Cost Uncertainty and Time Overruns in Public Procurement: a Scoring Auction for a Contract with Delay Penalties

Author

Listed:
  • Cesare Dosi

    (University of Padova and Centro di Ricerca Interuniversitario sull’Economia Pubblica (CRIEP))

  • Michele Moretto

    (University of Padova and Fondazione Eni Enrico Mattei (FEEM))

Abstract

Drawing on the real-options theory we analyse bidding behaviour in a sealed-bid-first-score procurement auction where suppliers, facing variable production costs, must simultaneously report the contract price and the cost level at which they intend to perform the project. We show that this award mechanism is potentially able to maximize total welfare. Next we look at the time incentives required to ensure compliance with the promised optimal trigger value. We show that ex-post efficiency may call for delay penalties higher than the anticipated harm caused by time overruns, in so doing questioning the efficiency rationale of existing liquidated damages rules.

Suggested Citation

  • Cesare Dosi & Michele Moretto, 2017. "Cost Uncertainty and Time Overruns in Public Procurement: a Scoring Auction for a Contract with Delay Penalties," Working Papers 2017.02, Fondazione Eni Enrico Mattei.
  • Handle: RePEc:fem:femwpa:2017.02
    as

    Download full text from publisher

    File URL: https://feem-media.s3.eu-central-1.amazonaws.com/wp-content/uploads/NDL2017-002.pdf
    Download Restriction: no
    ---><---

    Other versions of this item:

    References listed on IDEAS

    as
    1. Ottorino Chillemi & Claudio Mezzetti, 2014. "Optimal procurement mechanisms: bidding on price and damages for breach," Economic Theory, Springer;Society for the Advancement of Economic Theory (SAET), vol. 55(2), pages 335-355, February.
    2. Triantis, Alexander J & Triantis, George G, 1998. "Timing Problems in Contract Breach Decisions," Journal of Law and Economics, University of Chicago Press, vol. 41(1), pages 163-207, April.
    3. Cesare Dosi & Michele Moretto, 2015. "Procurement with Unenforceable Contract Time and the Law of Liquidated Damages," The Journal of Law, Economics, and Organization, Oxford University Press, vol. 31(1), pages 160-186.
    4. Yeon-Koo Che, 1993. "Design Competition through Multidimensional Auctions," RAND Journal of Economics, The RAND Corporation, vol. 24(4), pages 668-680, Winter.
    5. Gregory Lewis & Patrick Bajari, 2014. "Moral Hazard, Incentive Contracts, and Risk: Evidence from Procurement," The Review of Economic Studies, Review of Economic Studies Ltd, vol. 81(3), pages 1201-1228.
    6. Spagnolo, Giancarlo & Calzolari, Giacomo, 2009. "Relational Contracts and Competitive Screening," CEPR Discussion Papers 7434, C.E.P.R. Discussion Papers.
    7. Aaron S. Edlin & Alan Schwartz, 2003. "Optimal Penalties in Contracts," Law and Economics 0303002, University Library of Munich, Germany.
    8. Andrew Postlewaite, 2007. "Courts of Law and Unforeseen Contingencies," The Journal of Law, Economics, and Organization, Oxford University Press, vol. 23(3), pages 662-684, October.
    9. Decio Coviello & Luigi Moretti & Giancarlo Spagnolo & Paola Valbonesi, 2018. "Court Efficiency and Procurement Performance," Scandinavian Journal of Economics, Wiley Blackwell, vol. 120(3), pages 826-858, July.
    10. S. Ping Ho & Liang Liu, 2002. "An option pricing-based model for evaluating the financial viability of privatized infrastructure projects," Construction Management and Economics, Taylor & Francis Journals, vol. 20(2), pages 143-156.
    11. Chiara D’Alpaos & Michele Moretto & Paola Valbonesi & Sergio Vergalli, 2013. "Time overruns as opportunistic behavior in public procurement," Journal of Economics, Springer, vol. 110(1), pages 25-43, September.
    12. Avinash K. Dixit & Robert S. Pindyck, 1994. "Investment under Uncertainty," Economics Books, Princeton University Press, edition 1, number 5474.
    13. Abhijit V. Banerjee & Esther Duflo, 2000. "Reputation Effects and the Limits of Contracting: A Study of the Indian Software Industry," The Quarterly Journal of Economics, President and Fellows of Harvard College, vol. 115(3), pages 989-1017.
    14. Waehrer Keith, 1995. "A Model of Auction Contracts with Liquidated Damages," Journal of Economic Theory, Elsevier, vol. 67(2), pages 531-555, December.
    15. De Silva, Dakshina G. & Dunne, Timothy & Kankanamge, Anuruddha & Kosmopoulou, Georgia, 2008. "The impact of public information on bidding in highway procurement auctions," European Economic Review, Elsevier, vol. 52(1), pages 150-181, January.
    16. David Ford & Diane Lander & John Voyer, 2002. "A real options approach to valuing strategic flexibility in uncertain construction projects," Construction Management and Economics, Taylor & Francis Journals, vol. 20(4), pages 343-351.
    17. Spagnolo, Giancarlo, 2012. "Reputation, competition, and entry in procurement," International Journal of Industrial Organization, Elsevier, vol. 30(3), pages 291-296.
    18. Gregory Lewis & Patrick Bajari, 2011. "Procurement Contracting With Time Incentives: Theory and Evidence," The Quarterly Journal of Economics, President and Fellows of Harvard College, vol. 126(3), pages 1173-1211.
    19. Manelli, Alejandro M & Vincent, Daniel R, 1995. "Optimal Procurement Mechanisms," Econometrica, Econometric Society, vol. 63(3), pages 591-620, May.
    20. Michael Garvin & Charles Cheah, 2004. "Valuation techniques for infrastructure investment decisions," Construction Management and Economics, Taylor & Francis Journals, vol. 22(4), pages 373-383.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Cesare Dosi & Michele Moretto, 2017. "Cost Uncertainty and Time Overruns in Public Procurement: a Scoring Auction for a Contract with Delay Penalties," Working Papers 2017.02, Fondazione Eni Enrico Mattei.
    2. Di Corato, Luca & Dosi, Cesare & Moretto, Michele, 2018. "Multidimensional auctions for long-term procurement contracts with early-exit options: The case of conservation contracts," European Journal of Operational Research, Elsevier, vol. 267(1), pages 368-380.
    3. Di Corato, Luca & Dosi, Cesare & Moretto, Michele, 2015. "Multidimensional auctions for long-term procurement contracts under the threat of early exit: the case of conservation auctions," Working Paper Series 2015:6, Swedish University of Agricultural Sciences, Department Economics.
    4. Cesare Dosi & Michele Moretto, 2015. "Procurement with Unenforceable Contract Time and the Law of Liquidated Damages," The Journal of Law, Economics, and Organization, Oxford University Press, vol. 31(1), pages 160-186.
    5. Chiara D’Alpaos & Michele Moretto & Paola Valbonesi & Sergio Vergalli, 2013. "Time overruns as opportunistic behavior in public procurement," Journal of Economics, Springer, vol. 110(1), pages 25-43, September.
    6. Decio Coviello & Andrea Guglielmo & Giancarlo Spagnolo, 2018. "The Effect of Discretion on Procurement Performance," Management Science, INFORMS, vol. 64(2), pages 715-738, February.
    7. Bergman, Mats A. & Johansson, Per & Lundberg, Sofia & Spagnolo, Giancarlo, 2016. "Privatization and quality: Evidence from elderly care in Sweden," Journal of Health Economics, Elsevier, vol. 49(C), pages 109-119.
    8. Decio Coviello & Andrea Guglielmo & Giancarlo Spagnolo, 2015. "The Effect of Discretion on Procurement Performance," CEIS Research Paper 361, Tor Vergata University, CEIS, revised 17 Nov 2015.
    9. Indranil Chakraborty & Fahad Khalil & Jacques Lawarree, 2021. "Competitive procurement with ex post moral hazard," RAND Journal of Economics, RAND Corporation, vol. 52(1), pages 179-206, March.
    10. Nicholas Ryan, 2020. "Contract Enforcement and Productive Efficiency: Evidence From the Bidding and Renegotiation of Power Contracts in India," Econometrica, Econometric Society, vol. 88(2), pages 383-424, March.
    11. D'Alpaos, Chiara & Moretto, Michele & Valbonesi, Paola & Vergalli, Sergio, 2009. ""It Is Never too late": Optimal Penalty for Investment Delay in Public Procurement Contracts," Institutions and Markets Papers 54351, Fondazione Eni Enrico Mattei (FEEM).
    12. Werner Hölzl & Michael Böheim & Michael Klien & Eva Pichler, 2017. "Das öffentliche Beschaffungswesen im Spannungsfeld zwischen Billigst- und Bestbieterprinzip," WIFO Studies, WIFO, number 59256.
    13. Bergantiños, Gustavo & Lorenzo, Leticia, 2019. "How to apply penalties to avoid delays in projects," European Journal of Operational Research, Elsevier, vol. 275(2), pages 608-620.
    14. Leonardo M. Giuffrida & Gabriele Rovigatti, 2017. "Can the Private Sector Ensure the Public Interest? Evidence from Federal Procurement," CEIS Research Paper 411, Tor Vergata University, CEIS, revised 20 Jul 2017.
    15. Emery, Thomas & Mélon, Lela & Spruk, Rok, 2023. "Does e-procurement matter for economic growth? Subnational evidence from Australia," The Quarterly Review of Economics and Finance, Elsevier, vol. 89(C), pages 318-334.
    16. Giuseppe Francesco Gori & Patrizia Lattarulo & Marco Mariani, 2021. "The Expediting Effect of Monitoring on Infrastructural Works. A Regression-Discontinuity Approach with Multiple Assignment Variables," Papers 2102.09625, arXiv.org.
    17. Giuseppe Gori & Patrizia Lattarulo & Marco Mariani, 2014. "The effect of Regional Law 35/2011 on strategic public works," Studi e approfondimenti 521, Istituto Regionale per la Programmazione Economica della Toscana.
    18. Kim, Amy M. & Li, Huanan, 2020. "Incorporating the impacts of climate change in transportation infrastructure decision models," Transportation Research Part A: Policy and Practice, Elsevier, vol. 134(C), pages 271-287.
    19. Author-Name: Luca Di Corato & Cesare Dosi & Michele Moretto, 2014. "Bidding for Conservation Contracts," Working Papers 2014.65, Fondazione Eni Enrico Mattei.
    20. Calogero Guccio & Domenico Lisi & Ilde Rizzo, 2019. "When the purchasing officer looks the other way: on the waste effects of debauched local environment in public works execution," Economics of Governance, Springer, vol. 20(3), pages 205-236, September.

    More about this item

    Keywords

    Public Procurement; Fixed-price Contracts; Real Options; Time Overruns; Scoring Auctions; Liquidated Damages;
    All these keywords.

    JEL classification:

    • C61 - Mathematical and Quantitative Methods - - Mathematical Methods; Programming Models; Mathematical and Simulation Modeling - - - Optimization Techniques; Programming Models; Dynamic Analysis
    • D44 - Microeconomics - - Market Structure, Pricing, and Design - - - Auctions
    • D86 - Microeconomics - - Information, Knowledge, and Uncertainty - - - Economics of Contract Law
    • K12 - Law and Economics - - Basic Areas of Law - - - Contract Law

    NEP fields

    This paper has been announced in the following NEP Reports:

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:fem:femwpa:2017.02. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Alberto Prina Cerai (email available below). General contact details of provider: https://edirc.repec.org/data/feemmit.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.