IDEAS home Printed from https://ideas.repec.org/a/inm/oropre/v53y2005i2p313-327.html
   My bibliography  Save this article

An Efficient Optimal Solution to the Two-Hoist No-Wait Cyclic Scheduling Problem

Author

Listed:
  • Jiyin Liu

    (Business School, Loughborough University, Loughborough, Leicestershire LE11 3TU, United Kingdom)

  • Yun Jiang

    (Department of Industrial Engineering, Bilkent University, 06800 Bilkent, Ankara, Turkey)

Abstract

Hoist scheduling is a typical problem in the operation of electroplating systems. The cyclic scheduling policy is widely used in these systems in industry. Research on hoist scheduling has focused on the cyclic problem to minimize the cycle length. Most previous studies consider the single-hoist case. In practice, however, more than one hoist is often used in an electroplating line. This paper addresses the two-hoist, no-wait cyclic scheduling problem, in which the tank-processing times are constants and, upon completion of processing in a tank, the parts have to be moved to the next tank immediately. Based on the analysis of the problem properties, a polynomial algorithm is developed to obtain an optimal schedule. This algorithm first identifies a set of thresholds, which are special values of the cycle length, so that the feasibility property may change only at these thresholds. Feasibility checking is then carried out on each individual threshold in ascending order. The first feasible threshold found will be the optimal cycle length, and the corresponding feasible schedule is an optimal hoist schedule.

Suggested Citation

  • Jiyin Liu & Yun Jiang, 2005. "An Efficient Optimal Solution to the Two-Hoist No-Wait Cyclic Scheduling Problem," Operations Research, INFORMS, vol. 53(2), pages 313-327, April.
  • Handle: RePEc:inm:oropre:v:53:y:2005:i:2:p:313-327
    DOI: 10.1287/opre.1040.0167
    as

    Download full text from publisher

    File URL: http://dx.doi.org/10.1287/opre.1040.0167
    Download Restriction: no

    File URL: https://libkey.io/10.1287/opre.1040.0167?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Armstrong, Ronald & Lei, Lei & Gu, Shanhong, 1994. "A bounding scheme for deriving the minimal cycle time of a single-transporter N-stage process with time-window constraints," European Journal of Operational Research, Elsevier, vol. 78(1), pages 130-140, October.
    2. Y. Crama & V. Kats & J. van de Klundert & E. Levner, 2000. "Cyclic scheduling in robotic flowshops," Annals of Operations Research, Springer, vol. 96(1), pages 97-124, November.
    3. Lei Lei & Tzyh-Jong Wang, 1991. "The Minimum Common-Cycle Algorithm for Cyclic Scheduling of Two Material Handling Hoists with Time Window Constraints," Management Science, INFORMS, vol. 37(12), pages 1629-1639, December.
    4. Che, Ada & Chu, Chengbin & Levner, Eugene, 2003. "A polynomial algorithm for 2-degree cyclic robot scheduling," European Journal of Operational Research, Elsevier, vol. 145(1), pages 31-44, February.
    5. Chelliah Sriskandarajah & Nicholas Hall & Hichem Kamoun, 1998. "Scheduling large robotic cells without buffers," Annals of Operations Research, Springer, vol. 76(0), pages 287-321, January.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Paul, Henrik J. & Bierwirth, Christian & Kopfer, Herbert, 2007. "A heuristic scheduling procedure for multi-item hoist production lines," International Journal of Production Economics, Elsevier, vol. 105(1), pages 54-69, January.
    2. Che, Ada & Chabrol, Michelle & Gourgand, Michel & Wang, Yuan, 2012. "Scheduling multiple robots in a no-wait re-entrant robotic flowshop," International Journal of Production Economics, Elsevier, vol. 135(1), pages 199-208.
    3. Che, Ada & Chu, Chengbin, 2009. "Multi-degree cyclic scheduling of a no-wait robotic cell with multiple robots," European Journal of Operational Research, Elsevier, vol. 199(1), pages 77-88, November.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Kats, Vladimir & Lei, Lei & Levner, Eugene, 2008. "Minimizing the cycle time of multiple-product processing networks with a fixed operation sequence, setups, and time-window constraints," European Journal of Operational Research, Elsevier, vol. 187(3), pages 1196-1211, June.
    2. Drobouchevitch, Inna G. & Neil Geismar, H. & Sriskandarajah, Chelliah, 2010. "Throughput optimization in robotic cells with input and output machine buffers: A comparative study of two key models," European Journal of Operational Research, Elsevier, vol. 206(3), pages 623-633, November.
    3. Janny M. Y. Leung & Guoqing Zhang & Xiaoguang Yang & Raymond Mak & Kokin Lam, 2004. "Optimal Cyclic Multi-Hoist Scheduling: A Mixed Integer Programming Approach," Operations Research, INFORMS, vol. 52(6), pages 965-976, December.
    4. Milind Dawande & Michael Pinedo & Chelliah Sriskandarajah, 2009. "Multiple Part-Type Production in Robotic Cells: Equivalence of Two Real-World Models," Manufacturing & Service Operations Management, INFORMS, vol. 11(2), pages 210-228, February.
    5. Neil Geismar, H. & Dawande, Milind & Sriskandarajah, Chelliah, 2005. "Approximation algorithms for k-unit cyclic solutions in robotic cells," European Journal of Operational Research, Elsevier, vol. 162(2), pages 291-309, April.
    6. Paul, Henrik J. & Bierwirth, Christian & Kopfer, Herbert, 2007. "A heuristic scheduling procedure for multi-item hoist production lines," International Journal of Production Economics, Elsevier, vol. 105(1), pages 54-69, January.
    7. Sheen, Gwo-Ji & Liao, Lu-Wen, 2007. "A branch and bound algorithm for the one-machine scheduling problem with minimum and maximum time lags," European Journal of Operational Research, Elsevier, vol. 181(1), pages 102-116, August.
    8. Drobouchevitch, Inna G. & Sethi, Suresh P. & Sriskandarajah, Chelliah, 2006. "Scheduling dual gripper robotic cell: One-unit cycles," European Journal of Operational Research, Elsevier, vol. 171(2), pages 598-631, June.
    9. Chelliah Sriskandarajah & Inna Drobouchevitch & Suresh P. Sethi & Ramaswamy Chandrasekaran, 2004. "Scheduling Multiple Parts in a Robotic Cell Served by a Dual-Gripper Robot," Operations Research, INFORMS, vol. 52(1), pages 65-82, February.
    10. Bagchi, Tapan P. & Gupta, Jatinder N.D. & Sriskandarajah, Chelliah, 2006. "A review of TSP based approaches for flowshop scheduling," European Journal of Operational Research, Elsevier, vol. 169(3), pages 816-854, March.
    11. Crama, Yves, 1997. "Combinatorial optimization models for production scheduling in automated manufacturing systems," European Journal of Operational Research, Elsevier, vol. 99(1), pages 136-153, May.
    12. W Zahrouni & H Kamoun, 2011. "Transforming part-sequencing problems in a robotic cell into a GTSP," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 62(1), pages 114-123, January.
    13. Gultekin, Hakan & Akturk, M. Selim & Karasan, Oya Ekin, 2006. "Cyclic scheduling of a 2-machine robotic cell with tooling constraints," European Journal of Operational Research, Elsevier, vol. 174(2), pages 777-796, October.
    14. Carlier, Jacques & Haouari, Mohamed & Kharbeche, Mohamed & Moukrim, Aziz, 2010. "An optimization-based heuristic for the robotic cell problem," European Journal of Operational Research, Elsevier, vol. 202(3), pages 636-645, May.
    15. Hyun-Jung Kim & Jun-Ho Lee, 2021. "Cyclic robot scheduling for 3D printer-based flexible assembly systems," Annals of Operations Research, Springer, vol. 298(1), pages 339-359, March.
    16. SubaI, Corinne & Baptiste, Pierre & Niel, Eric, 2006. "Scheduling issues for environmentally responsible manufacturing: The case of hoist scheduling in an electroplating line," International Journal of Production Economics, Elsevier, vol. 99(1-2), pages 74-87, February.
    17. Xin Li & Richard Y. K. Fung, 2016. "Optimal K-unit cycle scheduling of two-cluster tools with residency constraints and general robot moving times," Journal of Scheduling, Springer, vol. 19(2), pages 165-176, April.
    18. Sofie Coene & Frits C. R. Spieksma & Gerhard J. Woeginger, 2011. "Charlemagne's Challenge: The Periodic Latency Problem," Operations Research, INFORMS, vol. 59(3), pages 674-683, June.
    19. Levner, Eugene & Kats, Vladimir & Levit, Vadim E., 1997. "An improved algorithm for cyclic flowshop scheduling in a robotic cell," European Journal of Operational Research, Elsevier, vol. 97(3), pages 500-508, March.
    20. Zhili Zhou & Ling Li, 2009. "A solution for cyclic scheduling of multi-hoists without overlapping," Annals of Operations Research, Springer, vol. 168(1), pages 5-21, April.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:inm:oropre:v:53:y:2005:i:2:p:313-327. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Asher (email available below). General contact details of provider: https://edirc.repec.org/data/inforea.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.