IDEAS home Printed from https://ideas.repec.org/a/cys/ecocyb/v50y2017i2p291-309.html
   My bibliography  Save this article

A Novel Vibration Damping Optimization Algorithm for Resource Constrained Multi- Project Scheduling Problem

Author

Listed:
  • Esmaeil MEHDIZADEH

    (Department of Industrial Engineering, Faculty of Industrial & Mechanical Engineering, Qazvin Branch, Islamic Azad University Qazvin, Iran)

  • Hamidreza AKBARI

    (Department of Industrial Engineering, Faculty of Industrial & Mechanical Engineering, Qazvin Branch, Islamic Azad University Qazvin, Iran)

Abstract

In this paper, we propose a Vibration Damping Optimization (VDO) algorithm with resonator loop as a meta-heuristic algorithm for solving resource constrained multi-project scheduling problem (RCMPSP). The objective is to determine the start time of the projects activities such that the total completion time of processes under the existing constraints would be minimized. This is the first attempt to develop a VDO algorithm for solving the RCMPSP. Also, a new solution representation scheme in a matrix form and special solution procedures are proposed. We explain the elements of the algorithm and solve some problems generated for this model including large size and small size instances. The performance of our proposed algorithm is evaluated by comparison with Simulated Annealing (SA) algorithm. The response surface methodology (RSM) is applied for tuning the parameters of the algorithms. The promising computational results validate the effectiveness of the proposed algorithm.

Suggested Citation

  • Esmaeil MEHDIZADEH & Hamidreza AKBARI, 2017. "A Novel Vibration Damping Optimization Algorithm for Resource Constrained Multi- Project Scheduling Problem," ECONOMIC COMPUTATION AND ECONOMIC CYBERNETICS STUDIES AND RESEARCH, Faculty of Economic Cybernetics, Statistics and Informatics, vol. 51(2), pages 291-309.
  • Handle: RePEc:cys:ecocyb:v:50:y:2017:i:2:p:291-309
    as

    Download full text from publisher

    File URL: ftp://www.eadr.ro/RePEc/cys/ecocyb_pdf/ecocyb2_2017p291-309.pdf
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. A. Alan B. Pritsker & Lawrence J. Waiters & Philip M. Wolfe, 1969. "Multiproject Scheduling with Limited Resources: A Zero-One Programming Approach," Management Science, INFORMS, vol. 16(1), pages 93-108, September.
    2. Christofides, Nicos & Alvarez-Valdes, R. & Tamarit, J. M., 1987. "Project scheduling with resource constraints: A branch and bound approach," European Journal of Operational Research, Elsevier, vol. 29(3), pages 262-273, June.
    3. Antonio Lova & Pilar Tormos, 2001. "Analysis of Scheduling Schemes and Heuristic Rules Performance in Resource-Constrained Multiproject Scheduling," Annals of Operations Research, Springer, vol. 102(1), pages 263-286, February.
    4. Browning, Tyson R. & Yassine, Ali A., 2010. "Resource-constrained multi-project scheduling: Priority rule performance revisited," International Journal of Production Economics, Elsevier, vol. 126(2), pages 212-228, August.
    5. Erik Demeulemeester & Willy Herroelen, 1992. "A Branch-and-Bound Procedure for the Multiple Resource-Constrained Project Scheduling Problem," Management Science, INFORMS, vol. 38(12), pages 1803-1818, December.
    6. Beşikci, Umut & Bilge, Ümit & Ulusoy, Gündüz, 2015. "Multi-mode resource constrained multi-project scheduling and resource portfolio problem," European Journal of Operational Research, Elsevier, vol. 240(1), pages 22-31.
    7. Kolisch, Rainer & Sprecher, Arno, 1996. "PSPLIB - a project scheduling problem library," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 396, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    8. I. Kurtulus & E. W. Davis, 1982. "Multi-Project Scheduling: Categorization of Heuristic Rules Performance," Management Science, INFORMS, vol. 28(2), pages 161-172, February.
    9. Vercellis, Carlo, 1994. "Constrained multi-project plannings problems: A Lagrangean decomposition approach," European Journal of Operational Research, Elsevier, vol. 78(2), pages 267-275, October.
    10. Lova, Antonio & Maroto, Concepcion & Tormos, Pilar, 2000. "A multicriteria heuristic method to improve resource allocation in multiproject scheduling," European Journal of Operational Research, Elsevier, vol. 127(2), pages 408-424, December.
    11. Kolisch, Rainer & Hartmann, Sönke, 1998. "Heuristic algorithms for solving the resource-constrained project scheduling problem: Classification and computational analysis," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 469, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Gómez Sánchez, Mariam & Lalla-Ruiz, Eduardo & Fernández Gil, Alejandro & Castro, Carlos & Voß, Stefan, 2023. "Resource-constrained multi-project scheduling problem: A survey," European Journal of Operational Research, Elsevier, vol. 309(3), pages 958-976.
    2. Bredael, Dries & Vanhoucke, Mario, 2023. "Multi-project scheduling: A benchmark analysis of metaheuristic algorithms on various optimisation criteria and due dates," European Journal of Operational Research, Elsevier, vol. 308(1), pages 54-75.
    3. Ben Issa, Samer & Patterson, Raymond A. & Tu, Yiliu, 2021. "Solving resource-constrained multi-project environment under different activity assumptions," International Journal of Production Economics, Elsevier, vol. 232(C).
    4. Rob Eynde & Mario Vanhoucke, 2020. "Resource-constrained multi-project scheduling: benchmark datasets and decoupled scheduling," Journal of Scheduling, Springer, vol. 23(3), pages 301-325, June.
    5. Krüger, Doreen & Scholl, Armin, 2009. "A heuristic solution framework for the resource constrained (multi-)project scheduling problem with sequence-dependent transfer times," European Journal of Operational Research, Elsevier, vol. 197(2), pages 492-508, September.
    6. Schirmer, Andreas & Riesenberg, Sven, 1997. "Parameterized heuristics for project scheduling: Biased random sampling methods," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 456, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    7. Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
    8. Gonçalves, J.F. & Mendes, J.J.M. & Resende, M.G.C., 2008. "A genetic algorithm for the resource constrained multi-project scheduling problem," European Journal of Operational Research, Elsevier, vol. 189(3), pages 1171-1190, September.
    9. Kolisch, Rainer, 1994. "Serial and parallel resource-constrained projekt scheduling methodes revisited: Theory and computation," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 344, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    10. Anıl Can & Gündüz Ulusoy, 2014. "Multi-project scheduling with two-stage decomposition," Annals of Operations Research, Springer, vol. 217(1), pages 95-116, June.
    11. Yaghoubi, Saeed & Noori, Siamak & Azaron, Amir & Fynes, Brian, 2015. "Resource allocation in multi-class dynamic PERT networks with finite capacity," European Journal of Operational Research, Elsevier, vol. 247(3), pages 879-894.
    12. Van Eynde, Rob & Vanhoucke, Mario, 2022. "New summary measures and datasets for the multi-project scheduling problem," European Journal of Operational Research, Elsevier, vol. 299(3), pages 853-868.
    13. Brucker, Peter & Drexl, Andreas & Mohring, Rolf & Neumann, Klaus & Pesch, Erwin, 1999. "Resource-constrained project scheduling: Notation, classification, models, and methods," European Journal of Operational Research, Elsevier, vol. 112(1), pages 3-41, January.
    14. He, Yukang & Jia, Tao & Zheng, Weibo, 2023. "Tabu search for dedicated resource-constrained multiproject scheduling to minimise the maximal cash flow gap under uncertainty," European Journal of Operational Research, Elsevier, vol. 310(1), pages 34-52.
    15. Kolisch, R. & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Omega, Elsevier, vol. 29(3), pages 249-272, June.
    16. M. Suresh & Pankaj Dutta & Karuna Jain, 2015. "Resource Constrained Multi-Project Scheduling Problem with Resource Transfer Times," Asia-Pacific Journal of Operational Research (APJOR), World Scientific Publishing Co. Pte. Ltd., vol. 32(06), pages 1-30, December.
    17. Kolisch, Rainer, 1996. "Serial and parallel resource-constrained project scheduling methods revisited: Theory and computation," European Journal of Operational Research, Elsevier, vol. 90(2), pages 320-333, April.
    18. Browning, Tyson R. & Yassine, Ali A., 2010. "Resource-constrained multi-project scheduling: Priority rule performance revisited," International Journal of Production Economics, Elsevier, vol. 126(2), pages 212-228, August.
    19. Yaghoubi, Saeed & Noori, Siamak & Azaron, Amir & Tavakkoli-Moghaddam, Reza, 2011. "Resource allocation in dynamic PERT networks with finite capacity," European Journal of Operational Research, Elsevier, vol. 215(3), pages 670-678, December.
    20. Jan Böttcher & Andreas Drexl & Rainer Kolisch & Frank Salewski, 1999. "Project Scheduling Under Partially Renewable Resource Constraints," Management Science, INFORMS, vol. 45(4), pages 543-559, April.

    More about this item

    Keywords

    multi-project; scheduling problem; resource constraints; project management; vibration damping optimization.;
    All these keywords.

    JEL classification:

    • M11 - Business Administration and Business Economics; Marketing; Accounting; Personnel Economics - - Business Administration - - - Production Management
    • C44 - Mathematical and Quantitative Methods - - Econometric and Statistical Methods: Special Topics - - - Operations Research; Statistical Decision Theory
    • C61 - Mathematical and Quantitative Methods - - Mathematical Methods; Programming Models; Mathematical and Simulation Modeling - - - Optimization Techniques; Programming Models; Dynamic Analysis

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:cys:ecocyb:v:50:y:2017:i:2:p:291-309. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Corina Saman (email available below). General contact details of provider: https://edirc.repec.org/data/feasero.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.