tavakkoli-Moghaddam, Reza, 2007. "Multi-objective time-cost trade-off in dynamic PERT networks using an interactive approach," European Journal of Operational Research, Elsevier, vol. 180(3), pages 1186-1200, August.
    5. Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
    6. Gómez Sánchez, Mariam & Lalla-Ruiz, Eduardo & Fernández Gil, Alejandro & Castro, Carlos & Voß, Stefan, 2023. "Resource-constrained multi-project scheduling problem: A survey," European Journal of Operational Research, Elsevier, vol. 309(3), pages 958-976.
    7. Azaron, Amir & Katagiri, Hideki & Sakawa, Masatoshi & Kato, Kosuke & Memariani, Azizollah, 2006. "A multi-objective resource allocation problem in PERT networks," European Journal of Operational Research, Elsevier, vol. 172(3), pages 838-854, August.
    8. Bredael, Dries & Vanhoucke, Mario, 2023. "Multi-project scheduling: A benchmark analysis of metaheuristic algorithms on various optimisation criteria and due dates," European Journal of Operational Research, Elsevier, vol. 308(1), pages 54-75.
    9. Gonçalves, J.F. & Mendes, J.J.M. & Resende, M.G.C., 2008. "A genetic algorithm for the resource constrained multi-project scheduling problem," European Journal of Operational Research, Elsevier, vol. 189(3), pages 1171-1190, September.
    10. Krüger, Doreen & Scholl, Armin, 2009. "A heuristic solution framework for the resource constrained (multi-)project scheduling problem with sequence-dependent transfer times," European Journal of Operational Research, Elsevier, vol. 197(2), pages 492-508, September.
    11. S. Selcuk Erenguc & Taeho Ahn & Daniel G. Conway, 2001. "The resource constrained project scheduling problem with multiple crashable modes: An exact solution method," Naval Research Logistics (NRL), John Wiley & Sons, vol. 48(2), pages 107-127, March.
    12. Cruz, F.R.B. & Van Woensel, T. & Smith, J. MacGregor, 2010. "Buffer and throughput trade-offs in M/G/1/K queueing networks: A bi-criteria approach," International Journal of Production Economics, Elsevier, vol. 125(2), pages 224-234, June.
    13. Ahn, Taeho & Erenguc, S. Selcuk, 1998. "The resource constrained project scheduling problem with multiple crashable modes: A heuristic procedure," European Journal of Operational Research, Elsevier, vol. 107(2), pages 250-259, June.
    14. Rob Eynde & Mario Vanhoucke, 2020. "Resource-constrained multi-project scheduling: benchmark datasets and decoupled scheduling," Journal of Scheduling, Springer, vol. 23(3), pages 301-325, June.
    15. Esmaeil MEHDIZADEH & Hamidreza AKBARI, 2017. "A Novel Vibration Damping Optimization Algorithm for Resource Constrained Multi- Project Scheduling Problem," ECONOMIC COMPUTATION AND ECONOMIC CYBERNETICS STUDIES AND RESEARCH, Faculty of Economic Cybernetics, Statistics and Informatics, vol. 51(2), pages 291-309.
    16. Mahtab Afsari & Hesam Javadi Vasigh, 2016. "A Mathematical Modeling for Delivery Time in Dynamic PERT Networks," Modern Applied Science, Canadian Center of Science and Education, vol. 10(3), pages 214-214, March.
    17. Anıl Can & Gündüz Ulusoy, 2014. "Multi-project scheduling with two-stage decomposition," Annals of Operations Research, Springer, vol. 217(1), pages 95-116, June.
    18. Nicole Megow & Rolf H. Möhring & Jens Schulz, 2011. "Decision Support and Optimization in Shutdown and Turnaround Scheduling," INFORMS Journal on Computing, INFORMS, vol. 23(2), pages 189-204, May.
    19. Hartmann, Sönke & Briskorn, Dirk, 2008. "A survey of variants and extensions of the resource-constrained project scheduling problem," Working Paper Series 02/2008, Hamburg School of Business Administration (HSBA).
    20. M. Suresh & Pankaj Dutta & Karuna Jain, 2015. "Resource Constrained Multi-Project Scheduling Problem with Resource Transfer Times," Asia-Pacific Journal of Operational Research (APJOR), World Scientific Publishing Co. Pte. Ltd., vol. 32(06), pages 1-30, December.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:ejores:v:247:y:2015:i:3:p:879-894. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/locate/eor .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.