A Branch-and-Price Algorithm for Parallel Machine Scheduling Using ZDDs and Generic Branching

Author

Listed:
  • Daniel Kowalczyk

    (ORSTAT, Faculty of Economics and Business, KU Leuven, 3000 Leuven, Belgium)

  • Roel Leus

    (ORSTAT, Faculty of Economics and Business, KU Leuven, 3000 Leuven, Belgium)

Abstract

We study the parallel machine scheduling problem to minimize the sum of the weighted completion times of the jobs to be scheduled (problem Pm ∥∑ w j C j in the standard three-field notation). We use the set covering formulation that was introduced by van den Akker et al. [van den Akker J, Hoogeveen J, van de Velde S (1999) Parallel machine scheduling by column generation. Oper. Res. 47(6):862–872.] for this problem, and we improve the computational performance of their branch-and-price (B&P) algorithm by a number of techniques, including a different generic branching scheme, zero-suppressed binary decision diagrams (ZDDs) to solve the pricing problem, dual-price smoothing as a stabilization method, and Farkas pricing to handle infeasibilities. We report computational results that show the effectiveness of the algorithmic enhancements, which depends on the characteristics of the instances. To the best of our knowledge, we are also the first to use ZDDs to solve the pricing problem in a B&P algorithm for a scheduling problem. The online supplement is available at https://doi.org/10.1287/ijoc.2018.0809 .

Suggested Citation

  • Daniel Kowalczyk & Roel Leus, 2018. "A Branch-and-Price Algorithm for Parallel Machine Scheduling Using ZDDs and Generic Branching," INFORMS Journal on Computing, INFORMS, vol. 30(4), pages 768-782, November.
  • Handle: RePEc:inm:orijoc:v:30:y:2018:i:4:p:768-782
    DOI: 10.1287/ijoc.2018.0809
    as

    Download full text from publisher

    File URL: https://doi.org/10.1287/ijoc.2018.0809
    Download Restriction: no

    File URL: https://libkey.io/10.1287/ijoc.2018.0809?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Azizoglu, Meral & Kirca, Omer, 1999. "On the minimization of total weighted flow time with identical and uniform parallel machines," European Journal of Operational Research, Elsevier, vol. 113(1), pages 91-100, February.
    2. DYER, Martin E. & WOLSEY, Laurence A., 1990. "Formulating the single machine sequencing problem with release dates as a mixed integer program," LIDAM Reprints CORE 878, Université catholique de Louvain, Center for Operations Research and Econometrics (CORE).
    3. Michael H. Rothkopf, 1966. "Scheduling Independent Tasks on Parallel Processors," Management Science, INFORMS, vol. 12(5), pages 437-447, January.
    4. E. L. Lawler & J. M. Moore, 1969. "A Functional Equation and its Application to Resource Allocation and Sequencing Problems," Management Science, INFORMS, vol. 16(1), pages 77-84, September.
    5. Louis-Philippe Bigras & Michel Gamache & Gilles Savard, 2008. "Time-Indexed Formulations and the Total Weighted Tardiness Problem," INFORMS Journal on Computing, INFORMS, vol. 20(1), pages 133-142, February.
    6. E. DYER, Martin & WOLSEY, Laurence A., 1990. "Formulating the single machine sequencing problem with release dates as a mixed integer program," LIDAM Reprints CORE 917, Université catholique de Louvain, Center for Operations Research and Econometrics (CORE).
    7. Pereira Lopes, Manuel J. & de Carvalho, J.M. Valerio, 2007. "A branch-and-price algorithm for scheduling parallel machines with sequence dependent setup times," European Journal of Operational Research, Elsevier, vol. 176(3), pages 1508-1527, February.
    8. J.M. van den Akker & C.A.J. Hurkens & M.W.P. Savelsbergh, 2000. "Time-Indexed Formulations for Machine Scheduling Problems: Column Generation," INFORMS Journal on Computing, INFORMS, vol. 12(2), pages 111-124, May.
    9. Zhi-Long Chen & Warren B. Powell, 1999. "Solving Parallel Machine Scheduling Problems by Column Generation," INFORMS Journal on Computing, INFORMS, vol. 11(1), pages 78-94, February.
    10. Wayne E. Smith, 1956. "Various optimizers for single‐stage production," Naval Research Logistics Quarterly, John Wiley & Sons, vol. 3(1‐2), pages 59-66, March.
    11. David Bergman & Andre A. Cire & Willem-Jan van Hoeve & J. N. Hooker, 2016. "Discrete Optimization with Decision Diagrams," INFORMS Journal on Computing, INFORMS, vol. 28(1), pages 47-66, February.
    12. Kerem Bülbül & Halil Şen, 2017. "An exact extended formulation for the unrelated parallel machine total weighted completion time problem," Journal of Scheduling, Springer, vol. 20(4), pages 373-389, August.
    13. Marjan van den Akker & Han Hoogeveen & Steef van de Velde, 2002. "Combining Column Generation and Lagrangean Relaxation to Solve a Single-Machine Common Due Date Problem," INFORMS Journal on Computing, INFORMS, vol. 14(1), pages 37-51, February.
    14. J. M. van den Akker & J. A. Hoogeveen & S. L. van de Velde, 1999. "Parallel Machine Scheduling by Column Generation," Operations Research, INFORMS, vol. 47(6), pages 862-872, December.
    15. Anuj Mehrotra & Michael A. Trick, 1996. "A Column Generation Approach for Graph Coloring," INFORMS Journal on Computing, INFORMS, vol. 8(4), pages 344-354, November.
    16. Andre A. Cire & Willem-Jan van Hoeve, 2013. "Multivalued Decision Diagrams for Sequencing Problems," Operations Research, INFORMS, vol. 61(6), pages 1411-1428, December.
    17. Scott Webster, 1992. "New Bounds for the Identical Parallel Processor Weighted Flow Time Problem," Management Science, INFORMS, vol. 38(1), pages 124-136, January.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Flores-Quiroz, Angela & Strunz, Kai, 2021. "A distributed computing framework for multi-stage stochastic planning of renewable power systems with energy storage as flexibility option," Applied Energy, Elsevier, vol. 291(C).
    2. Guopeng Song & Roel Leus, 2022. "Parallel Machine Scheduling Under Uncertainty: Models and Exact Algorithms," INFORMS Journal on Computing, INFORMS, vol. 34(6), pages 3059-3079, November.
    3. Margarita P. Castro & Andre A. Cire & J. Christopher Beck, 2022. "Decision Diagrams for Discrete Optimization: A Survey of Recent Advances," INFORMS Journal on Computing, INFORMS, vol. 34(4), pages 2271-2295, July.
    4. Kramer, Arthur & Dell’Amico, Mauro & Iori, Manuel, 2019. "Enhanced arc-flow formulations to minimize weighted completion time on identical parallel machines," European Journal of Operational Research, Elsevier, vol. 275(1), pages 67-79.
    5. Novak, Antonin & Sucha, Premysl & Novotny, Matej & Stec, Richard & Hanzalek, Zdenek, 2022. "Scheduling jobs with normally distributed processing times on parallel machines," European Journal of Operational Research, Elsevier, vol. 297(2), pages 422-441.
    6. Teobaldo Bulhões & Ruslan Sadykov & Anand Subramanian & Eduardo Uchoa, 2020. "On the exact solution of a large class of parallel machine scheduling problems," Journal of Scheduling, Springer, vol. 23(4), pages 411-429, August.
    7. Kramer, Arthur & Iori, Manuel & Lacomme, Philippe, 2021. "Mathematical formulations for scheduling jobs on identical parallel machines with family setup times and total weighted completion time minimization," European Journal of Operational Research, Elsevier, vol. 289(3), pages 825-840.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Arthur Kramer & Anand Subramanian, 2019. "A unified heuristic and an annotated bibliography for a large class of earliness–tardiness scheduling problems," Journal of Scheduling, Springer, vol. 22(1), pages 21-57, February.
    2. Kerem Bülbül & Halil Şen, 2017. "An exact extended formulation for the unrelated parallel machine total weighted completion time problem," Journal of Scheduling, Springer, vol. 20(4), pages 373-389, August.
    3. Stéphane Dauzère-Pérès & Sigrid Lise Nonås, 2023. "An improved decision support model for scheduling production in an engineer-to-order manufacturer," 4OR, Springer, vol. 21(2), pages 247-300, June.
    4. Dunstall, Simon & Wirth, Andrew, 2005. "A comparison of branch-and-bound algorithms for a family scheduling problem with identical parallel machines," European Journal of Operational Research, Elsevier, vol. 167(2), pages 283-296, December.
    5. Kramer, Arthur & Dell’Amico, Mauro & Iori, Manuel, 2019. "Enhanced arc-flow formulations to minimize weighted completion time on identical parallel machines," European Journal of Operational Research, Elsevier, vol. 275(1), pages 67-79.
    6. Zhi Pei & Mingzhong Wan & Ziteng Wang, 2020. "A new approximation algorithm for unrelated parallel machine scheduling with release dates," Annals of Operations Research, Springer, vol. 285(1), pages 397-425, February.
    7. Kerem Bülbül & Philip Kaminsky & Candace Yano, 2004. "Flow shop scheduling with earliness, tardiness, and intermediate inventory holding costs," Naval Research Logistics (NRL), John Wiley & Sons, vol. 51(3), pages 407-445, April.
    8. C N Potts & V A Strusevich, 2009. "Fifty years of scheduling: a survey of milestones," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 60(1), pages 41-68, May.
    9. Xiangtong Qi, 2005. "A logistics scheduling model: Inventory cost reduction by batching," Naval Research Logistics (NRL), John Wiley & Sons, vol. 52(4), pages 312-320, June.
    10. Kramer, Arthur & Iori, Manuel & Lacomme, Philippe, 2021. "Mathematical formulations for scheduling jobs on identical parallel machines with family setup times and total weighted completion time minimization," European Journal of Operational Research, Elsevier, vol. 289(3), pages 825-840.
    11. Rabia Nessah & Chengbin Chu, 2010. "Infinite split scheduling: a new lower bound of total weighted completion time on parallel machines with job release dates and unavailability periods," Annals of Operations Research, Springer, vol. 181(1), pages 359-375, December.
    12. Francis Sourd, 2009. "New Exact Algorithms for One-Machine Earliness-Tardiness Scheduling," INFORMS Journal on Computing, INFORMS, vol. 21(1), pages 167-175, February.
    13. Lotte Berghman & Roel Leus & Frits Spieksma, 2014. "Optimal solutions for a dock assignment problem with trailer transportation," Annals of Operations Research, Springer, vol. 213(1), pages 3-25, February.
    14. Teobaldo Bulhões & Ruslan Sadykov & Anand Subramanian & Eduardo Uchoa, 2020. "On the exact solution of a large class of parallel machine scheduling problems," Journal of Scheduling, Springer, vol. 23(4), pages 411-429, August.
    15. Plateau, M.-C. & Rios-Solis, Y.A., 2010. "Optimal solutions for unrelated parallel machines scheduling problems using convex quadratic reformulations," European Journal of Operational Research, Elsevier, vol. 201(3), pages 729-736, March.
    16. Natashia Boland & Riley Clement & Hamish Waterer, 2016. "A Bucket Indexed Formulation for Nonpreemptive Single Machine Scheduling Problems," INFORMS Journal on Computing, INFORMS, vol. 28(1), pages 14-30, February.
    17. Jans, Raf, 2010. "Classification of Dantzig-Wolfe reformulations for binary mixed integer programming problems," European Journal of Operational Research, Elsevier, vol. 204(2), pages 251-254, July.
    18. Wang, Ting & Baldacci, Roberto & Lim, Andrew & Hu, Qian, 2018. "A branch-and-price algorithm for scheduling of deteriorating jobs and flexible periodic maintenance on a single machine," European Journal of Operational Research, Elsevier, vol. 271(3), pages 826-838.
    19. Prahalad Venkateshan & Joseph Szmerekovsky & George Vairaktarakis, 2020. "A cutting plane approach for the multi-machine precedence-constrained scheduling problem," Annals of Operations Research, Springer, vol. 285(1), pages 247-271, February.
    20. Chung‐Yee Lee & Zhi‐Long Chen, 2000. "Scheduling jobs and maintenance activities on parallel machines," Naval Research Logistics (NRL), John Wiley & Sons, vol. 47(2), pages 145-165, March.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:inm:orijoc:v:30:y:2018:i:4:p:768-782. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Asher (email available below). General contact details of provider: https://edirc.repec.org/data/inforea.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.