On Calculating Activity Slack in Stochastic Project Networks
Author
Abstract
Suggested Citation
DOI: 10.3844/ajebasp.2010.78.85
Download full text from publisher
References listed on IDEAS
- Elmaghraby, Salah E., 2005. "On the fallacy of averages in project risk management," European Journal of Operational Research, Elsevier, vol. 165(2), pages 307-313, September.
- Elmaghraby, Salah E., 2000. "On criticality and sensitivity in activity networks," European Journal of Operational Research, Elsevier, vol. 127(2), pages 220-238, December.
- George B. Kleindorfer, 1971. "Bounding Distributions for a Stochastic Acyclic Network," Operations Research, INFORMS, vol. 19(7), pages 1586-1601, December.
- V. G. Kulkarni & V. G. Adlakha, 1986. "Markov and Markov-Regenerative pert Networks," Operations Research, INFORMS, vol. 34(5), pages 769-781, October.
- J. J. Martin, 1965. "Distribution of the Time Through a Directed, Acyclic Network," Operations Research, INFORMS, vol. 13(1), pages 46-66, February.
- Bajis Dodin, 1984. "Determining the K Most Critical Paths in PERT Networks," Operations Research, INFORMS, vol. 32(4), pages 859-877, August.
- D. R. Fulkerson, 1962. "Expected Critical Path Lengths in PERT Networks," Operations Research, INFORMS, vol. 10(6), pages 808-817, December.
- Pierre Robillard & Michel Trahan, 1976. "Technical Note—Expected Completion Time in Pert Networks," Operations Research, INFORMS, vol. 24(1), pages 177-182, February.
Most related items
These are the items that most often cite the same works as this one and are cited by the same works as this one.- Azaron, Amir & Fatemi Ghomi, S.M.T., 2008. "Lower bound for the mean project completion time in dynamic PERT networks," European Journal of Operational Research, Elsevier, vol. 186(1), pages 120-127, April.
- Tetsuo Iida, 2000. "Computing bounds on project duration distributions for stochastic PERT networks," Naval Research Logistics (NRL), John Wiley & Sons, vol. 47(7), pages 559-580, October.
- Azaron, Amir & Fynes, Brian & Modarres, Mohammad, 2011. "Due date assignment in repetitive projects," International Journal of Production Economics, Elsevier, vol. 129(1), pages 79-85, January.
- Madadi, M. & Iranmanesh, H., 2012. "A management oriented approach to reduce a project duration and its risk (variability)," European Journal of Operational Research, Elsevier, vol. 219(3), pages 751-761.
- Fatemi Ghomi, S. M. T. & Hashemin, S. S., 1999. "A new analytical algorithm and generation of Gaussian quadrature formula for stochastic network," European Journal of Operational Research, Elsevier, vol. 114(3), pages 610-625, May.
- Azaron, Amir & Katagiri, Hideki & Sakawa, Masatoshi & Kato, Kosuke & Memariani, Azizollah, 2006. "A multi-objective resource allocation problem in PERT networks," European Journal of Operational Research, Elsevier, vol. 172(3), pages 838-854, August.
- Vaseghi, Forough & Martens, Annelies & Vanhoucke, Mario, 2024. "Analysis of the impact of corrective actions for stochastic project networks," European Journal of Operational Research, Elsevier, vol. 316(2), pages 503-518.
- Davaadorjin Monhor, 2011. "A new probabilistic approach to the path criticality in stochastic PERT," Central European Journal of Operations Research, Springer;Slovak Society for Operations Research;Hungarian Operational Research Society;Czech Society for Operations Research;Österr. Gesellschaft für Operations Research (ÖGOR);Slovenian Society Informatika - Section for Operational Research;Croatian Operational Research Society, vol. 19(4), pages 615-633, December.
- Yousry Abdelkader, 2010. "Adjustment of the moments of the project completion times when activity times are exponentially distributed," Annals of Operations Research, Springer, vol. 181(1), pages 503-514, December.
- Elmaghraby, Salah E., 2000. "On criticality and sensitivity in activity networks," European Journal of Operational Research, Elsevier, vol. 127(2), pages 220-238, December.
- Elmaghraby, S. E. & Fathi, Y. & Taner, M. R., 1999. "On the sensitivity of project variability to activity mean duration," International Journal of Production Economics, Elsevier, vol. 62(3), pages 219-232, September.
- Stefan Creemers & Erik Demeulemeester & Stijn Vonder, 2014.
"A new approach for quantitative risk analysis,"
Annals of Operations Research, Springer, vol. 213(1), pages 27-65, February.
- S. Creemers & E. Demeulemeester & S. van de Vonder, 2013. "A new approach for quantitative risk analysis," Post-Print hal-00846528, HAL.
- Vanhoucke, Mario, 2010. "Using activity sensitivity and network topology information to monitor project time performance," Omega, Elsevier, vol. 38(5), pages 359-370, October.
- Wiesemann, Wolfram & Kuhn, Daniel & Rustem, Berç, 2010. "Maximizing the net present value of a project under uncertainty," European Journal of Operational Research, Elsevier, vol. 202(2), pages 356-367, April.
- Zhichao Zheng & Karthik Natarajan & Chung-Piaw Teo, 2016. "Least Squares Approximation to the Distribution of Project Completion Times with Gaussian Uncertainty," Operations Research, INFORMS, vol. 64(6), pages 1406-1421, December.
- Amir Azaron & Hideki Katagiri & Masatoshi Sakawa, 2007. "Time-cost trade-off via optimal control theory in Markov PERT networks," Annals of Operations Research, Springer, vol. 150(1), pages 47-64, March.
- Bregman, Robert L., 2009. "A heuristic procedure for solving the dynamic probabilistic project expediting problem," European Journal of Operational Research, Elsevier, vol. 192(1), pages 125-137, January.
- Hazır, Öncü & Ulusoy, Gündüz, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," International Journal of Production Economics, Elsevier, vol. 223(C).
- Azaron, Amir & Katagiri, Hideki & Kato, Kosuke & Sakawa, Masatoshi, 2006. "Longest path analysis in networks of queues: Dynamic scheduling problems," European Journal of Operational Research, Elsevier, vol. 174(1), pages 132-149, October.
- Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2022. "Using Earned Value Management and Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 297(2), pages 451-466.
More about this item
Keywords
Project management; project planning; stochastic activity durations; project risk; activity slack;All these keywords.
Statistics
Access and download statisticsCorrections
All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:abk:jajeba:ajebasp.2010.78.85. See general information about how to correct material in RePEc.
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.
For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Jeffery Daniels (email available below). General contact details of provider: https://thescipub.com .
Please note that corrections may take a couple of weeks to filter through the various RePEc services.