A fuzzy random integrated inventory model with imperfect production under optimal vendor investment

Author

Listed:
  • Oshmita Dey

    (Techno India University)

Abstract

This article investigates an integrated single-vendor single-buyer production-inventory model with imperfect production under a mixed environment where fuzziness and randomness appear simultaneously. The paper focuses on representing the annual customer demand as a triangular fuzzy number together with an associated probability. A further assumption is that the production process is not perfect and goes ‘out-of-control’ with a certain probability. This causes the vendor, in particular, and the supply chain, in general, to incur an additional warranty cost and also leads to the production of larger batch sizes to compensate the imperfection. In order to avoid these extra costs, the vendor makes an investment to improve the production process quality and hence reduce the number of defective items produced. The expected annual integrated total cost is derived with these assumptions under the n-shipment policy. A methodology is proposed to minimize crisp equivalent of the expected annual integrated total cost so as to obtain the optimal values of the number of shipments, the shipment lot-size, the safety stock factor and the ‘out-of-control’ probability. A numerical example is given to illustrate this proposed methodology and to highlight the advantage of investing in reducing the probability of the production process going ‘out-of-control’.

Suggested Citation

  • Oshmita Dey, 2019. "A fuzzy random integrated inventory model with imperfect production under optimal vendor investment," Operational Research, Springer, vol. 19(1), pages 101-115, March.
  • Handle: RePEc:spr:operea:v:19:y:2019:i:1:d:10.1007_s12351-016-0286-1
    DOI: 10.1007/s12351-016-0286-1
    as

    Download full text from publisher

    File URL: http://link.springer.com/10.1007/s12351-016-0286-1
    File Function: Abstract
    Download Restriction: Access to the full text of the articles in this series is restricted.

    File URL: https://libkey.io/10.1007/s12351-016-0286-1?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Glock, C. H., 2009. "A Comment: "Integrated single vendor single buyer model with stochastic demand and variable lead time"," Publications of Darmstadt Technical University, Institute for Business Studies (BWL) 57828, Darmstadt Technical University, Department of Business Administration, Economics and Law, Institute for Business Studies (BWL).
    2. Huang, Chao-Kuei, 2004. "An optimal policy for a single-vendor single-buyer integrated production-inventory problem with process unreliability consideration," International Journal of Production Economics, Elsevier, vol. 91(1), pages 91-98, September.
    3. Gour Chandra Mahata, 2015. "An integrated production-inventory model with backorder and lot for lot policy in fuzzy sense," International Journal of Mathematics in Operational Research, Inderscience Enterprises Ltd, vol. 7(1), pages 69-102.
    4. Ouyang, Liang-Yuh & Wu, Kun-Shan & Ho, Chia-Huei, 2007. "An integrated vendor-buyer inventory model with quality improvement and lead time reduction," International Journal of Production Economics, Elsevier, vol. 108(1-2), pages 349-358, July.
    5. Dey, Oshmita & Chakraborty, Debjani, 2011. "A fuzzy random continuous review inventory system," International Journal of Production Economics, Elsevier, vol. 132(1), pages 101-106, July.
    6. Glock, Christoph H., 2009. "A comment: "Integrated single vendor-single buyer model with stochastic demand and variable lead time"," International Journal of Production Economics, Elsevier, vol. 122(2), pages 790-792, December.
    7. Lokesh Nagar & Pankaj Dutta & Karuna Jain, 2014. "An integrated supply chain model for new products with imprecise production and supply under scenario dependent fuzzy random demand," International Journal of Systems Science, Taylor & Francis Journals, vol. 45(5), pages 873-887, May.
    8. Glock, C. H., 2012. "Lead time reduction strategies in a single-vendor-single-buyer integrated inventory model with lot size-dependent lead times and stochastic demand," Publications of Darmstadt Technical University, Institute for Business Studies (BWL) 57816, Darmstadt Technical University, Department of Business Administration, Economics and Law, Institute for Business Studies (BWL).
    9. M Ben-Daya & M Hariga, 2000. "Economic lot scheduling problem with imperfect production processes," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 51(7), pages 875-881, July.
    10. Hau L. Lee & Meir J. Rosenblatt, 1987. "Simultaneous Determination of Production Cycle and Inspection Schedules in a Production System," Management Science, INFORMS, vol. 33(9), pages 1125-1136, September.
    11. Chang, Hung-Chi & Yao, Jing-Shing & Ouyang, Liang-Yuh, 2006. "Fuzzy mixture inventory model involving fuzzy random variable lead time demand and fuzzy total demand," European Journal of Operational Research, Elsevier, vol. 169(1), pages 65-80, February.
    12. Dey, Oshmita & Chakraborty, Debjani, 2009. "Fuzzy periodic review system with fuzzy random variable demand," European Journal of Operational Research, Elsevier, vol. 198(1), pages 113-120, October.
    13. Salameh, M. K. & Jaber, M. Y., 2000. "Economic production quantity model for items with imperfect quality," International Journal of Production Economics, Elsevier, vol. 64(1-3), pages 59-64, March.
    14. Hsiao, Yu-Cheng, 2008. "Integrated logistic and inventory model for a two-stage supply chain controlled by the reorder and shipping points with sharing information," International Journal of Production Economics, Elsevier, vol. 115(1), pages 229-235, September.
    15. Ben-Daya, M. & Hariga, M., 2004. "Integrated single vendor single buyer model with stochastic demand and variable lead time," International Journal of Production Economics, Elsevier, vol. 92(1), pages 75-80, November.
    16. Glock, Christoph H., 2012. "Lead time reduction strategies in a single-vendor–single-buyer integrated inventory model with lot size-dependent lead times and stochastic demand," International Journal of Production Economics, Elsevier, vol. 136(1), pages 37-44.
    17. Dey, O. & Giri, B.C., 2014. "Optimal vendor investment for reducing defect rate in a vendor–buyer integrated system with imperfect production process," International Journal of Production Economics, Elsevier, vol. 155(C), pages 222-228.
    18. Goyal, Suresh Kumar & Cardenas-Barron, Leopoldo Eduardo, 2002. "Note on: Economic production quantity model for items with imperfect quality - a practical approach," International Journal of Production Economics, Elsevier, vol. 77(1), pages 85-87, May.
    19. Evan L. Porteus, 1986. "Optimal Lot Sizing, Process Quality Improvement and Setup Cost Reduction," Operations Research, INFORMS, vol. 34(1), pages 137-144, February.
    20. Hill, Roger M., 1997. "The single-vendor single-buyer integrated production-inventory model with a generalised policy," European Journal of Operational Research, Elsevier, vol. 97(3), pages 493-499, March.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Barros, Júlio & Cortez, Paulo & Carvalho, M. Sameiro, 2021. "A systematic literature review about dimensioning safety stock under uncertainties and risks in the procurement process," Operations Research Perspectives, Elsevier, vol. 8(C).
    2. Mostafa Parsa & Ali Shahandeh Nookabadi & Zümbül Atan & Yaser Malekian, 2022. "An optimal inventory policy for a multi-echelon closed-loop supply chain of postconsumer recycled content products," Operational Research, Springer, vol. 22(3), pages 1887-1938, July.
    3. Md Sadikur Rahman & Subhajit Das & Amalesh Kumar Manna & Ali Akbar Shaikh & Asoke Kumar Bhunia & Leopoldo Eduardo Cárdenas-Barrón & Gerardo Treviño-Garza & Armando Céspedes-Mota, 2021. "A Mathematical Model of the Production Inventory Problem for Mixing Liquid Considering Preservation Facility," Mathematics, MDPI, vol. 9(24), pages 1-19, December.
    4. Amalendu Singha Mahapatra & Hardik N Soni & Maheswar Singha Mahapatra & Biswajit Sarkar & Sanat Majumder, 2021. "A Continuous Review Production-Inventory System with a Variable Preparation Time in a Fuzzy Random Environment," Mathematics, MDPI, vol. 9(7), pages 1-27, March.
    5. Tiwari, Sunil & Kazemi, Nima & Modak, Nikunja Mohan & Cárdenas-Barrón, Leopoldo Eduardo & Sarkar, Sumon, 2020. "The effect of human errors on an integrated stochastic supply chain model with setup cost reduction and backorder price discount," International Journal of Production Economics, Elsevier, vol. 226(C).

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Dey, O. & Giri, B.C., 2014. "Optimal vendor investment for reducing defect rate in a vendor–buyer integrated system with imperfect production process," International Journal of Production Economics, Elsevier, vol. 155(C), pages 222-228.
    2. K. F. Mary Latha & M. Ganesh Kumar & R. Uthayakumar, 2021. "Two echelon economic lot sizing problems with geometric shipment policy backorder price discount and optimal investment to reduce ordering cost," OPSEARCH, Springer;Operational Research Society of India, vol. 58(4), pages 1133-1163, December.
    3. AlDurgam, Mohammad & Adegbola, Kehinde & Glock, Christoph H., 2017. "A single-vendor single-manufacturer integrated inventory model with stochastic demand and variable production rate," International Journal of Production Economics, Elsevier, vol. 191(C), pages 335-350.
    4. Glock, Christoph H., 2012. "The joint economic lot size problem: A review," International Journal of Production Economics, Elsevier, vol. 135(2), pages 671-686.
    5. Sumon Sarkar & Sunil Tiwari & B. C. Giri, 2022. "Impact of uncertain demand and lead-time reduction on two-echelon supply chain," Annals of Operations Research, Springer, vol. 315(2), pages 2027-2055, August.
    6. B.C. Giri & S. Sharma, 2014. "Lot sizing and unequal-sized shipment policy for an integrated production-inventory system," International Journal of Systems Science, Taylor & Francis Journals, vol. 45(5), pages 888-901, May.
    7. Khan, M. & Jaber, M.Y. & Guiffrida, A.L. & Zolfaghari, S., 2011. "A review of the extensions of a modified EOQ model for imperfect quality items," International Journal of Production Economics, Elsevier, vol. 132(1), pages 1-12, July.
    8. Ravi Shankar Kumar & M. K. Tiwari & A. Goswami, 2016. "Two-echelon fuzzy stochastic supply chain for the manufacturer–buyer integrated production–inventory system," Journal of Intelligent Manufacturing, Springer, vol. 27(4), pages 875-888, August.
    9. Huang, Chao-Kuei, 2004. "An optimal policy for a single-vendor single-buyer integrated production-inventory problem with process unreliability consideration," International Journal of Production Economics, Elsevier, vol. 91(1), pages 91-98, September.
    10. Mehmood Khan & Matloub Hussain & Leopoldo Eduardo Cárdenas-Barrón, 2017. "Learning and screening errors in an EPQ inventory model for supply chains with stochastic lead time demands," International Journal of Production Research, Taylor & Francis Journals, vol. 55(16), pages 4816-4832, August.
    11. Irfanullah Khan & Jihed Jemai & Han Lim & Biswajit Sarkar, 2019. "Effect of Electrical Energy on the Manufacturing Setup Cost Reduction, Transportation Discounts, and Process Quality Improvement in a Two-Echelon Supply Chain Management under a Service-Level Constrai," Energies, MDPI, vol. 12(19), pages 1-32, September.
    12. Hsu, Jia-Tzer & Hsu, Lie-Fern, 2013. "An EOQ model with imperfect quality items, inspection errors, shortage backordering, and sales returns," International Journal of Production Economics, Elsevier, vol. 143(1), pages 162-170.
    13. Tien-Yu Lin & Kuo-Lung Hou, 2015. "An imperfect quality economic order quantity with advanced receiving," TOP: An Official Journal of the Spanish Society of Statistics and Operations Research, Springer;Sociedad de Estadística e Investigación Operativa, vol. 23(2), pages 535-551, July.
    14. S. Sarkar & B. C. Giri, 2020. "A vendor–buyer integrated inventory system with variable lead time and uncertain market demand," Operational Research, Springer, vol. 20(1), pages 491-515, March.
    15. M. Ganesh Kumar & R. Uthayakumar, 2017. "An integrated single vendor–buyer inventory model for imperfect production process with stochastic demand in controllable lead time," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 8(2), pages 1041-1054, November.
    16. M. A. Hoque, 2021. "An optimal solution policy to an integrated manufacturer-retailers problem with normal distribution of lead times of delivering equal and unequal-sized batches," OPSEARCH, Springer;Operational Research Society of India, vol. 58(2), pages 483-512, June.
    17. Lie-Fern Hsu & Jia-Tzer Hsu, 2016. "Economic production quantity (EPQ) models under an imperfect production process with shortages backordered," International Journal of Systems Science, Taylor & Francis Journals, vol. 47(4), pages 852-867, March.
    18. Ivan Darma Wangsa & Hui Ming Wee & Shih-Hsien Tseng, 2019. "A coordinated vendor–buyer system considering loss and damage claims, insurance cost and stochastic lead time," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 10(3), pages 384-398, June.
    19. Soumya Kanti Hota & Biswajit Sarkar & Santanu Kumar Ghosh, 2020. "Effects of Unequal Lot Size and Variable Transportation in Unreliable Supply Chain Management," Mathematics, MDPI, vol. 8(3), pages 1-24, March.
    20. Priyamvada & Prerna Gautam & Aditi Khanna, 2021. "Sustainable production strategies for deteriorating and imperfect quality items with an investment in preservation technology," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 12(5), pages 910-918, October.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:spr:operea:v:19:y:2019:i:1:d:10.1007_s12351-016-0286-1. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Sonal Shukla or Springer Nature Abstracting and Indexing (email available below). General contact details of provider: http://www.springer.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.