Explaining cost overruns in infrastructural projects: A new framework with applications to Sweden

Author

Listed:
  • Brunes, Fredrik

    (Department of Real Estate and Construction Management, Royal Institute of Technology)

  • Lind, Hans

    (Department of Real Estate and Construction Management, Royal Institute of Technology)

Abstract

The first part of the article presents a new framework for analyzing cost overruns. It has a descriptive part in two dimensions: when during the process that the cost overrun arose and what part of the cost function was responsible (change in the product, change in quantities of the inputs and change in price of inputs. The explanatory part is a development of Flyvbjerg´s theories and identifies four possible explanations: political/strategic aspects, psychological aspects, competence related and bad luck. It is argued that Flyvbjerg´s technological explanation belongs to the descriptive part. The empirical part of the paper uses this framework to analyze cost overruns in infrastructure projects in Sweden, primarily based on a questionnaire to experienced project managers. The results is that most of the cost overruns occur in the planning stages up to the final design and are related to design changes and to increases in the amount of inputs needed because of technical and administrative problems. Of the explanatory factors there is most support for lack of competence and optimism bias.

Suggested Citation

  • Brunes, Fredrik & Lind, Hans, 2014. "Explaining cost overruns in infrastructural projects: A new framework with applications to Sweden," Working Paper Series 14/1, Royal Institute of Technology, Department of Real Estate and Construction Management & Banking and Finance.
  • Handle: RePEc:hhs:kthrec:2014_001
    as

    Download full text from publisher

    File URL: http://kth.diva-portal.org/smash/get/diva2:706121/FULLTEXT01.pdf
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Cantarelli, C.C. & van Wee, B. & Molin, E.J.E. & Flyvbjerg, B., 2012. "Different cost performance: different determinants?," Transport Policy, Elsevier, vol. 22(C), pages 88-95.
    2. Chantal C. Cantarelli & Caspar G. Chorus & Scott W. Cunningham, 2013. "Explaining Cost Overruns of Large-Scale Transportation Infrastructure Projects using a Signalling Game," Papers 1307.2180, arXiv.org.
    3. Cantarelli, C.C. & Molin, E.J.E. & van Wee, B. & Flyvbjerg, B., 2012. "Characteristics of cost overruns for Dutch transport infrastructure projects and the importance of the decision to build and project phases," Transport Policy, Elsevier, vol. 22(C), pages 49-56.
    4. Cantarelli, C.C. & Flyvbjerg, B. & Buhl, S.L., 2012. "Geographical variation in project cost performance: the Netherlands versus worldwide," Journal of Transport Geography, Elsevier, vol. 24(C), pages 324-331.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Temitope Seun Omotayo & Bankole Awuzie & Valerie Kenechukwu Obi & Saheed Ajayi & Lovelin Ifeoma Obi & Oluyomi Osobajo & Adekunle Oke, 2022. "The System Dynamics Analysis of Cost Overrun Causations in UK Rail Projects in a COVID-19 Epidemic Era," SAGE Open, , vol. 12(2), pages 21582440221, May.
    2. Borg, Lena & Lind, Hans, 2014. "Framework for Structuring Procurement Contracts," Working Paper Series 14/9, Royal Institute of Technology, Department of Real Estate and Construction Management & Banking and Finance.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Verweij, Stefan & van Meerkerk, Ingmar & Korthagen, Iris A., 2015. "Reasons for contract changes in implementing Dutch transportation infrastructure projects: An empirical exploration," Transport Policy, Elsevier, vol. 37(C), pages 195-202.
    2. Love, Peter E.D. & Zhou, Jingyang & Edwards, David J. & Irani, Zahir & Sing, Chun-Pong, 2017. "Off the rails: The cost performance of infrastructure rail projects," Transportation Research Part A: Policy and Practice, Elsevier, vol. 99(C), pages 14-29.
    3. Chong, Uven & Hopkins, Omar, 2016. "An international experience on the evolution of road costs during the project life cycle," Transport Policy, Elsevier, vol. 48(C), pages 60-66.
    4. Flyvbjerg, Bent & Ansar, Atif & Budzier, Alexander & Buhl, Søren & Cantarelli, Chantal & Garbuio, Massimo & Glenting, Carsten & Holm, Mette Skamris & Lovallo, Dan & Lunn, Daniel & Molin, Eric & Rønnes, 2018. "Five things you should know about cost overrun," Transportation Research Part A: Policy and Practice, Elsevier, vol. 118(C), pages 174-190.
    5. Dejan Makovšek & Marian Moszoro, 2018. "Risk pricing inefficiency in public–private partnerships," Transport Reviews, Taylor & Francis Journals, vol. 38(3), pages 298-321, May.
    6. Love, Peter E.D. & Ahiaga-Dagbui, Dominic D. & Irani, Zahir, 2016. "Cost overruns in transportation infrastructure projects: Sowing the seeds for a probabilistic theory of causation," Transportation Research Part A: Policy and Practice, Elsevier, vol. 92(C), pages 184-194.
    7. Cavalieri, Marina & Cristaudo, Rossana & Guccio, Calogero, 2019. "On the magnitude of cost overruns throughout the project life-cycle: An assessment for the Italian transport infrastructure projects," Transport Policy, Elsevier, vol. 79(C), pages 21-36.
    8. Servranckx, Tom & Vanhoucke, Mario & Aouam, Tarik, 2021. "Practical application of reference class forecasting for cost and time estimations: Identifying the properties of similarity," European Journal of Operational Research, Elsevier, vol. 295(3), pages 1161-1179.
    9. Miranda Sarmento, J.J., 2014. "Public private partnerships," Other publications TiSEM c7d4c978-234c-4f88-83ed-1, Tilburg University, School of Economics and Management.
    10. Makovšek, Dejan, 2014. "Systematic construction risk, cost estimation mechanism and unit price movements," Transport Policy, Elsevier, vol. 35(C), pages 135-145.
    11. Abeysekara, Baudhi & Perera, Piyaruwan & Chhipi Shrestha, Gyan Kumar & Gunaruwan, Lalithasiri & Kumarage, Amal & Sadiq, Rehan & Hewage, Kasun, 2021. "Improving the capital deployment efficiency: An infrastructure investment planning process in transportation project," Research in Transportation Economics, Elsevier, vol. 88(C).
    12. Jarosław Górecki & Manuel Díaz-Madroñero, 2020. "Who Risks and Wins?—Simulated Cost Variance in Sustainable Construction Projects," Sustainability, MDPI, vol. 12(8), pages 1-31, April.
    13. Miranda Sarmento, J.J. & Renneboog, Luc, 2017. "Cost overruns in public sector investment projects," Other publications TiSEM 51799a3e-4c78-4dbd-b330-b, Tilburg University, School of Economics and Management.
    14. Francisco Pinheiro Catalão & Carlos Oliveira Cruz & Joaquim Miranda Sarmento, 2023. "The entanglement of time and cost deviations in public projects," Annals of Public and Cooperative Economics, Wiley Blackwell, vol. 94(1), pages 241-272, March.
    15. Love, Peter E.D. & Ahiaga-Dagbui, Dominic D., 2018. "Debunking fake news in a post-truth era: The plausible untruths of cost underestimation in transport infrastructure projects," Transportation Research Part A: Policy and Practice, Elsevier, vol. 113(C), pages 357-368.
    16. Saule Baurzhan & Glenn P. Jenkins & Godwin O. Olasehinde-Williams, 2021. "The Economic Performance of Hydropower Dams Supported by the World Bank Group, 1975–2015," Energies, MDPI, vol. 14(9), pages 1-22, May.
    17. Saule Baurzhan & Glenn Jenkins & Godwin O. Olasehinde-Williams, 2021. "The Economic Performance of Hydropower Dams Supported by the World Bank Group, 1975–2015," Working Paper 1463, Economics Department, Queen's University.
    18. Molinari, Laura & Haezendonck, Elvira & Mabillard, Vincent, 2023. "Cost overruns of Belgian transport infrastructure projects: Analyzing variations over three land transport modes and two project phases," Transport Policy, Elsevier, vol. 134(C), pages 167-179.
    19. Love, Peter E.D. & Sing, Michael C.P. & Ika, Lavagnon A. & Newton, Sidney, 2019. "The cost performance of transportation projects: The fallacy of the Planning Fallacy account," Transportation Research Part A: Policy and Practice, Elsevier, vol. 122(C), pages 1-20.
    20. Steininger, Bertram & Groth, Martin & Weber, Birgitte, 2020. "Cost overruns and delays in infrastructure projects: the case of Stuttgart 21," Working Paper Series 20/11, Royal Institute of Technology, Department of Real Estate and Construction Management & Banking and Finance.

    More about this item

    Keywords

    cost overrun; theoretical framework; infrastructure; Sweden;
    All these keywords.

    JEL classification:

    • L21 - Industrial Organization - - Firm Objectives, Organization, and Behavior - - - Business Objectives of the Firm
    • L24 - Industrial Organization - - Firm Objectives, Organization, and Behavior - - - Contracting Out; Joint Ventures
    • L32 - Industrial Organization - - Nonprofit Organizations and Public Enterprise - - - Public Enterprises; Public-Private Enterprises

    NEP fields

    This paper has been announced in the following NEP Reports:

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:hhs:kthrec:2014_001. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Cecilia Hermansson (email available below). General contact details of provider: https://edirc.repec.org/data/ifkthse.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.