Contributors to construction delays

Author

Listed:
  • Mohan Kumaraswamy
  • Daniel Chan

Abstract

Projects can be delayed for a large number of reasons. The third phase of an investigation into such factors focused on the causes of construction delays in Hong Kong. A questionnaire was based on 83 factors identified in previous phases of the investigation. Analysis of the responses reveals differences in perceptions of the relative significance of factors between clients, consultants and contractors. There was general agreement about the relative importance of delay factors such as unforeseen ground conditions. Improving productivity is a useful approach to controlling delays. Important factors affecting productivity itself are thus examined in more depth, with a view to enhancing productivity and reducing delays. The conclusions of this phase of the investigation include a ranking of factors and factor categories that are perceived by different groups of project participants to contribute to delays. For example, higher-ranking factors, such as unforeseen ground conditions, and factor categories such as project-related factors, are found to merit special management attention in countering construction delays. The high degree of disagreement as discerned between the groups of clients, consultants and contractors is indicative of their experiences, possible prejudices and lack of effective communication. It is also confirmed that productivity and other non-scope factors such as effective communications should supplement the project scope factors incorporated into the construction time prediction models that were proposed in the previous phases of this investigation.

Suggested Citation

  • Mohan Kumaraswamy & Daniel Chan, 1998. "Contributors to construction delays," Construction Management and Economics, Taylor & Francis Journals, vol. 16(1), pages 17-29.
  • Handle: RePEc:taf:conmgt:v:16:y:1998:i:1:p:17-29
    DOI: 10.1080/014461998372556
    as

    Download full text from publisher

    File URL: http://www.tandfonline.com/doi/abs/10.1080/014461998372556
    Download Restriction: Access to full text is restricted to subscribers.

    File URL: https://libkey.io/10.1080/014461998372556?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. A. Q. Adeleke & A. Y. Bahaudin & A. M. Kamaruddeen, 2018. "Organizational Internal Factors and Construction Risk Management among Nigerian Construction Companies," Global Business Review, International Management Institute, vol. 19(4), pages 921-938, August.
    2. Adriana Gómez-Cabrera & Amalia Sanz-Benlloch & Laura Montalban-Domingo & Jose Luis Ponz-Tienda & Eugenio Pellicer, 2020. "Identification of Factors Affecting the Performance of Rural Road Projects in Colombia," Sustainability, MDPI, vol. 12(18), pages 1-18, September.
    3. Mekhala Kaluarachchi & Anuradha Waidyasekara & Raufdeen Rameezdeen & Nicholas Chileshe, 2021. "Mitigating Dust Pollution from Construction Activities: A Behavioural Control Perspective," Sustainability, MDPI, vol. 13(16), pages 1-19, August.
    4. Myung-Hun Kim & Eul-Bum Lee, 2019. "A Forecast Model for the Level of Engineering Maturity Impact on Contractor’s Procurement and Construction Costs for Offshore EPC Megaprojects," Energies, MDPI, vol. 12(12), pages 1-18, June.
    5. Goutom K. Pall & Adrian J. Bridge & Jason Gray & Martin Skitmore, 2019. "Causes of Delay in Power Transmission Projects: An Empirical Study," Energies, MDPI, vol. 13(1), pages 1-29, December.
    6. Hemanta Doloi & Anil Sawhney & K.C. Iyer, 2012. "Structural equation model for investigating factors affecting delay in Indian construction projects," Construction Management and Economics, Taylor & Francis Journals, vol. 30(10), pages 869-884, October.
    7. Charles Gyan & Abena Oforiwaa Ampomah, 2016. "Effects of Stakeholder Conflicts on Community Development Projects in Kenyase," SAGE Open, , vol. 6(1), pages 21582440166, March.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:taf:conmgt:v:16:y:1998:i:1:p:17-29. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Longhurst (email available below). General contact details of provider: http://www.tandfonline.com/RCME20 .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.