Adaptive policies for multi-mode project scheduling under uncertainty

Author

Listed:
  • Godinho, Pedro
  • Branco, Fernando G.

Abstract

In this paper we propose an adaptive model for multi-mode project scheduling under uncertainty. We assume that there is a due date for concluding the project and a tardiness penalty for failing to meet this due date, and that several distinct modes may be used to undertake each activity. We define scheduling policies based on a set of thresholds. The starting time of the activity is compared with those thresholds in order to define the execution mode.

Suggested Citation

  • Godinho, Pedro & Branco, Fernando G., 2012. "Adaptive policies for multi-mode project scheduling under uncertainty," European Journal of Operational Research, Elsevier, vol. 216(3), pages 553-562.
  • Handle: RePEc:eee:ejores:v:216:y:2012:i:3:p:553-562
    DOI: 10.1016/j.ejor.2011.08.010
    as

    Download full text from publisher

    File URL: http://www.sciencedirect.com/science/article/pii/S0377221711007296
    Download Restriction: Full text for ScienceDirect subscribers only

    File URL: https://libkey.io/10.1016/j.ejor.2011.08.010?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Herroelen, Willy & Leus, Roel, 2005. "Project scheduling under uncertainty: Survey and research potentials," European Journal of Operational Research, Elsevier, vol. 165(2), pages 289-306, September.
    2. Azaron, Amir & Tavakkoli-Moghaddam, Reza, 2007. "Multi-objective time-cost trade-off in dynamic PERT networks using an interactive approach," European Journal of Operational Research, Elsevier, vol. 180(3), pages 1186-1200, August.
    3. S.E. Elmaghraby & C.D. Morgan, 2007. "Resource Allocation in Activity Networks under Stochastic Conditions. A Geometric Programming-Sample Path Optimization Approach," Review of Business and Economic Literature, KU Leuven, Faculty of Economics and Business (FEB), Review of Business and Economic Literature, vol. 0(3), pages 367-390.
    4. M. Vanhoucke, 2007. "An electromagnetic time/cost trade-off optimization in project scheduling," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 07/457, Ghent University, Faculty of Economics and Business Administration.
    5. Golenko-Ginzburg, Dimitri & Gonik, Aharon, 1998. "A heuristic for network project scheduling with random activity durations depending on the resource allocation," International Journal of Production Economics, Elsevier, vol. 55(2), pages 149-162, July.
    6. W. J. Gutjahr & C. Strauss & E. Wagner, 2000. "A Stochastic Branch-and-Bound Approach to Activity Crashing in Project Management," INFORMS Journal on Computing, INFORMS, vol. 12(2), pages 125-135, May.
    7. Tereso, Anabela P. & Araujo, M. Madalena T. & Elmaghraby, Salah E., 2004. "Adaptive resource allocation in multimodal activity networks," International Journal of Production Economics, Elsevier, vol. 92(1), pages 1-10, November.
    8. Azaron, Amir & Katagiri, Hideki & Sakawa, Masatoshi & Kato, Kosuke & Memariani, Azizollah, 2006. "A multi-objective resource allocation problem in PERT networks," European Journal of Operational Research, Elsevier, vol. 172(3), pages 838-854, August.
    9. Elmaghraby, Salah E., 2005. "On the fallacy of averages in project risk management," European Journal of Operational Research, Elsevier, vol. 165(2), pages 307-313, September.
    10. Ş. Birbil & Shu-Cherng Fang & Ruey-Lin Sheu, 2004. "On the Convergence of a Population-Based Global Optimization Algorithm," Journal of Global Optimization, Springer, vol. 30(2), pages 301-318, November.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Öncü Hazir & Gündüz Ulusoy, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," Post-Print hal-02898162, HAL.
    2. Gutjahr, Walter J., 2015. "Bi-Objective Multi-Mode Project Scheduling Under Risk Aversion," European Journal of Operational Research, Elsevier, vol. 246(2), pages 421-434.
    3. Pedro Godinho & João Paulo Costa, 2020. "A stochastic model and algorithms for determining efficient time–cost tradeoffs for a project activity," Operational Research, Springer, vol. 20(1), pages 319-348, March.
    4. Hazır, Öncü & Ulusoy, Gündüz, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," International Journal of Production Economics, Elsevier, vol. 223(C).

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Öncü Hazir & Gündüz Ulusoy, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," Post-Print hal-02898162, HAL.
    2. Hazır, Öncü & Ulusoy, Gündüz, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," International Journal of Production Economics, Elsevier, vol. 223(C).
    3. Pedro Godinho & João Paulo Costa, 2020. "A stochastic model and algorithms for determining efficient time–cost tradeoffs for a project activity," Operational Research, Springer, vol. 20(1), pages 319-348, March.
    4. Trietsch, Dan & Mazmanyan, Lilit & Gevorgyan, Lilit & Baker, Kenneth R., 2012. "Modeling activity times by the Parkinson distribution with a lognormal core: Theory and validation," European Journal of Operational Research, Elsevier, vol. 216(2), pages 386-396.
    5. Siqian Shen & J. Cole Smith & Shabbir Ahmed, 2010. "Expectation and Chance-Constrained Models and Algorithms for Insuring Critical Paths," Management Science, INFORMS, vol. 56(10), pages 1794-1814, October.
    6. Gutjahr, Walter J., 2015. "Bi-Objective Multi-Mode Project Scheduling Under Risk Aversion," European Journal of Operational Research, Elsevier, vol. 246(2), pages 421-434.
    7. Sobel, Matthew J. & Szmerekovsky, Joseph G. & Tilson, Vera, 2009. "Scheduling projects with stochastic activity duration to maximize expected net present value," European Journal of Operational Research, Elsevier, vol. 198(3), pages 697-705, November.
    8. Xiong, Jian & Leus, Roel & Yang, Zhenyu & Abbass, Hussein A., 2016. "Evolutionary multi-objective resource allocation and scheduling in the Chinese navigation satellite system project," European Journal of Operational Research, Elsevier, vol. 251(2), pages 662-675.
    9. Azaron, Amir & Fatemi Ghomi, S.M.T., 2008. "Lower bound for the mean project completion time in dynamic PERT networks," European Journal of Operational Research, Elsevier, vol. 186(1), pages 120-127, April.
    10. Wiesemann, Wolfram & Kuhn, Daniel & Rustem, Berç, 2010. "Maximizing the net present value of a project under uncertainty," European Journal of Operational Research, Elsevier, vol. 202(2), pages 356-367, April.
    11. Xue Li & Zhengwen He & Nengmin Wang & Mario Vanhoucke, 2022. "Multimode time-cost-robustness trade-off project scheduling problem under uncertainty," Journal of Combinatorial Optimization, Springer, vol. 43(5), pages 1173-1202, July.
    12. Bordley, Robert F. & Keisler, Jeffrey M. & Logan, Tom M., 2019. "Managing projects with uncertain deadlines," European Journal of Operational Research, Elsevier, vol. 274(1), pages 291-302.
    13. Yaghoubi, Saeed & Noori, Siamak & Azaron, Amir & Fynes, Brian, 2015. "Resource allocation in multi-class dynamic PERT networks with finite capacity," European Journal of Operational Research, Elsevier, vol. 247(3), pages 879-894.
    14. Carlo Meloni & Marco Pranzo, 2020. "Expected shortfall for the makespan in activity networks under imperfect information," Flexible Services and Manufacturing Journal, Springer, vol. 32(3), pages 668-692, September.
    15. Azaron, Amir & Tavakkoli-Moghaddam, Reza, 2007. "Multi-objective time-cost trade-off in dynamic PERT networks using an interactive approach," European Journal of Operational Research, Elsevier, vol. 180(3), pages 1186-1200, August.
    16. Herroelen, Willy & Leus, Roel, 2005. "Project scheduling under uncertainty: Survey and research potentials," European Journal of Operational Research, Elsevier, vol. 165(2), pages 289-306, September.
    17. Yangyang Liang & Nanfang Cui & Tian Wang & Erik Demeulemeester, 2019. "Robust resource-constrained max-NPV project scheduling with stochastic activity duration," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 41(1), pages 219-254, March.
    18. KIlIç, Murat & Ulusoy, Gündüz & Serifoglu, Funda Sivrikaya, 2008. "A bi-objective genetic algorithm approach to risk mitigation in project scheduling," International Journal of Production Economics, Elsevier, vol. 112(1), pages 202-216, March.
    19. Joel Goh & Nicholas G. Hall, 2013. "Total Cost Control in Project Management via Satisficing," Management Science, INFORMS, vol. 59(6), pages 1354-1372, June.
    20. Bregman, Robert L., 2009. "A heuristic procedure for solving the dynamic probabilistic project expediting problem," European Journal of Operational Research, Elsevier, vol. 192(1), pages 125-137, January.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:ejores:v:216:y:2012:i:3:p:553-562. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/locate/eor .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.