Multi-objective optimisation in flexible assembly job shop scheduling using a distributed ant colony system
Author
Abstract
Suggested Citation
DOI: 10.1016/j.ejor.2019.11.016
Download full text from publisher
As the access to this document is restricted, you may want to search for a different version of it.
References listed on IDEAS
- Zhang, Luping & Wong, T.N., 2015. "An object-coding genetic algorithm for integrated process planning and scheduling," European Journal of Operational Research, Elsevier, vol. 244(2), pages 434-444.
- De Giovanni, L. & Pezzella, F., 2010. "An Improved Genetic Algorithm for the Distributed and Flexible Job-shop Scheduling problem," European Journal of Operational Research, Elsevier, vol. 200(2), pages 395-408, January.
- Xiong, Fuli & Xing, Keyi & Wang, Feng, 2015. "Scheduling a hybrid assembly-differentiation flowshop to minimize total flow time," European Journal of Operational Research, Elsevier, vol. 240(2), pages 338-354.
- Koulamas, Christos & Kyparisis, George J., 2007. "A note on the two-stage assembly flow shop scheduling problem with uniform parallel machines," European Journal of Operational Research, Elsevier, vol. 182(2), pages 945-951, October.
- Sawik, Tadeusz, 2004. "Loading and scheduling of a flexible assembly system by mixed integer programming," European Journal of Operational Research, Elsevier, vol. 154(1), pages 1-19, April.
- Kovalyov, M. Y. & Potts, C. N. & Strusevich, V. A., 2004. "Batching decisions for assembly production systems," European Journal of Operational Research, Elsevier, vol. 157(3), pages 620-642, September.
- Kacem, Imed & Hammadi, Slim & Borne, Pierre, 2002. "Pareto-optimality approach for flexible job-shop scheduling problems: hybridization of evolutionary algorithms and fuzzy logic," Mathematics and Computers in Simulation (MATCOM), Elsevier, vol. 60(3), pages 245-276.
- Menezes, Gustavo Campos & Mateus, Geraldo Robson & Ravetti, Martín Gómez, 2017. "A branch and price algorithm to solve the integrated production planning and scheduling in bulk ports," European Journal of Operational Research, Elsevier, vol. 258(3), pages 926-937.
- Hariri, A. M. A. & Potts, C. N., 1997. "A branch and bound algorithm for the two-stage assembly scheduling problem," European Journal of Operational Research, Elsevier, vol. 103(3), pages 547-556, December.
- Ho, Nhu Binh & Tay, Joc Cing & Lai, Edmund M.-K., 2007. "An effective architecture for learning and evolving flexible job-shop schedules," European Journal of Operational Research, Elsevier, vol. 179(2), pages 316-333, June.
- Al-Anzi, Fawaz S. & Allahverdi, Ali, 2007. "A self-adaptive differential evolution heuristic for two-stage assembly scheduling problem to minimize maximum lateness with setup times," European Journal of Operational Research, Elsevier, vol. 182(1), pages 80-94, October.
- Framinan, Jose M. & Perez-Gonzalez, Paz & Fernandez-Viagas, Victor, 2019. "Deterministic assembly scheduling problems: A review and classification of concurrent-type scheduling models and solution procedures," European Journal of Operational Research, Elsevier, vol. 273(2), pages 401-417.
- S. Zhang & T. N. Wong, 2018. "Integrated process planning and scheduling: an enhanced ant colony optimization heuristic with parameter tuning," Journal of Intelligent Manufacturing, Springer, vol. 29(3), pages 585-601, March.
- Yokoyama, Masao, 2008. "Flow-shop scheduling with setup and assembly operations," European Journal of Operational Research, Elsevier, vol. 187(3), pages 1184-1195, June.
- Yokoyama, Masao & Santos, Daryl L., 2005. "Three-stage flow-shop scheduling with assembly operations to minimize the weighted sum of product completion times," European Journal of Operational Research, Elsevier, vol. 161(3), pages 754-770, March.
- Sun, Xi & Morizawa, Kazuko & Nagasawa, Hiroyuki, 2003. "Powerful heuristics to minimize makespan in fixed, 3-machine, assembly-type flowshop scheduling," European Journal of Operational Research, Elsevier, vol. 146(3), pages 498-516, May.
- Sabuncuoglu, Ihsan & Gocgun, Yasin & Erel, Erdal, 2008. "Backtracking and exchange of information: Methods to enhance a beam search algorithm for assembly line scheduling," European Journal of Operational Research, Elsevier, vol. 186(3), pages 915-930, May.
- Loukil, T. & Teghem, J. & Tuyttens, D., 2005. "Solving multi-objective production scheduling problems using metaheuristics," European Journal of Operational Research, Elsevier, vol. 161(1), pages 42-61, February.
- Moslehi, Ghasem & Mahnam, Mehdi, 2011. "A Pareto approach to multi-objective flexible job-shop scheduling problem using particle swarm optimization and local search," International Journal of Production Economics, Elsevier, vol. 129(1), pages 14-22, January.
- Perez-Gonzalez, Paz & Framinan, Jose M., 2014. "A common framework and taxonomy for multicriteria scheduling problems with interfering and competing jobs: Multi-agent scheduling problems," European Journal of Operational Research, Elsevier, vol. 235(1), pages 1-16.
Citations
Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
Cited by:
- Dauzère-Pérès, Stéphane & Ding, Junwen & Shen, Liji & Tamssaouet, Karim, 2024. "The flexible job shop scheduling problem: A review," European Journal of Operational Research, Elsevier, vol. 314(2), pages 409-432.
- Hosseini, Amir & Otto, Alena & Pesch, Erwin, 2024. "Scheduling in manufacturing with transportation: Classification and solution techniques," European Journal of Operational Research, Elsevier, vol. 315(3), pages 821-843.
Most related items
These are the items that most often cite the same works as this one and are cited by the same works as this one.- Framinan, Jose M. & Perez-Gonzalez, Paz & Fernandez-Viagas, Victor, 2019. "Deterministic assembly scheduling problems: A review and classification of concurrent-type scheduling models and solution procedures," European Journal of Operational Research, Elsevier, vol. 273(2), pages 401-417.
- Hatami, Sara & Ruiz, Rubén & Andrés-Romano, Carlos, 2015. "Heuristics and metaheuristics for the distributed assembly permutation flowshop scheduling problem with sequence dependent setup times," International Journal of Production Economics, Elsevier, vol. 169(C), pages 76-88.
- Sung, Chang Sup & Juhn, Jaeho, 2009. "Makespan minimization for a 2-stage assembly scheduling problem subject to component available time constraint," International Journal of Production Economics, Elsevier, vol. 119(2), pages 392-401, June.
- Yiyi Xu & M’hammed Sahnoun & Fouad Ben Abdelaziz & David Baudry, 2022. "A simulated multi-objective model for flexible job shop transportation scheduling," Annals of Operations Research, Springer, vol. 311(2), pages 899-920, April.
- Niloy J. Mukherjee & Subhash C. Sarin & Daniel A. Neira, 2023. "Lot streaming for a two-stage assembly system in the presence of handling costs," Journal of Scheduling, Springer, vol. 26(4), pages 335-351, August.
- Wei Xiong & Dongmei Fu, 2018. "A new immune multi-agent system for the flexible job shop scheduling problem," Journal of Intelligent Manufacturing, Springer, vol. 29(4), pages 857-873, April.
- Zikai Zhang & Qiuhua Tang, 2022. "Integrating preventive maintenance to two-stage assembly flow shop scheduling: MILP model, constructive heuristics and meta-heuristics," Flexible Services and Manufacturing Journal, Springer, vol. 34(1), pages 156-203, March.
- Alper Türkyılmaz & Özlem Şenvar & İrem Ünal & Serol Bulkan, 2020. "A research survey: heuristic approaches for solving multi objective flexible job shop problems," Journal of Intelligent Manufacturing, Springer, vol. 31(8), pages 1949-1983, December.
- Li, Xinyu & Gao, Liang, 2016. "An effective hybrid genetic algorithm and tabu search for flexible job shop scheduling problem," International Journal of Production Economics, Elsevier, vol. 174(C), pages 93-110.
- Sung, C.S. & Kim, Hyun Ah, 2008. "A two-stage multiple-machine assembly scheduling problem for minimizing sum of completion times," International Journal of Production Economics, Elsevier, vol. 113(2), pages 1038-1048, June.
- Zhu, Xuedong & Son, Junbo & Zhang, Xi & Wu, Jianguo, 2023. "Constraint programming and logic-based Benders decomposition for the integrated process planning and scheduling problem," Omega, Elsevier, vol. 117(C).
- Hao-Chin Chang & Tung-Kuan Liu, 2017. "Optimisation of distributed manufacturing flexible job shop scheduling by using hybrid genetic algorithms," Journal of Intelligent Manufacturing, Springer, vol. 28(8), pages 1973-1986, December.
- Koulamas, Christos & Kyparisis, George J., 2007. "A note on the two-stage assembly flow shop scheduling problem with uniform parallel machines," European Journal of Operational Research, Elsevier, vol. 182(2), pages 945-951, October.
- Nicolás Álvarez-Gil & Rafael Rosillo & David de la Fuente & Raúl Pino, 2021. "A discrete firefly algorithm for solving the flexible job-shop scheduling problem in a make-to-order manufacturing system," Central European Journal of Operations Research, Springer;Slovak Society for Operations Research;Hungarian Operational Research Society;Czech Society for Operations Research;Österr. Gesellschaft für Operations Research (ÖGOR);Slovenian Society Informatika - Section for Operational Research;Croatian Operational Research Society, vol. 29(4), pages 1353-1374, December.
- Xiong, Fuli & Xing, Keyi & Wang, Feng, 2015. "Scheduling a hybrid assembly-differentiation flowshop to minimize total flow time," European Journal of Operational Research, Elsevier, vol. 240(2), pages 338-354.
- Miguel A. Fernández Pérez & Fernanda M. P. Raupp, 2016. "A Newton-based heuristic algorithm for multi-objective flexible job-shop scheduling problem," Journal of Intelligent Manufacturing, Springer, vol. 27(2), pages 409-416, April.
- Vilcot, Geoffrey & Billaut, Jean-Charles, 2008. "A tabu search and a genetic algorithm for solving a bicriteria general job shop scheduling problem," European Journal of Operational Research, Elsevier, vol. 190(2), pages 398-411, October.
- Chiang, Tsung-Che & Lin, Hsiao-Jou, 2013. "A simple and effective evolutionary algorithm for multiobjective flexible job shop scheduling," International Journal of Production Economics, Elsevier, vol. 141(1), pages 87-98.
- Shaojun Lu & Jun Pei & Xinbao Liu & Xiaofei Qian & Nenad Mladenovic & Panos M. Pardalos, 2020. "Less is more: variable neighborhood search for integrated production and assembly in smart manufacturing," Journal of Scheduling, Springer, vol. 23(6), pages 649-664, December.
- Lin, B.M.T. & Cheng, T.C.E. & Chou, A.S.C., 2007. "Scheduling in an assembly-type production chain with batch transfer," Omega, Elsevier, vol. 35(2), pages 143-151, April.
More about this item
Keywords
Scheduling; Flexible assembly job shop scheduling; Multi-objective optimisation; Meta-heuristics; Ant colony optimisation;All these keywords.
Statistics
Access and download statisticsCorrections
All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:ejores:v:283:y:2020:i:2:p:441-460. See general information about how to correct material in RePEc.
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.
For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/locate/eor .
Please note that corrections may take a couple of weeks to filter through the various RePEc services.