Identification and illumination of popular misconceptions about project scheduling and time buffering in a resource-constrained environment

Author

Listed:
  • W Herroelen

    (Katholieke Universiteit Leuven)

  • R Leus

    (Katholieke Universiteit Leuven)

Abstract

The lack of proper project planning is often cited as one of the main reasons why projects fail to be completed in time and within budget. In this paper, we identify and illuminate several possible misconceptions that go round in project management periodicals and in the mindset of practising project managers and that may hamper successful project planning. The misconceptions relate to the role of the critical path, the critical sequence (critical chain), active schedules, and the insertion of buffers in the baseline schedule as a protective mechanism against schedule distortions during project execution. The possible fallacies are illustrated using example schedules developed for an illustrative project.

Suggested Citation

  • W Herroelen & R Leus, 2005. "Identification and illumination of popular misconceptions about project scheduling and time buffering in a resource-constrained environment," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 56(1), pages 102-109, January.
  • Handle: RePEc:pal:jorsoc:v:56:y:2005:i:1:d:10.1057_palgrave.jors.2601813
    DOI: 10.1057/palgrave.jors.2601813
    as

    Download full text from publisher

    File URL: http://link.springer.com/10.1057/palgrave.jors.2601813
    File Function: Abstract
    Download Restriction: Access to full text is restricted to subscribers.

    File URL: https://libkey.io/10.1057/palgrave.jors.2601813?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Kolisch, Rainer, 1999. "Resource allocation capabilities of commercial project management software packages," Publications of Darmstadt Technical University, Institute for Business Studies (BWL) 7938, Darmstadt Technical University, Department of Business Administration, Economics and Law, Institute for Business Studies (BWL).
    2. Kolisch, R. & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Omega, Elsevier, vol. 29(3), pages 249-272, June.
    3. Rainer Kolisch, 1999. "Resource Allocation Capabilities of Commercial Project Management Software Packages," Interfaces, INFORMS, vol. 29(4), pages 19-31, August.
    4. Willis, R. J., 1985. "Critical path analysis and resource constrained project scheduling -- Theory and practice," European Journal of Operational Research, Elsevier, vol. 21(2), pages 149-155, August.
    5. A. R. Klingel, Jr., 1966. "Bias in Pert Project Completion Time Calculations for a Real Network," Management Science, INFORMS, vol. 13(4), pages 194-201, December.
    6. Sprecher, Arno & Kolisch, Rainer & Drexl, Andreas, 1995. "Semi-active, active, and non-delay schedules for the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 80(1), pages 94-102, January.
    7. P Tormos & A Lova, 2001. "Tools for resource-constrained project scheduling and control: forward and backward slack analysis," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 52(7), pages 779-788, July.
    8. Richard J. Schonberger, 1981. "Why Projects Are “Always” Late: A Rationale Based on Manual Simulation of a PERT/CPM Network," Interfaces, INFORMS, vol. 11(5), pages 66-70, October.
    9. Brucker, Peter & Drexl, Andreas & Mohring, Rolf & Neumann, Klaus & Pesch, Erwin, 1999. "Resource-constrained project scheduling: Notation, classification, models, and methods," European Journal of Operational Research, Elsevier, vol. 112(1), pages 3-41, January.
    10. Wilson, James M., 2003. "Gantt charts: A centenary appreciation," European Journal of Operational Research, Elsevier, vol. 149(2), pages 430-437, September.
    11. Jerome D. Wiest, 1964. "Some Properties of Schedules for Large Projects with Limited Resources," Operations Research, INFORMS, vol. 12(3), pages 395-418, June.
    12. De Wit, Jan & Herroelen, Willy, 1990. "An evaluation of microcomputer-based software packages for project management," European Journal of Operational Research, Elsevier, vol. 49(1), pages 102-139, November.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Wan-An Cui, 2018. "Critical Sequences and Resource Links Optimization in Resource-Constrained Project Scheduling," Asia-Pacific Journal of Operational Research (APJOR), World Scientific Publishing Co. Pte. Ltd., vol. 35(05), pages 1-26, October.
    2. Liu Shu-Shun & Kuo-Chuan Shih, 2009. "A framework of critical resource chain for project schedule analysis," Construction Management and Economics, Taylor & Francis Journals, vol. 27(9), pages 857-869.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Kolisch, R. & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Omega, Elsevier, vol. 29(3), pages 249-272, June.
    2. Philipp Baumann & Norbert Trautmann, 2016. "A note on the selection of priority rules in software packages for project management," Flexible Services and Manufacturing Journal, Springer, vol. 28(4), pages 694-702, December.
    3. Valls, Vicente & Ballestin, Francisco & Quintanilla, Sacramento, 2005. "Justification and RCPSP: A technique that pays," European Journal of Operational Research, Elsevier, vol. 165(2), pages 375-386, September.
    4. Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre (Ed.), 2000. "Jahresbericht 1999," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 522, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    5. Bouleimen, K. & Lecocq, H., 2003. "A new efficient simulated annealing algorithm for the resource-constrained project scheduling problem and its multiple mode version," European Journal of Operational Research, Elsevier, vol. 149(2), pages 268-281, September.
    6. Ballestí­n, Francisco & Valls, Vicente & Quintanilla, Sacramento, 2008. "Pre-emption in resource-constrained project scheduling," European Journal of Operational Research, Elsevier, vol. 189(3), pages 1136-1152, September.
    7. Mingers, John & White, Leroy, 2010. "A review of the recent contribution of systems thinking to operational research and management science," European Journal of Operational Research, Elsevier, vol. 207(3), pages 1147-1161, December.
    8. Kolisch, Rainer & Padman, Rema, 1997. "An integrated survey of project scheduling," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 463, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    9. Lova, Antonio & Maroto, Concepcion & Tormos, Pilar, 2000. "A multicriteria heuristic method to improve resource allocation in multiproject scheduling," European Journal of Operational Research, Elsevier, vol. 127(2), pages 408-424, December.
    10. Andreas Schirmer, 2000. "Case‐based reasoning and improved adaptive search for project scheduling," Naval Research Logistics (NRL), John Wiley & Sons, vol. 47(3), pages 201-222, April.
    11. Moumene, Khaled & Ferland, Jacques A., 2009. "Activity list representation for a generalization of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 199(1), pages 46-54, November.
    12. Weglarz, Jan & Józefowska, Joanna & Mika, Marek & Waligóra, Grzegorz, 2011. "Project scheduling with finite or infinite number of activity processing modes - A survey," European Journal of Operational Research, Elsevier, vol. 208(3), pages 177-205, February.
    13. Browning, Tyson R. & Yassine, Ali A., 2010. "Resource-constrained multi-project scheduling: Priority rule performance revisited," International Journal of Production Economics, Elsevier, vol. 126(2), pages 212-228, August.
    14. Wendi Tian & Erik Demeulemeester, 2014. "Railway scheduling reduces the expected project makespan over roadrunner scheduling in a multi-mode project scheduling environment," Annals of Operations Research, Springer, vol. 213(1), pages 271-291, February.
    15. Andrzej Kozik, 2017. "Handling precedence constraints in scheduling problems by the sequence pair representation," Journal of Combinatorial Optimization, Springer, vol. 33(2), pages 445-472, February.
    16. Xiong, Jian & Leus, Roel & Yang, Zhenyu & Abbass, Hussein A., 2016. "Evolutionary multi-objective resource allocation and scheduling in the Chinese navigation satellite system project," European Journal of Operational Research, Elsevier, vol. 251(2), pages 662-675.
    17. M. Vanhoucke, 2006. "A scatter search procedure for maximizing the net present value of a project under renewable resource constraints," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 06/417, Ghent University, Faculty of Economics and Business Administration.
    18. Dieter Debels & Mario Vanhoucke, 2007. "A Decomposition-Based Genetic Algorithm for the Resource-Constrained Project-Scheduling Problem," Operations Research, INFORMS, vol. 55(3), pages 457-469, June.
    19. Schirmer, Andreas & Riesenberg, Sven, 1997. "Parameterized heuristics for project scheduling: Biased random sampling methods," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 456, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    20. Moukrim, Aziz & Quilliot, Alain & Toussaint, Hélène, 2015. "An effective branch-and-price algorithm for the Preemptive Resource Constrained Project Scheduling Problem based on minimal Interval Order Enumeration," European Journal of Operational Research, Elsevier, vol. 244(2), pages 360-368.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:pal:jorsoc:v:56:y:2005:i:1:d:10.1057_palgrave.jors.2601813. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Sonal Shukla or Springer Nature Abstracting and Indexing (email available below). General contact details of provider: http://www.palgrave-journals.com/ .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.