Resource constrained scheduling simulation model for alternative stochastic network projects
Author
Abstract
Suggested Citation
DOI: 10.1016/S0378-4754(03)00050-8
Download full text from publisher
As the access to this document is restricted, you may want to search for a different version of it.
References listed on IDEAS
- Golenko-Ginzburg, Dimitri & Gonik, Aharon, 1997. "Stochastic network project scheduling with non-consumable limited resources," International Journal of Production Economics, Elsevier, vol. 48(1), pages 29-37, January.
- Kidd, John B, 1987. "A comparison between the VERT program and other methods of project duration estimation," Omega, Elsevier, vol. 15(2), pages 129-134.
- Golenko-Ginzburg, Dimitri & Gonik, Aharon, 1998. "A heuristic for network project scheduling with random activity durations depending on the resource allocation," International Journal of Production Economics, Elsevier, vol. 55(2), pages 149-162, July.
- Golenko-Ginzburg, Dmitri, 1988. "Controlled alternative activity networks for project management," European Journal of Operational Research, Elsevier, vol. 37(3), pages 336-346, December.
- Willis, R. J., 1985. "Critical path analysis and resource constrained project scheduling -- Theory and practice," European Journal of Operational Research, Elsevier, vol. 21(2), pages 149-155, August.
- Golenko-Ginzburg, Dimitri, 1993. "A two-level decision-making model for controlling stochastic projects," International Journal of Production Economics, Elsevier, vol. 32(1), pages 117-127, August.
Citations
Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
Cited by:
- Qin, Rui & Liu, Yan-Kui, 2010. "Modeling data envelopment analysis by chance method in hybrid uncertain environments," Mathematics and Computers in Simulation (MATCOM), Elsevier, vol. 80(5), pages 922-950.
- Dorota Kuchta & Stanisław Stanek, 2020. "Application of Simulation to Selecting Project Strategy for Autonomous Research Projects at Public Universities," Administrative Sciences, MDPI, vol. 10(1), pages 1-23, March.
Most related items
These are the items that most often cite the same works as this one and are cited by the same works as this one.- Golenko-Ginzburg, Dimitri & Gonik, Aharon & Kesler, Shmuel, 1996. "Hierarchical decision-making model for planning and controlling stochastic projects," International Journal of Production Economics, Elsevier, vol. 46(1), pages 39-54, December.
- Azaron, Amir & Tavakkoli-Moghaddam, Reza, 2007. "Multi-objective time-cost trade-off in dynamic PERT networks using an interactive approach," European Journal of Operational Research, Elsevier, vol. 180(3), pages 1186-1200, August.
- Hazır, Öncü & Ulusoy, Gündüz, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," International Journal of Production Economics, Elsevier, vol. 223(C).
- Williams, Terry, 1999. "Towards realism in network simulation," Omega, Elsevier, vol. 27(3), pages 305-314, June.
- Golenko-Ginzburg, Dimitri & Gonik, Aharon, 1997. "Stochastic network project scheduling with non-consumable limited resources," International Journal of Production Economics, Elsevier, vol. 48(1), pages 29-37, January.
- Williams, Terry, 1995. "A classified bibliography of recent research relating to project risk management," European Journal of Operational Research, Elsevier, vol. 85(1), pages 18-38, August.
- Golenko-Ginzburg, Dimitri & Gonik, Aharon, 1998. "A heuristic for network project scheduling with random activity durations depending on the resource allocation," International Journal of Production Economics, Elsevier, vol. 55(2), pages 149-162, July.
- Rabbani, M. & Fatemi Ghomi, S.M.T. & Jolai, F. & Lahiji, N.S., 2007. "A new heuristic for resource-constrained project scheduling in stochastic networks using critical chain concept," European Journal of Operational Research, Elsevier, vol. 176(2), pages 794-808, January.
- Golenko-Ginzburg, Dimitri & Gonik, Aharon, 1998. "High performance heuristic algorithm for controlling stochastic network projects," International Journal of Production Economics, Elsevier, vol. 54(3), pages 235-245, May.
- Herroelen, Willy & Leus, Roel, 2005. "Project scheduling under uncertainty: Survey and research potentials," European Journal of Operational Research, Elsevier, vol. 165(2), pages 289-306, September.
- Öncü Hazir & Gündüz Ulusoy, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," Post-Print hal-02898162, HAL.
- Dimitri, Golenko-Ginzburg & Shimon, Sitniakovski & Ljubisa, Papic, 2000. "Resource supportability simulation model for a man–machine production system," Mathematics and Computers in Simulation (MATCOM), Elsevier, vol. 53(1), pages 105-112.
- Xiong, Jian & Leus, Roel & Yang, Zhenyu & Abbass, Hussein A., 2016. "Evolutionary multi-objective resource allocation and scheduling in the Chinese navigation satellite system project," European Journal of Operational Research, Elsevier, vol. 251(2), pages 662-675.
- Menipaz, Ehud & Ben-Yair, Avner, 2002. "Three-parametrical harmonization model in project management by means of simulation," Mathematics and Computers in Simulation (MATCOM), Elsevier, vol. 59(5), pages 431-436.
- Chen, Shih-Pin & Tsai, Ming-Jiun, 2011. "Time-cost trade-off analysis of project networks in fuzzy environments," European Journal of Operational Research, Elsevier, vol. 212(2), pages 386-397, July.
- Li, Haitao & Womer, Norman K., 2015. "Solving stochastic resource-constrained project scheduling problems by closed-loop approximate dynamic programming," European Journal of Operational Research, Elsevier, vol. 246(1), pages 20-33.
- Laslo, Zohar & Keren, Baruch & Ilani, Hagai, 2008. "Minimizing task completion time with the execution set method," European Journal of Operational Research, Elsevier, vol. 187(3), pages 1513-1519, June.
- Geng, Sunyue & Liu, Sifeng & Fang, Zhigeng & Gao, Su, 2021. "A reliable framework for satellite networks achieving energy requirements," Reliability Engineering and System Safety, Elsevier, vol. 216(C).
- W Herroelen & R Leus, 2005. "Identification and illumination of popular misconceptions about project scheduling and time buffering in a resource-constrained environment," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 56(1), pages 102-109, January.
- Godinho, Pedro & Branco, Fernando G., 2012. "Adaptive policies for multi-mode project scheduling under uncertainty," European Journal of Operational Research, Elsevier, vol. 216(3), pages 553-562.
More about this item
Keywords
Alternative decision nodes; Probabilistic branching; Joint variant; Renewable resources; Resource constrained GERT project scheduling algorithm; Stochastic project simulation;All these keywords.
Statistics
Access and download statisticsCorrections
All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:matcom:v:63:y:2003:i:2:p:105-117. See general information about how to correct material in RePEc.
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.
For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.journals.elsevier.com/mathematics-and-computers-in-simulation/ .
Please note that corrections may take a couple of weeks to filter through the various RePEc services.