A robust scheduling for the multi-mode project scheduling problem with a given deadline under uncertainty of activity duration

Author

Listed:
  • Hadi Moradi
  • Shahram Shadrokh

Abstract

The problem of this paper deals with the multi-mode project scheduling problem under uncertainty of activity duration where only the renewable resources are taken into account and a given deadline has to be met at the cost of recruiting additional resources. A heuristic algorithm is employed to solve this problem, and to maintain the robustness of the baseline schedule, the concept of critical chain project management (CCPM) is applied in which a new definition to resource buffer is considered. A simulation methodology is used to determine the size and location of resource buffers in the schedules in which three different buffer sizes and three different uncertainty levels are considered. Results and analysis of the simulation outcomes illustrate that resource buffers are useful and should be simulated by the CCPM schedules, as they help to decrease the total duration of the project during implementation and meet the deadline of the project with more assurance.

Suggested Citation

  • Hadi Moradi & Shahram Shadrokh, 2019. "A robust scheduling for the multi-mode project scheduling problem with a given deadline under uncertainty of activity duration," International Journal of Production Research, Taylor & Francis Journals, vol. 57(10), pages 3138-3167, May.
  • Handle: RePEc:taf:tprsxx:v:57:y:2019:i:10:p:3138-3167
    DOI: 10.1080/00207543.2018.1552371
    as

    Download full text from publisher

    File URL: http://hdl.handle.net/10.1080/00207543.2018.1552371
    Download Restriction: Access to full text is restricted to subscribers.

    File URL: https://libkey.io/10.1080/00207543.2018.1552371?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Akbarzadeh, Babak & Maenhout, Broos, 2024. "A study on policy decisions to embed flexibility for reactive recovery in the planning and scheduling process in operating rooms," Omega, Elsevier, vol. 126(C).
    2. Zarghami, Seyed Ashkan & Dumrak, Jantanee, 2021. "Aleatory uncertainty quantification of project resources and its application to project scheduling," Reliability Engineering and System Safety, Elsevier, vol. 211(C).
    3. Drăgan, George Bogdan & Vasilache, Raluca Oana & Schin, George Cristian, 2020. "Exploring eco-label industry actors’ perceptions on the capabilities of a forthcoming multiple project management software – An fsQCA approach," Journal of Business Research, Elsevier, vol. 115(C), pages 281-288.
    4. Guofeng Ma & Jianyao Jia & Tiancheng Zhu & Shan Jiang, 2019. "A Critical Design Structure Method for Project Schedule Development under Rework Risks," Sustainability, MDPI, vol. 11(24), pages 1-20, December.
    5. Zhao, Mingxuan & Zhou, Jian & Wang, Ke & Pantelous, Athanasios A., 2023. "Project scheduling problem with fuzzy activity durations: A novel operational law based solution framework," European Journal of Operational Research, Elsevier, vol. 306(2), pages 519-534.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:taf:tprsxx:v:57:y:2019:i:10:p:3138-3167. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Longhurst (email available below). General contact details of provider: http://www.tandfonline.com/TPRS20 .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.