IDEAS home Printed from https://ideas.repec.org/p/zbw/cauman/404.html
   My bibliography  Save this paper

Shortcomings of MRP II and a new planning meta-method

Author

Listed:
  • Kimms, Alf
  • Drexl, Andreas

Abstract

Lot sizing when done for the short-term heavily interacts with the sequencing decisions for the operations to be performed. Especially for real-world situations where capacities are scarce, demand is dynamic, and precedence relations among the operations have to be taken into account the MRP II logic which is implemented in most production planning systems does not satisfy. In this paper, we will reveal the shortcomings of MRP II by means of an example. A mixed-integer programming model is then defined to specify the problem of capacitated, dynamic, multi-level Iot sizing and scheduling. Also, we present a generic solution method (a so-called meta-method) which may be used as a basis of more advanced implementations that may replace the traditional MRP II Systems.

Suggested Citation

  • Kimms, Alf & Drexl, Andreas, 1996. "Shortcomings of MRP II and a new planning meta-method," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 404, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
  • Handle: RePEc:zbw:cauman:404
    as

    Download full text from publisher

    File URL: https://www.econstor.eu/bitstream/10419/149035/1/manuskript_404.pdf
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Kimms, Alf, 1994. "Optimal multi-level lot sizing and scheduling with dedicated machines," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 351, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    2. Kimms, Alf, 1994. "Demand shuffle - a novel method for multi-level proportional lot sizing and scheduling," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 355, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    3. Haase, Knut & Kimms, Alf, 1996. "Lot sizing and scheduling with sequence dependent setup costs and times and efficient rescheduling opportunities," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 393, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    4. L. S. Lasdon & R. C. Terjung, 1971. "An Efficient Algorithm for Multi-Item Scheduling," Operations Research, INFORMS, vol. 19(4), pages 946-969, August.
    5. Kimms, Alf, 1993. "A cellular automaton based heuristic for multi-level lot sizing and scheduling," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 331, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    6. Lotfi, Vahid & Chen, Wun-Hwa, 1991. "An optimal algorithm for the multi-item capacitated production planning problem," European Journal of Operational Research, Elsevier, vol. 52(2), pages 179-193, May.
    7. Drexl, Andreas & Haase, Knut, 1995. "Proportional lotsizing and scheduling," International Journal of Production Economics, Elsevier, vol. 40(1), pages 73-87, June.
    8. Gary D. Eppen & R. Kipp Martin, 1987. "Solving Multi-Item Capacitated Lot-Sizing Problems Using Variable Redefinition," Operations Research, INFORMS, vol. 35(6), pages 832-848, December.
    9. Kimms, A., 1996. "Multi-level, single-machine lot sizing and scheduling (with initial inventory)," European Journal of Operational Research, Elsevier, vol. 89(1), pages 86-99, February.
    10. Kirca, Omer & Kokten, Melih, 1994. "A new heuristic approach for the multi-item dynamic lot sizing problem," European Journal of Operational Research, Elsevier, vol. 75(2), pages 332-341, June.
    11. Zapfel, Gunther & Missbauer, Hubert, 1993. "New concepts for production planning and control," European Journal of Operational Research, Elsevier, vol. 67(3), pages 297-320, June.
    12. Moustapha Diaby & Harish C. Bahl & Mark H. Karwan & Stanley Zionts, 1992. "A Lagrangean Relaxation Approach for Very-Large-Scale Capacitated Lot-Sizing," Management Science, INFORMS, vol. 38(9), pages 1329-1340, September.
    13. Sohner, Volkmar & Schneeweiss, Christoph, 1995. "Hierarchically integrated lot size optimization," European Journal of Operational Research, Elsevier, vol. 86(1), pages 73-90, October.
    14. Marc Salomon & Leo G. Kroon & Roelof Kuik & Luk N. Van Wassenhove, 1991. "Some Extensions of the Discrete Lotsizing and Scheduling Problem," Management Science, INFORMS, vol. 37(7), pages 801-812, July.
    15. van Hoesel, Stan & Kolen, Antoon, 1994. "A linear description of the discrete lot-sizing and scheduling problem," European Journal of Operational Research, Elsevier, vol. 75(2), pages 342-353, June.
    16. Haase, Knut, 1993. "Capacitated lot-sizing with linked production quantities of adjacent periods," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 334, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    17. Fleischmann, Bernhard, 1990. "The discrete lot-sizing and scheduling problem," European Journal of Operational Research, Elsevier, vol. 44(3), pages 337-348, February.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Kimms, Alf, 1996. "Improved lower bounds for the proportional lot sizing and scheduling problem," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 414, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    2. Kimms, Alf & Drexl, Andreas, 1996. "Proportional lot sizing and scheduling: Some extensions," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 407, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    3. Drexl, A. & Kimms, A., 1997. "Lot sizing and scheduling -- Survey and extensions," European Journal of Operational Research, Elsevier, vol. 99(2), pages 221-235, June.
    4. Kimms, Alf & Drexl, Andreas, 1996. "Some insights into proportional lot sizing and scheduling," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 406, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    5. Kimms, Alf, 1996. "A genetic algorithm for multi-level, multi-machine lot sizing and scheduling," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 415, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    6. Jans, Raf & Degraeve, Zeger, 2007. "Meta-heuristics for dynamic lot sizing: A review and comparison of solution approaches," European Journal of Operational Research, Elsevier, vol. 177(3), pages 1855-1875, March.
    7. Kimms, A, 1998. "Stability Measures for Rolling Schedules with Applications to Capacity Expansion Planning, Master Production Scheduling, and Lot Sizing," Omega, Elsevier, vol. 26(3), pages 355-366, June.
    8. Kimms, Alf, 1996. "Stability measures for rolling schedules with applications to capacity expansion planning, master production scheduling, and lot sizing," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 418, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    9. Jans, R.F. & Degraeve, Z., 2005. "Modeling Industrial Lot Sizing Problems: A Review," ERIM Report Series Research in Management ERS-2005-049-LIS, Erasmus Research Institute of Management (ERIM), ERIM is the joint research institute of the Rotterdam School of Management, Erasmus University and the Erasmus School of Economics (ESE) at Erasmus University Rotterdam.
    10. Drexl, Andreas & Jordan, Carsten & Kimms, Alf, 1997. "Gruppierungs- und Reihenfolgeprobleme in der Fertigung," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 447, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    11. Drexl, Andreas & Haase, Knut, 1995. "Proportional lotsizing and scheduling," International Journal of Production Economics, Elsevier, vol. 40(1), pages 73-87, June.
    12. Alf Kimms, 1998. "Ablauforganisation bei Serienproduktion in Fließfertigungssystemen," Schmalenbach Journal of Business Research, Springer, vol. 50(7), pages 641-655, July.
    13. Drexl, Andreas & Haase, Knut, 1997. "Vorbeugende Instandhaltung und Eilaufträge in der Produktionsplanung," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 450, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    14. Lee, Younsoo & Lee, Kyungsik, 2020. "Lot-sizing and scheduling in flat-panel display manufacturing process," Omega, Elsevier, vol. 93(C).
    15. Ozdamar, Linet & Birbil, Sevket Ilker, 1998. "Hybrid heuristics for the capacitated lot sizing and loading problem with setup times and overtime decisions," European Journal of Operational Research, Elsevier, vol. 110(3), pages 525-547, November.
    16. Karina Copil & Martin Wörbelauer & Herbert Meyr & Horst Tempelmeier, 2017. "Simultaneous lotsizing and scheduling problems: a classification and review of models," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 39(1), pages 1-64, January.
    17. Bouchriha, Hanen & Ouhimmou, Mustapha & D'Amours, Sophie, 2007. "Lot sizing problem on a paper machine under a cyclic production approach," International Journal of Production Economics, Elsevier, vol. 105(2), pages 318-328, February.
    18. Drexl, Andreas & Kimms, Alf, 1996. "Lot sizing and scheduling: Survey and extensions," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 421, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    19. Fandel, Gunter & Stammen-Hegene, Cathrin, 2006. "Simultaneous lot sizing and scheduling for multi-product multi-level production," International Journal of Production Economics, Elsevier, vol. 104(2), pages 308-316, December.
    20. Carsten Jordan & Andreas Drexl, 1998. "Discrete Lotsizing and Scheduling by Batch Sequencing," Management Science, INFORMS, vol. 44(5), pages 698-713, May.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:zbw:cauman:404. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: ZBW - Leibniz Information Centre for Economics (email available below). General contact details of provider: https://edirc.repec.org/data/ibkiede.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.