Warm-Mix Asphalt Study: First-Level Analysis of Phase 2 HVS and Laboratory Testing, and Phase 1 and Phase 2 Forensic Assessments

Author

Listed:
  • Jones, David
  • Wu, Rongzong
  • Tsai, Bor-Wen
  • Harvey, John T.

Abstract

This first-level report describes the second phase of a warm-mix asphalt study, which compares the performance of a control mix, produced and constructed at conventional hot-mix asphalt temperatures, with three mixes produced with warm-mix additives, produced and compacted at approximately 35°C (60°F) lower than the control. The additives tested included Advera WMA®, EvothermTM, and Sasobit®. The results of the second phase of Heavy Vehicle Simulator (HVS) and laboratory testing are discussed. The study includes these key findings: • Based on the results of HVS testing and a forensic investigation of the test track, it is concluded that the use of any of the three warm-mix asphalt technologies included in this experiment will not significantly influence the rutting performance or moisture sensitivity of the mix. • The duration and rut depths of the embedment phase of the warm-mix sections were approximately half that of the control, an opposite trend to that observed in Phase 1, indicating that the effects of oxidation of the binder at lower temperatures may only influence rutting performance in the first few months after construction. • No difficulty was experienced in the preparation of field-mixed, laboratory-compacted specimens at actual construction temperatures. Lower air-void contents were achieved in the laboratory-prepared specimens compared to specimens sampled from the HVS test track. • Limited laboratory moisture sensitivity testing confirmed that all the mixes tested were potentially susceptible to moisture damage. There was, however, no difference in the level of moisture sensitivity between the control mix and mixes with the additives assessed in this study. The HVS and laboratory testing completed in this phase of the study support the findings of the first phase of testing in that no results were obtained to suggest that the warm-mix technologies assessed in this study should not be used in new construction, rehabilitation, or pavement preservation applications in California. Final recommendations on the use of warm-mix asphalt will only be made after further research and monitoring of full-scale pilot studies on inservice pavements is completed. It is recommended that use of warm-mix technologies continue in full-scale pilot studies on in-service pavements until a decision is made on statewide use.

Suggested Citation

  • Jones, David & Wu, Rongzong & Tsai, Bor-Wen & Harvey, John T., 2009. "Warm-Mix Asphalt Study: First-Level Analysis of Phase 2 HVS and Laboratory Testing, and Phase 1 and Phase 2 Forensic Assessments," Institute of Transportation Studies, Working Paper Series qt9ws8s626, Institute of Transportation Studies, UC Davis.
  • Handle: RePEc:cdl:itsdav:qt9ws8s626
    as

    Download full text from publisher

    File URL: https://www.escholarship.org/uc/item/9ws8s626.pdf;origin=repeccitec
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Jones, David & Wu, Rongzong & Tsai, Bor-Wen & Lu, Qing & Harvey, John T., 2008. "Warm-Mix Asphalt Study: Test Track Construction and First-Level Analysis of Phase 1 HVS and Laboratory Testing," Institute of Transportation Studies, Working Paper Series qt6tc86078, Institute of Transportation Studies, UC Davis.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Jones, D., 2014. "Warm-Mix Asphalt Study: Summary Report on Warm-Mix Asphalt Research in California," Institute of Transportation Studies, Working Paper Series qt6pp4p46t, Institute of Transportation Studies, UC Davis.
    2. Farshidi, F. & Jones, D. & Harvey, J. T., 2013. "Warm-Mix Asphalt Study: Evaluation of Rubberized Hot- and Warm-Mix Asphalt with Respect to Emissions," Institute of Transportation Studies, Working Paper Series qt24x065cd, Institute of Transportation Studies, UC Davis.
    3. Jones, David & Farshidi, Frank & Harvey, John T., 2013. "Warm-Mix Asphalt Study: Summary Report on Rubberized Warm-Mix Asphalt Research," Institute of Transportation Studies, Working Paper Series qt1gs139mk, Institute of Transportation Studies, UC Davis.
    4. Farshidi, Frank & Jones, David & Harvey, John T., 2013. "Warm-Mix Asphalt Study: Evaluation of Hot and Warm Mix Asphalt with Respect to Binder Aging," Institute of Transportation Studies, Working Paper Series qt91x0c3hd, Institute of Transportation Studies, UC Davis.
    5. Jones, D. & Tsai, B., 2012. "Warm-Mix Asphalt Study: First-Level Analysis of Phase 2b Laboratory Testing on Laboratory-Prepared Specimens," Institute of Transportation Studies, Working Paper Series qt39c2g14q, Institute of Transportation Studies, UC Davis.
    6. Jones, D., 2013. "Warm-Mix Asphalt Study: Field Test Performance Evaluation," Institute of Transportation Studies, Working Paper Series qt4bp7602f, Institute of Transportation Studies, UC Davis.
    7. Jones, David & Tsai, Bor-Wen & Signore, James, 2010. "Warm-Mix Asphalt Study: Laboratory Test Results for AkzoNobel RedisetTM WMX," Institute of Transportation Studies, Working Paper Series qt1hm6760x, Institute of Transportation Studies, UC Davis.
    8. Jones, David & Wu, Rongzong & Tsai, Bor-Wen & Harvey, John T., 2011. "Warm-Mix Asphalt Study: Test Track Construction and FirstLevel Analysis of Phase 3b HVS and Laboratory Testing (Rubberized Asphalt, Mix Design #2)," Institute of Transportation Studies, Working Paper Series qt8j93g6t2, Institute of Transportation Studies, UC Davis.
    9. Jones, David & Wu, Rongzong & Tsai, Bor-Wen & Harvey, John T., 2011. "Warm-Mix Asphalt Study: Test Track Construction and First-Level Analysis of Phase 3a HVS and Laboratory Testing (Rubberized Asphalt, Mix Design #1)," Institute of Transportation Studies, Working Paper Series qt9958p8fc, Institute of Transportation Studies, UC Davis.

    More about this item

    Keywords

    Engineering;

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:cdl:itsdav:qt9ws8s626. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Lisa Schiff (email available below). General contact details of provider: https://edirc.repec.org/data/itucdus.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.