Application Of Primavera P6 Software For Scheduling Single Constrained Resource In Small Gas Station Project

Author

Listed:
  • Mabrouka Shahat Younis Elfargani

    (Civil Engineering Department, Al Gubba, University of Derna, Libya)

  • Ahmed Fthallh Mhmmed

    (Omar AL Mukhtar University, Civil Engineering Dep., AL-Gubba, Libya)

  • Aimen Emragha Abd alati Abd allah

    (Omar AL Mukhtar University, Civil Engineering Dep., AL-Gubba, Libya)

  • Abd aullah Mansor Algedo

    (Omar AL Mukhtar University, Civil Engineering Dep., AL-Gubba, Libya)

  • Hamad Fryaj Hamad Amer

    (Omar AL Mukhtar University, Civil Engineering Dep., AL-Gubba, Libya)

  • Youssf Tiher Abobker Hasan

    (Omar AL Mukhtar University, Civil Engineering Dep., AL-Gubba, Libya)

Abstract

The Success in the use of the Primavera P6 Software to schedule the project depends on the size of the project, the level of its complexity the time allocated for its execution and the requirements dictated by owner of the project……etc. The basic idea behind the proposed system is the use of software set up for this purpose in order to delineate start- finish time by applying Critical Path Method, the Primavera P6 Software for scheduling single constrained resource in projects. They may only of solutions start by scheduling and analyzing the resource time period by time period, and resource by resource when the amount of the resources available is exceeded the method of tasks is examined and rare resources are then allocated according is the levels of priority. A major position arises then: how to increase the time necessary for the completion of the project with the remaining minimum with due respect to the labor limitations. The answer lies in the application of the Primavera P6 Software which is used in practical situations, so as to avoid mathematical complications which are characteristics of perfect model methods. In order to achieve the best solution, activities are re- scheduled based on labor constraints according to various numerous bases. These were applied on a project for the construction of a small size Gas Station, classified under small construction projects which include 29 activities. The 3 stages of implementation were applied tested to the project mainly planning, scheduling and control. We obtained the desired results with an increase in the time allocated for the completion of the project with strictest minimum possible while respecting labor constraints.

Suggested Citation

  • Mabrouka Shahat Younis Elfargani & Ahmed Fthallh Mhmmed & Aimen Emragha Abd alati Abd allah & Abd aullah Mansor Algedo & Hamad Fryaj Hamad Amer & Youssf Tiher Abobker Hasan, 2022. "Application Of Primavera P6 Software For Scheduling Single Constrained Resource In Small Gas Station Project," Engineering Heritage Journal (GWK), Zibeline International Publishing, vol. 6(2), pages 65-72, October.
  • Handle: RePEc:zib:zbngwk:v:6:y:2022:i:2:p:65-72
    DOI: 10.26480/gwk.02.2022.65.72
    as

    Download full text from publisher

    File URL: https://enggheritage.com/archives/2gwk2022/2gwk2022-65-72.pdf
    Download Restriction: no

    File URL: https://libkey.io/10.26480/gwk.02.2022.65.72?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. J A Bowers, 2000. "Multiple schedules and measures of resource constrained float," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 51(7), pages 855-862, July.
    2. Jerome D. Wiest, 1964. "Some Properties of Schedules for Large Projects with Limited Resources," Operations Research, INFORMS, vol. 12(3), pages 395-418, June.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Jan Böttcher & Andreas Drexl & Rainer Kolisch & Frank Salewski, 1999. "Project Scheduling Under Partially Renewable Resource Constraints," Management Science, INFORMS, vol. 45(4), pages 543-559, April.
    2. W Herroelen & R Leus, 2005. "Identification and illumination of popular misconceptions about project scheduling and time buffering in a resource-constrained environment," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 56(1), pages 102-109, January.
    3. Kyunghwan Kim, 2020. "Generalized Resource-Constrained Critical Path Method to Improve Sustainability in Construction Project Scheduling," Sustainability, MDPI, vol. 12(21), pages 1-19, October.
    4. Böttcher, Jan & Drexl, Andreas & Kolisch, Rainer & Salewski, Frank, 1996. "Project scheduling under partially renewable resource constraints," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 398, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    5. Ballestí­n, Francisco & Valls, Vicente & Quintanilla, Sacramento, 2008. "Pre-emption in resource-constrained project scheduling," European Journal of Operational Research, Elsevier, vol. 189(3), pages 1136-1152, September.
    6. Scott E. Sampson & Elliott N. Weiss, 1993. "Local search techniques for the generalized resource constrained project scheduling problem," Naval Research Logistics (NRL), John Wiley & Sons, vol. 40(5), pages 665-675, August.
    7. Kolisch, Rainer & Padman, Rema, 1997. "An integrated survey of project scheduling," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 463, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    8. Lova, Antonio & Maroto, Concepcion & Tormos, Pilar, 2000. "A multicriteria heuristic method to improve resource allocation in multiproject scheduling," European Journal of Operational Research, Elsevier, vol. 127(2), pages 408-424, December.
    9. Valls, Vicente & Ballestin, Francisco & Quintanilla, Sacramento, 2005. "Justification and RCPSP: A technique that pays," European Journal of Operational Research, Elsevier, vol. 165(2), pages 375-386, September.
    10. Kolisch, R. & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Omega, Elsevier, vol. 29(3), pages 249-272, June.
    11. Dumez, Dorian & Tilk, Christian & Irnich, Stefan & Lehuédé, Fabien & Olkis, Katharina & Péton, Olivier, 2023. "A matheuristic for a 2-echelon vehicle routing problem with capacitated satellites and reverse flows," European Journal of Operational Research, Elsevier, vol. 305(1), pages 64-84.
    12. Sprecher, Arno & Kolisch, Rainer & Drexl, Andreas, 1995. "Semi-active, active, and non-delay schedules for the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 80(1), pages 94-102, January.
    13. Sprecher, Arno & Kolisch, Rainer & Drexl, Andreas, 1993. "Semi-active, active and non-delay schedules for the resource-constrained project scheduling problem," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 307, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    14. Wan-An Cui, 2018. "Critical Sequences and Resource Links Optimization in Resource-Constrained Project Scheduling," Asia-Pacific Journal of Operational Research (APJOR), World Scientific Publishing Co. Pte. Ltd., vol. 35(05), pages 1-26, October.
    15. Drexl, Andreas & Kolisch, Rainer, 1994. "Model-based assembly management in machine tool manufacturing," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 346, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    16. Demeulemeester, Erik L. & Herroelen, Willy S., 1996. "An efficient optimal solution procedure for the preemptive resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 90(2), pages 334-348, April.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:zib:zbngwk:v:6:y:2022:i:2:p:65-72. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Zibeline International Publishing (email available below). General contact details of provider: https://enggheritage.com/ .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.