IDEAS home Printed from https://ideas.repec.org/p/por/fepwps/186.html
   My bibliography  Save this paper

Beam search algorithms for the single machine total weighted tardiness scheduling problem with sequence-dependent setups

Author

Listed:
  • Jorge M. S. Valente

    (Faculdade de Economia, Universidade do Porto)

Abstract

In this paper, we consider the single machine weighted tardiness scheduling problem with sequence-dependent setups. We present heuristic algorithms based on the beam search technique. These algorithms include classic beam search procedures, as well as the filtered and recovering variants. Previous beam search implementations use fixed beam and filter widths. We consider the usual fixed width algorithms, and develop new versions that use variable beam and filter widths. Two new improvement procedures, based on adjacent pairwise interchanges and 3-swaps, are also presented. The computational results show that the beam search versions with a variable width are marginally superior to their fixed value counterparts, even when a lower average number of beam and filter nodes is used. The best results are given by the filtered beam search algorithms. For large problems, however, these procedures require excessive computation times. The priority beam search algorithms are much faster, and can therefore be used for the largest instances. The 3-swap method is the best of the improvement procedures, giving the largest relative improvement and decreasing the total cost for a larger number of instances.

Suggested Citation

  • Jorge M. S. Valente, 2005. "Beam search algorithms for the single machine total weighted tardiness scheduling problem with sequence-dependent setups," FEP Working Papers 186, Universidade do Porto, Faculdade de Economia do Porto.
  • Handle: RePEc:por:fepwps:186
    as

    Download full text from publisher

    File URL: http://www.fep.up.pt/investigacao/workingpapers/05.08.10_WP186_jorge.pdf
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Jon K. Wilbrecht & William B. Prescott, 1969. "The Influence of Setup Time on Job Shop Performance," Management Science, INFORMS, vol. 16(4), pages 274-280, December.
    2. Chris N. Potts & Luk N. Van Wassenhove, 1985. "A Branch and Bound Algorithm for the Total Weighted Tardiness Problem," Operations Research, INFORMS, vol. 33(2), pages 363-377, April.
    3. Raman, Narayan & Rachamadugu, Ram V. & Talbot, F. Brian, 1989. "Real-time scheduling of an automated manufacturing center," European Journal of Operational Research, Elsevier, vol. 40(2), pages 222-242, May.
    4. Sabuncuoglu, I. & Bayiz, M., 1999. "Job shop scheduling with beam search," European Journal of Operational Research, Elsevier, vol. 118(2), pages 390-412, October.
    5. Sen, Tapan & Sulek, Joanne M. & Dileepan, Parthasarati, 2003. "Static scheduling research to minimize weighted and unweighted tardiness: A state-of-the-art survey," International Journal of Production Economics, Elsevier, vol. 83(1), pages 1-12, January.
    6. Allahverdi, Ali & Gupta, Jatinder N. D. & Aldowaisan, Tariq, 1999. "A review of scheduling research involving setup considerations," Omega, Elsevier, vol. 27(2), pages 219-239, April.
    7. F Della Croce & V T'kindt, 2002. "A Recovering Beam Search algorithm for the one-machine dynamic total completion time scheduling problem," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 53(11), pages 1275-1280, November.
    8. Lee, Young Hoon & Pinedo, Michael, 1997. "Scheduling jobs on parallel machines with sequence-dependent setup times," European Journal of Operational Research, Elsevier, vol. 100(3), pages 464-474, August.
    9. Potts, Chris N. & Kovalyov, Mikhail Y., 2000. "Scheduling with batching: A review," European Journal of Operational Research, Elsevier, vol. 120(2), pages 228-249, January.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Armentano, Vinicius Amaral & de Franca Filho, Moacir Felizardo, 2007. "Minimizing total tardiness in parallel machine scheduling with setup times: An adaptive memory-based GRASP approach," European Journal of Operational Research, Elsevier, vol. 183(1), pages 100-114, November.
    2. Dunstall, Simon & Wirth, Andrew, 2005. "A comparison of branch-and-bound algorithms for a family scheduling problem with identical parallel machines," European Journal of Operational Research, Elsevier, vol. 167(2), pages 283-296, December.
    3. C N Potts & V A Strusevich, 2009. "Fifty years of scheduling: a survey of milestones," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 60(1), pages 41-68, May.
    4. Og[breve]uz, Ceyda & Sibel Salman, F. & Bilgintürk YalçIn, Zehra, 2010. "Order acceptance and scheduling decisions in make-to-order systems," International Journal of Production Economics, Elsevier, vol. 125(1), pages 200-211, May.
    5. Hinder, Oliver & Mason, Andrew J., 2017. "A novel integer programing formulation for scheduling with family setup times on a single machine to minimize maximum lateness," European Journal of Operational Research, Elsevier, vol. 262(2), pages 411-423.
    6. Rego, César & Duarte, Renato, 2009. "A filter-and-fan approach to the job shop scheduling problem," European Journal of Operational Research, Elsevier, vol. 194(3), pages 650-662, May.
    7. Valente, Jorge M.S., 2007. "Improving the performance of the ATC dispatch rule by using workload data to determine the lookahead parameter value," International Journal of Production Economics, Elsevier, vol. 106(2), pages 563-573, April.
    8. Jorge M. S. Valente, 2007. "Beam search heuristics for the single machine scheduling problem with linear earliness and quadratic tardiness costs," FEP Working Papers 250, Universidade do Porto, Faculdade de Economia do Porto.
    9. Grundel, Soesja & Çiftçi, Barış & Borm, Peter & Hamers, Herbert, 2013. "Family sequencing and cooperation," European Journal of Operational Research, Elsevier, vol. 226(3), pages 414-424.
    10. D Biskup & M Feldmann, 2006. "Lot streaming with variable sublots: an integer programming formulation," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 57(3), pages 296-303, March.
    11. Schaller, Jeffrey, 2007. "Scheduling on a single machine with family setups to minimize total tardiness," International Journal of Production Economics, Elsevier, vol. 105(2), pages 329-344, February.
    12. Mujawar, Sachin & Huang, Simin & Nagi, Rakesh, 2012. "Scheduling to minimize stringer utilization for continuous annealing operations," Omega, Elsevier, vol. 40(4), pages 437-444.
    13. Sabuncuoglu, Ihsan & Gocgun, Yasin & Erel, Erdal, 2008. "Backtracking and exchange of information: Methods to enhance a beam search algorithm for assembly line scheduling," European Journal of Operational Research, Elsevier, vol. 186(3), pages 915-930, May.
    14. Ciavotta, Michele & Detti, Paolo & Meloni, Carlo & Pranzo, Marco, 2008. "A bi-objective coordination setup problem in a two-stage production system," European Journal of Operational Research, Elsevier, vol. 189(3), pages 734-745, September.
    15. Allahverdi, Ali & Gupta, Jatinder N. D. & Aldowaisan, Tariq, 1999. "A review of scheduling research involving setup considerations," Omega, Elsevier, vol. 27(2), pages 219-239, April.
    16. Xi, Yue & Jang, Jaejin, 2012. "Scheduling jobs on identical parallel machines with unequal future ready time and sequence dependent setup: An experimental study," International Journal of Production Economics, Elsevier, vol. 137(1), pages 1-10.
    17. Quadt, Daniel & Kuhn, Heinrich, 2007. "Batch scheduling of jobs with identical process times on flexible flow lines," International Journal of Production Economics, Elsevier, vol. 105(2), pages 385-401, February.
    18. Lele Zhang & Andrew Wirth, 2016. "Online Machine Scheduling with Family Setups," Asia-Pacific Journal of Operational Research (APJOR), World Scientific Publishing Co. Pte. Ltd., vol. 33(04), pages 1-16, August.
    19. Shim, Sang-Oh & Kim, Yeong-Dae, 2007. "Scheduling on parallel identical machines to minimize total tardiness," European Journal of Operational Research, Elsevier, vol. 177(1), pages 135-146, February.
    20. Dolgui, Alexandre & Kovalev, Sergey & Kovalyov, Mikhail Y. & Nossack, Jenny & Pesch, Erwin, 2014. "Minimizing setup costs in a transfer line design problem with sequential operation processing," International Journal of Production Economics, Elsevier, vol. 151(C), pages 186-194.

    More about this item

    Keywords

    scheduling; weighted tardiness; sequence-dependent setups; beam search;
    All these keywords.

    NEP fields

    This paper has been announced in the following NEP Reports:

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:por:fepwps:186. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: the person in charge (email available below). General contact details of provider: https://edirc.repec.org/data/fepuppt.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.