Dynamic-Bayesian-Network-Based Project Cost Overrun Prediction Model

Author

Listed:
  • Sou-Sen Leu

    (Department of Construction Engineering, National Taiwan University of Science and Technology, 43 Keelung Rd., Sec. 4, Taipei 106, Taiwan)

  • Cheng-Yu Lu

    (Department of Construction Engineering, National Taiwan University of Science and Technology, 43 Keelung Rd., Sec. 4, Taipei 106, Taiwan)

  • Pei-Lin Wu

    (Department of Construction Engineering, National Taiwan University of Science and Technology, 43 Keelung Rd., Sec. 4, Taipei 106, Taiwan)

Abstract

One common problem in the construction industry is project cost overrun. Cost overrun can have significant impacts on financial profitability, project completion, project quality, and stakeholder satisfaction. The average percentage of construction project overrun can vary widely depending on the project type, size, complexity, and location. Many approaches can be adopted to prevent or mitigate project cost overrun, and one of them is a more accurate cost estimate and prediction. Several studies on the construction project cost overrun estimation and prediction have been conducted based on historical data; nevertheless, each project has its project characteristics and cost trend. Real-time, project-specific cost data are more reliable for forecasting the cost trend of the project itself. There are many influence factors that may interdependently affect the construction project cost overrun. This paper proposes a real-time predict cost overrun risk prediction model based on the influence factors and their interdependence as well as the corrective actions if adopted. This study used a dynamic Bayesian network (DBN) to formulate problem architecture and to use the input–output hidden Markov method (I/O HMM) with particle filter (PF) to run inference. Six building and mass rapid transit projects in Taiwan were used as model validation and comparison. The posterior probabilities from the DBN-based cost overrun risk prediction model were highly consistent with the cost overrun ratios of real construction projects. Moreover, it is superior to other prediction models in terms of accuracy. The proposed model could provide project managers with an early alert for cost overrun.

Suggested Citation

  • Sou-Sen Leu & Cheng-Yu Lu & Pei-Lin Wu, 2023. "Dynamic-Bayesian-Network-Based Project Cost Overrun Prediction Model," Sustainability, MDPI, vol. 15(5), pages 1-14, March.
  • Handle: RePEc:gam:jsusta:v:15:y:2023:i:5:p:4570-:d:1087210
    as

    Download full text from publisher

    File URL: https://www.mdpi.com/2071-1050/15/5/4570/pdf
    Download Restriction: no

    File URL: https://www.mdpi.com/2071-1050/15/5/4570/
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Peter Kaming & Paul Olomolaiye & Gary Holt & Frank Harris, 1997. "Factors influencing construction time and cost overruns on high-rise projects in Indonesia," Construction Management and Economics, Taylor & Francis Journals, vol. 15(1), pages 83-94.
    2. Odeck, James, 2004. "Cost overruns in road construction--what are their sizes and determinants?," Transport Policy, Elsevier, vol. 11(1), pages 43-53, January.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Rui Han & Shiqi Yang, 2023. "A Study on Industrial Heritage Renewal Strategy Based on Hybrid Bayesian Network," Sustainability, MDPI, vol. 15(13), pages 1-32, July.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Miranda Sarmento, J.J. & Renneboog, Luc, 2017. "Cost overruns in public sector investment projects," Other publications TiSEM 51799a3e-4c78-4dbd-b330-b, Tilburg University, School of Economics and Management.
    2. Moschouli, Eleni & Soecipto, Raden Murwantara & Vanelslander, Thierry, 2019. "Cost performance of transport infrastructure projects before and after the global financial crisis (GFC): Are differences observed in the conditions of project performance?," Research in Transportation Economics, Elsevier, vol. 75(C), pages 21-35.
    3. Miranda Sarmento, J.J., 2014. "Public private partnerships," Other publications TiSEM c7d4c978-234c-4f88-83ed-1, Tilburg University, School of Economics and Management.
    4. Chantal C. Cantarelli & Bert van Wee & Eric J. E. Molin & Bent Flyvbjerg, 2013. "Different Cost Performance: Different Determinants? The Case of Cost Overruns in Dutch Transportation Infrastructure Projects," Papers 1307.2179, arXiv.org, revised Jan 2015.
    5. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2018. "Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project," Sustainability, MDPI, vol. 10(12), pages 1-18, December.
    6. Cantarelli, C.C. & Flyvbjerg, B. & Buhl, S.L., 2012. "Geographical variation in project cost performance: the Netherlands versus worldwide," Journal of Transport Geography, Elsevier, vol. 24(C), pages 324-331.
    7. Herve Kabanda & Alex Romard & Fuze Yurtsever & Anjali Wadhera & Joshua Andrews & Craig Merrett, 2021. "Construction Time Estimation Function for Canadian Utility Scale Power Plants," Energies, MDPI, vol. 14(17), pages 1-16, August.
    8. Holz-Rau, Christian & Scheiner, Joachim, 2011. "Safety and travel time in cost-benefit analysis: A sensitivity analysis for North Rhine-Westphalia," Transport Policy, Elsevier, vol. 18(2), pages 336-346, March.
    9. Love, Peter E.D. & Ika, Lavagnon A. & Ahiaga-Dagbui, Dominic D., 2019. "On de-bunking ‘fake news’ in a post truth era: Why does the Planning Fallacy explanation for cost overruns fall short?," Transportation Research Part A: Policy and Practice, Elsevier, vol. 126(C), pages 397-408.
    10. Hugo Priemus & Bert van Wee (ed.), 2013. "International Handbook on Mega-Projects," Books, Edward Elgar Publishing, number 14791.
    11. Dahl, Roy Endré & Lorentzen, Sindre & Oglend, Atle & Osmundsen, Petter, 2017. "Pro-cyclical petroleum investments and cost overruns in Norway," Energy Policy, Elsevier, vol. 100(C), pages 68-78.
    12. Adriana Gómez-Cabrera & Amalia Sanz-Benlloch & Laura Montalban-Domingo & Jose Luis Ponz-Tienda & Eugenio Pellicer, 2020. "Identification of Factors Affecting the Performance of Rural Road Projects in Colombia," Sustainability, MDPI, vol. 12(18), pages 1-18, September.
    13. Minhyuk Jung & Shira You & Seokho Chi & Ilhan Yu & Bon-Gang Hwang, 2018. "The Relationship between Unbilled Accounts Receivable and Financial Performance of Construction Contractors," Sustainability, MDPI, vol. 10(8), pages 1-14, July.
    14. Chantal C. Cantarelli & Bent Flyvbjerg, 2013. "Mega-projects’ cost performance and lock-in: problems and solutions," Chapters, in: Hugo Priemus & Bert van Wee (ed.), International Handbook on Mega-Projects, chapter 15, pages 333-355, Edward Elgar Publishing.
    15. Edyta Plebankiewicz & Damian Wieczorek, 2020. "Prediction of Cost Overrun Risk in Construction Projects," Sustainability, MDPI, vol. 12(22), pages 1-15, November.
    16. Petr Halámek & Radka Matuszková & Michal Radimský, 2021. "Modernisation of Regional Roads Evaluated Using Ex-Post CBA," Sustainability, MDPI, vol. 13(4), pages 1-20, February.
    17. Cantarelli, C.C. & Molin, E.J.E. & van Wee, B. & Flyvbjerg, B., 2012. "Characteristics of cost overruns for Dutch transport infrastructure projects and the importance of the decision to build and project phases," Transport Policy, Elsevier, vol. 22(C), pages 49-56.
    18. Verweij, Stefan & van Meerkerk, Ingmar & Korthagen, Iris A., 2015. "Reasons for contract changes in implementing Dutch transportation infrastructure projects: An empirical exploration," Transport Policy, Elsevier, vol. 37(C), pages 195-202.
    19. Love, Peter E.D. & Zhou, Jingyang & Edwards, David J. & Irani, Zahir & Sing, Chun-Pong, 2017. "Off the rails: The cost performance of infrastructure rail projects," Transportation Research Part A: Policy and Practice, Elsevier, vol. 99(C), pages 14-29.
    20. Chong, Uven & Hopkins, Omar, 2016. "An international experience on the evolution of road costs during the project life cycle," Transport Policy, Elsevier, vol. 48(C), pages 60-66.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jsusta:v:15:y:2023:i:5:p:4570-:d:1087210. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.