Enhanced heuristic for finance-based scheduling of construction projects

Author

Listed:
  • Yuvraj Gajpal
  • Ashraf Elazouni

Abstract

Typically, construction contractors operate under cash-constrained operating conditions. The lag between the time when contractors spend money to accomplish work on site and the time when payments are actually made by clients, which partially compensate contractors for the accomplished work, constantly creates a finance deficit. Contractors often supplement finance deficits using external funds procured through establishing credit-line bank accounts which typically allow contractors to withdraw cash up to specified credit limits. This makes the task of project scheduling considering the constraints of specified finance very important for financial and operational planning. This scheduling concept and technique are referred to as finance-based scheduling. An enhanced heuristic is proposed to devise finance-based schedules of multiple projects within contractors' portfolios. The enhancement is achieved by replacing the exhaustive enumeration technique employed in the heuristic to specify activities' start times with a polynomial shifting algorithm. This enhancement resulted in a substantial reduction in the number of solutions explored before a feasible solution is encountered. The enhanced heuristic was validated through comparison with the integer programming technique using 240 problems of randomly generated networks of sizes that range from 30 to 240 activities. Further, it was proved that the enhanced heuristic can be easily scaled up to handle portfolios of multiple large-size projects.

Suggested Citation

  • Yuvraj Gajpal & Ashraf Elazouni, 2015. "Enhanced heuristic for finance-based scheduling of construction projects," Construction Management and Economics, Taylor & Francis Journals, vol. 33(7), pages 531-553, July.
  • Handle: RePEc:taf:conmgt:v:33:y:2015:i:7:p:531-553
    DOI: 10.1080/01446193.2015.1063676
    as

    Download full text from publisher

    File URL: http://hdl.handle.net/10.1080/01446193.2015.1063676
    Download Restriction: Access to full text is restricted to subscribers.

    File URL: https://libkey.io/10.1080/01446193.2015.1063676?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Mohammed Mubashir Ali & Ashraf Elazouni, 2009. "Finance-based CPM/LOB scheduling of projects with repetitive non-serial activities," Construction Management and Economics, Taylor & Francis Journals, vol. 27(9), pages 839-856.
    2. Hong Zhang & Heng Li & C. M. Tam, 2006. "Heuristic scheduling of resource-constrained, multiple-mode and repetitive projects," Construction Management and Economics, Taylor & Francis Journals, vol. 24(2), pages 159-169.
    3. Lihua He & Lianying Zhang, 2013. "Dynamic priority rule-based forward-backward heuristic algorithm for resource levelling problem in construction project," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 64(8), pages 1106-1117, August.
    4. Bhaskar, Tarun & Pal, Manabendra N. & Pal, Asim K., 2011. "A heuristic method for RCPSP with fuzzy activity times," European Journal of Operational Research, Elsevier, vol. 208(1), pages 57-66, January.
    5. Robert A. Russell, 1986. "A Comparison of Heuristics for Scheduling Projects with Cash Flows and Resource Restrictions," Management Science, INFORMS, vol. 32(10), pages 1291-1300, October.
    6. Neumann, K. & Zimmermann, J., 1999. "Resource levelling for projects with schedule-dependent time windows," European Journal of Operational Research, Elsevier, vol. 117(3), pages 591-605, September.
    7. Ashraf Elazouni, 2009. "Heuristic method for multi-project finance-based scheduling," Construction Management and Economics, Taylor & Francis Journals, vol. 27(2), pages 199-211.
    8. A. H. Russell, 1970. "Cash Flows in Networks," Management Science, INFORMS, vol. 16(5), pages 357-373, January.
    9. Ranjbar, Mohammad & De Reyck, Bert & Kianfar, Fereydoon, 2009. "A hybrid scatter search for the discrete time/resource trade-off problem in project scheduling," European Journal of Operational Research, Elsevier, vol. 193(1), pages 35-48, February.
    10. Huan Neng Chiu & Deng Maw Tsai, 2002. "An efficient search procedure for the resource-constrained multi-project scheduling problem with discounted cash flows," Construction Management and Economics, Taylor & Francis Journals, vol. 20(1), pages 55-66.
    11. M.L. Mittal & Arun Kanda, 2009. "Two-phase heuristics for scheduling of multiple projects," International Journal of Operational Research, Inderscience Enterprises Ltd, vol. 4(2), pages 159-177.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Mahir Msawil & Faris Elghaish & Krisanthi Seneviratne & Stephen McIlwaine, 2021. "Developing a Parametric Cash Flow Forecasting Model for Complex Infrastructure Projects: A Comparative Study," Sustainability, MDPI, vol. 13(20), pages 1-26, October.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Ashraf Elazouni, 2009. "Heuristic method for multi-project finance-based scheduling," Construction Management and Economics, Taylor & Francis Journals, vol. 27(2), pages 199-211.
    2. He, Zhengwen & Wang, Nengmin & Jia, Tao & Xu, Yu, 2009. "Simulated annealing and tabu search for multi-mode project payment scheduling," European Journal of Operational Research, Elsevier, vol. 198(3), pages 688-696, November.
    3. Hongbo Li & Linwen Zheng & Hanyu Zhu, 2023. "Resource leveling in projects with flexible structures," Annals of Operations Research, Springer, vol. 321(1), pages 311-342, February.
    4. Herroelen, Willy S. & Van Dommelen, Patrick & Demeulemeester, Erik L., 1997. "Project network models with discounted cash flows a guided tour through recent developments," European Journal of Operational Research, Elsevier, vol. 100(1), pages 97-121, July.
    5. Mika, Marek & Waligora, Grzegorz & Weglarz, Jan, 2005. "Simulated annealing and tabu search for multi-mode resource-constrained project scheduling with positive discounted cash flows and different payment models," European Journal of Operational Research, Elsevier, vol. 164(3), pages 639-668, August.
    6. Nursel Kavlak & Gündüz Ulusoy & Funda Sivrikaya Şerifoğlu & Ş. İlker Birbil, 2009. "Client‐contractor bargaining on net present value in project scheduling with limited resources," Naval Research Logistics (NRL), John Wiley & Sons, vol. 56(2), pages 93-112, March.
    7. Weglarz, Jan & Józefowska, Joanna & Mika, Marek & Waligóra, Grzegorz, 2011. "Project scheduling with finite or infinite number of activity processing modes - A survey," European Journal of Operational Research, Elsevier, vol. 208(3), pages 177-205, February.
    8. Rob Eynde & Mario Vanhoucke, 2020. "Resource-constrained multi-project scheduling: benchmark datasets and decoupled scheduling," Journal of Scheduling, Springer, vol. 23(3), pages 301-325, June.
    9. Kolisch, Rainer & Sprecher, Arno & Drexl, Andreas, 1992. "Characterization and generation of a general class of resource-constrained project scheduling problems: Easy and hard instances," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 301, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    10. Yang, Kum Khiong & Tay, Lee Choo & Sum, Chee Chuong, 1995. "A comparison of stochastic scheduling rules for maximizing project net present value," European Journal of Operational Research, Elsevier, vol. 85(2), pages 327-339, September.
    11. Etgar, Ran & Shtub, Avraham & LeBlanc, Larry J., 1997. "Scheduling projects to maximize net present value -- the case of time-dependent, contingent cash flows," European Journal of Operational Research, Elsevier, vol. 96(1), pages 90-96, January.
    12. Kolisch, R. & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Omega, Elsevier, vol. 29(3), pages 249-272, June.
    13. Mahir Msawil & Faris Elghaish & Krisanthi Seneviratne & Stephen McIlwaine, 2021. "Developing a Parametric Cash Flow Forecasting Model for Complex Infrastructure Projects: A Comparative Study," Sustainability, MDPI, vol. 13(20), pages 1-26, October.
    14. Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
    15. Wenhui Zhao & Nicholas G. Hall & Zhixin Liu, 2020. "Project Evaluation and Selection with Task Failures," Production and Operations Management, Production and Operations Management Society, vol. 29(2), pages 428-446, February.
    16. Bogumiła Krzeszowska, 2013. "Three step procedure for a multiple criteria problem of project portfolio scheduling," Operations Research and Decisions, Wroclaw University of Science and Technology, Faculty of Management, vol. 23(4), pages 55-74.
    17. Neumann, K. & Zimmermann, J., 2000. "Procedures for resource leveling and net present value problems in project scheduling with general temporal and resource constraints," European Journal of Operational Research, Elsevier, vol. 127(2), pages 425-443, December.
    18. Kolisch, Rainer, 1996. "Investitionsplanung in Netzwerken," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 423, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    19. Neumann, K. & Schwindt, C. & Zimmermann, J., 2003. "Order-based neighborhoods for project scheduling with nonregular objective functions," European Journal of Operational Research, Elsevier, vol. 149(2), pages 325-343, September.
    20. Vanhoucke, Mario & Demeulemeester, Erik & Herroelen, Willy, 2003. "Progress payments in project scheduling problems," European Journal of Operational Research, Elsevier, vol. 148(3), pages 604-620, August.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:taf:conmgt:v:33:y:2015:i:7:p:531-553. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Longhurst (email available below). General contact details of provider: http://www.tandfonline.com/RCME20 .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.