Scheduling semiconductor test operations: Minimizing maximum lateness and number of tardy jobs on a single machine
Author
Abstract
Suggested Citation
DOI: 10.1002/1520-6750(199204)39:33.0.CO;2-F
Download full text from publisher
References listed on IDEAS
- E. L. Lawler & J. M. Moore, 1969. "A Functional Equation and its Application to Resource Allocation and Sequencing Problems," Management Science, INFORMS, vol. 16(1), pages 77-84, September.
- E. L. Lawler, 1973. "Optimal Sequencing of a Single Machine Subject to Precedence Constraints," Management Science, INFORMS, vol. 19(5), pages 544-546, January.
- B. J. Lageweg & J. K. Lenstra & A. H. G. Rinnooy Kan, 1976. "Minimizing maximum lateness on one machine: computational experience and some applications," Statistica Neerlandica, Netherlands Society for Statistics and Operations Research, vol. 30(1), pages 25-41, March.
- Kenneth R. Baker & Zaw‐Sing Su, 1974. "Sequencing with due‐dates and early start times to minimize maximum tardiness," Naval Research Logistics Quarterly, John Wiley & Sons, vol. 21(1), pages 171-176, March.
- C. N. Potts, 1980. "Technical Note—Analysis of a Heuristic for One Machine Sequencing with Release Dates and Delivery Times," Operations Research, INFORMS, vol. 28(6), pages 1436-1441, December.
- Graham McMahon & Michael Florian, 1975. "On Scheduling with Ready Times and Due Dates to Minimize Maximum Lateness," Operations Research, INFORMS, vol. 23(3), pages 475-482, June.
- Jean-Claude Picard & Maurice Queyranne, 1978. "The Time-Dependent Traveling Salesman Problem and Its Application to the Tardiness Problem in One-Machine Scheduling," Operations Research, INFORMS, vol. 26(1), pages 86-110, February.
Citations
Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
Cited by:
- Koulamas, Christos & Kyparisis, George J., 2023. "A classification of dynamic programming formulations for offline deterministic single-machine scheduling problems," European Journal of Operational Research, Elsevier, vol. 305(3), pages 999-1017.
- Yu, Tae-Sun & Han, Jun-Hee, 2021. "Scheduling proportionate flow shops with preventive machine maintenance," International Journal of Production Economics, Elsevier, vol. 231(C).
Most related items
These are the items that most often cite the same works as this one and are cited by the same works as this one.- Wenda Zhang & Jason J. Sauppe & Sheldon H. Jacobson, 2021. "An Improved Branch-and-Bound Algorithm for the One-Machine Scheduling Problem with Delayed Precedence Constraints," INFORMS Journal on Computing, INFORMS, vol. 33(3), pages 1091-1102, July.
- Rubing Chen & Jinjiang Yuan, 2020. "Single-machine scheduling of proportional-linearly deteriorating jobs with positional due indices," 4OR, Springer, vol. 18(2), pages 177-196, June.
- Briskorn, Dirk & Davari, Morteza & Matuschke, Jannik, 2021. "Single-machine scheduling with an external resource," European Journal of Operational Research, Elsevier, vol. 293(2), pages 457-468.
- Alexander A. Lazarev & Nikolay Pravdivets & Frank Werner, 2020. "On the Dual and Inverse Problems of Scheduling Jobs to Minimize the Maximum Penalty," Mathematics, MDPI, vol. 8(7), pages 1-15, July.
- Dauzere-Peres, Stephane, 1995. "A procedure for the one-machine sequencing problem with dependent jobs," European Journal of Operational Research, Elsevier, vol. 81(3), pages 579-589, March.
- Tzafestas, Spyros & Triantafyllakis, Alekos, 1993. "Deterministic scheduling in computing and manufacturing systems: a survey of models and algorithms," Mathematics and Computers in Simulation (MATCOM), Elsevier, vol. 35(5), pages 397-434.
- Lancia, Giuseppe, 2000. "Scheduling jobs with release dates and tails on two unrelated parallel machines to minimize the makespan," European Journal of Operational Research, Elsevier, vol. 120(2), pages 277-288, January.
- Lushchakova, Irene N., 2000. "Minimizing functions of infeasibilities in a two-machine flow shop," European Journal of Operational Research, Elsevier, vol. 121(2), pages 380-393, March.
- Liang-Liang Fu & Mohamed Ali Aloulou & Christian Artigues, 2018. "Integrated production and outbound distribution scheduling problems with job release dates and deadlines," Journal of Scheduling, Springer, vol. 21(4), pages 443-460, August.
- Blazewicz, Jacek & Domschke, Wolfgang & Pesch, Erwin, 1996. "The job shop scheduling problem: Conventional and new solution techniques," European Journal of Operational Research, Elsevier, vol. 93(1), pages 1-33, August.
- Stanisław Gawiejnowicz, 2020. "A review of four decades of time-dependent scheduling: main results, new topics, and open problems," Journal of Scheduling, Springer, vol. 23(1), pages 3-47, February.
- Pan, Yunpeng & Shi, Leyuan, 2006. "Branch-and-bound algorithms for solving hard instances of the one-machine sequencing problem," European Journal of Operational Research, Elsevier, vol. 168(3), pages 1030-1039, February.
- C N Potts & V A Strusevich, 2009. "Fifty years of scheduling: a survey of milestones," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 60(1), pages 41-68, May.
- Bachtenkirch, David & Bock, Stefan, 2022. "Finding efficient make-to-order production and batch delivery schedules," European Journal of Operational Research, Elsevier, vol. 297(1), pages 133-152.
- Federico Alonso-Pecina & José Alberto Hernández & José Maria Sigarreta & Nodari Vakhania, 2020. "Fast Approximation for Scheduling One Machine," Mathematics, MDPI, vol. 8(9), pages 1-18, September.
- Cheng, T. C. E. & Ng, C. T. & Yuan, J. J. & Liu, Z. H., 2005. "Single machine scheduling to minimize total weighted tardiness," European Journal of Operational Research, Elsevier, vol. 165(2), pages 423-443, September.
- Philip Kaminsky, 2003. "The effectiveness of the longest delivery time rule for the flow shop delivery time problem," Naval Research Logistics (NRL), John Wiley & Sons, vol. 50(3), pages 257-272, April.
- Shabtay, Dvir, 2016. "Optimal restricted due date assignment in scheduling," European Journal of Operational Research, Elsevier, vol. 252(1), pages 79-89.
- Florian Jaehn & Helmut A. Sedding, 2016. "Scheduling with time-dependent discrepancy times," Journal of Scheduling, Springer, vol. 19(6), pages 737-757, December.
- Stanisław Gawiejnowicz & Alexander Kononov, 2014. "Isomorphic scheduling problems," Annals of Operations Research, Springer, vol. 213(1), pages 131-145, February.
Corrections
All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:wly:navres:v:39:y:1992:i:3:p:369-388. See general information about how to correct material in RePEc.
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.
For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Wiley Content Delivery (email available below). General contact details of provider: https://doi.org/10.1002/(ISSN)1520-6750 .
Please note that corrections may take a couple of weeks to filter through the various RePEc services.