The Effectiveness of Risk Management: An Analysis of Project Risk Planning Across Industries and Countries

Author

Listed:
  • Ofer Zwikael
  • Mark Ahn

Abstract

This article examines the effectiveness of current risk management practices to reduce project risk using a multinational, multi‐industry study across different scenarios and cultures. A survey was administered to 701 project managers, and their supervisors, in seven industries and three diverse countries (New Zealand, Israel, and Japan), in multiple languages during the 2002–2007 period. Results of this study show that project context—industry and country where a project is executed—significantly impacts perceived levels of project risk, and the intensity of risk management processes. Our findings also suggest that risk management moderates the relationship between risk level and project success. Specifically, we found that even moderate levels of risk management planning are sufficient to reduce the negative effect risk levels have on project success.

Suggested Citation

  • Ofer Zwikael & Mark Ahn, 2011. "The Effectiveness of Risk Management: An Analysis of Project Risk Planning Across Industries and Countries," Risk Analysis, John Wiley & Sons, vol. 31(1), pages 25-37, January.
  • Handle: RePEc:wly:riskan:v:31:y:2011:i:1:p:25-37
    DOI: 10.1111/j.1539-6924.2010.01470.x
    as

    Download full text from publisher

    File URL: https://doi.org/10.1111/j.1539-6924.2010.01470.x
    Download Restriction: no

    File URL: https://libkey.io/10.1111/j.1539-6924.2010.01470.x?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Hausman, Jerry A. & Lo, Andrew W. & MacKinlay, A. Craig, 1992. "An ordered probit analysis of transaction stock prices," Journal of Financial Economics, Elsevier, vol. 31(3), pages 319-379, June.
    2. K. John Holmes & Judith A. Graham & Thomas McKone & Chris Whipple, 2009. "Regulatory Models and the Environment: Practice, Pitfalls, and Prospects," Risk Analysis, John Wiley & Sons, vol. 29(2), pages 159-170, February.
    3. Hainaut, Donatien & Devolder, Pierre, 2007. "Management of a pension fund under mortality and financial risks," Insurance: Mathematics and Economics, Elsevier, vol. 41(1), pages 134-155, July.
    4. Zeyuan Qiu & Tony Prato & Francis McCamley, 2001. "Evaluating Environmental Risks Using Safety-First Constraints," American Journal of Agricultural Economics, Agricultural and Applied Economics Association, vol. 83(2), pages 402-413.
    5. Elias, Arun Abraham, 2008. "Energy efficiency in New Zealand's residential sector: A systemic analysis," Energy Policy, Elsevier, vol. 36(9), pages 3278-3285, September.
    6. Pongsakdi, Arkadej & Rangsunvigit, Pramoch & Siemanond, Kitipat & Bagajewicz, Miguel J., 2006. "Financial risk management in the planning of refinery operations," International Journal of Production Economics, Elsevier, vol. 103(1), pages 64-86, September.
    7. Aaron J. Shenhar, 2001. "One Size Does Not Fit All Projects: Exploring Classical Contingency Domains," Management Science, INFORMS, vol. 47(3), pages 394-414, March.
    8. Seyed Mohammad Seyedhoseini & Siamak Noori & Mohammad Ali Hatefi, 2009. "An Integrated Methodology for Assessment and Selection of the Project Risk Response Actions," Risk Analysis, John Wiley & Sons, vol. 29(5), pages 752-763, May.
    9. Yacov Y. Haimes & Stan Kaplan & James H. Lambert, 2002. "Risk Filtering, Ranking, and Management Framework Using Hierarchical Holographic Modeling," Risk Analysis, John Wiley & Sons, vol. 22(2), pages 383-397, April.
    10. Arnd Huchzermeier & Christoph H. Loch, 2001. "Project Management Under Risk: Using the Real Options Approach to Evaluate Flexibility in R...D," Management Science, INFORMS, vol. 47(1), pages 85-101, January.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Hwee-Joo Kam & Thomas Mattson & Sanjay Goel, 0. "A Cross Industry Study of Institutional Pressures on Organizational Effort to Raise Information Security Awareness," Information Systems Frontiers, Springer, vol. 0, pages 1-24.
    2. Rocío Rodríguez-Rivero & Isabel Ortiz-Marcos & Javier Romero & Luis Ballesteros-Sánchez, 2020. "Finding the Links between Risk Management and Project Success: Evidence from International Development Projects in Colombia," Sustainability, MDPI, vol. 12(21), pages 1-19, November.
    3. John Malu Nzioki & Dr. Mary Nyawira Mwenda, 2021. "Enhancing Performance of the Building Construction Industry through Quantitative Risk Analysis and Risk Response: A Case of Exchequer Funded Building Construction Projects in Machakos County, Kenya," International Journal of Research and Innovation in Social Science, International Journal of Research and Innovation in Social Science (IJRISS), vol. 5(3), pages 31-39, March.
    4. Raffaele Testorelli & Anna Tiso & Chiara Verbano, 2024. "Value Creation with Project Risk Management: A Holistic Framework," Sustainability, MDPI, vol. 16(2), pages 1-20, January.
    5. Hwee-Joo Kam & Thomas Mattson & Sanjay Goel, 2020. "A Cross Industry Study of Institutional Pressures on Organizational Effort to Raise Information Security Awareness," Information Systems Frontiers, Springer, vol. 22(5), pages 1241-1264, October.
    6. Amin Khalifeh & Ahmad Samed Al-Adwan & Mohammed Kasem Alrousan & Husam Yaseen & Belal Mathani & Firas Rashed Wahsheh, 2023. "Exploring the Nexus of Sustainability and Project Success: A Proposed Framework for the Software Sector," Sustainability, MDPI, vol. 15(22), pages 1-18, November.
    7. Jesko Schulte & Sophie I. Hallstedt, 2018. "Company Risk Management in Light of the Sustainability Transition," Sustainability, MDPI, vol. 10(11), pages 1-25, November.
    8. Nicoleta Daniela IGNAT, 2019. "Risk Assessment Of Projects Co-Financed By The European Social Fund," Proceedings of the INTERNATIONAL MANAGEMENT CONFERENCE, Faculty of Management, Academy of Economic Studies, Bucharest, Romania, vol. 13(1), pages 833-844, November.
    9. Hadi Sarvari & Alireza Valipour & Nordin Yahya & Norhazilan MD Noor & Michael Beer & Nerija Banaitiene, 2019. "Approaches to Risk Identification in Public–Private Partnership Projects: Malaysian Private Partners’ Overview," Administrative Sciences, MDPI, vol. 9(1), pages 1-18, February.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Hazır, Öncü & Ulusoy, Gündüz, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," International Journal of Production Economics, Elsevier, vol. 223(C).
    2. Öncü Hazir & Gündüz Ulusoy, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," Post-Print hal-02898162, HAL.
    3. Hong, Harrison & Rady, Sven, 2002. "Strategic trading and learning about liquidity," Journal of Financial Markets, Elsevier, vol. 5(4), pages 419-450, October.
    4. Richard K. Lyons, 1996. "Foreign Exchange Volume: Sound and Fury Signifying Nothing?," NBER Chapters, in: The Microstructure of Foreign Exchange Markets, pages 183-208, National Bureau of Economic Research, Inc.
    5. Gerhard, Frank & Hess, Dieter & Pohlmeier, Winfried, 1998. "What a Difference a Day Makes: On the Common Market Microstructure of Trading Days," CoFE Discussion Papers 98/01, University of Konstanz, Center of Finance and Econometrics (CoFE).
    6. Hong‐Chih Huang, 2010. "Optimal Multiperiod Asset Allocation: Matching Assets to Liabilities in a Discrete Model," Journal of Risk & Insurance, The American Risk and Insurance Association, vol. 77(2), pages 451-472, June.
    7. Hasbrouck, Joel, 1996. "Order characteristics and stock price evolution An application to program trading," Journal of Financial Economics, Elsevier, vol. 41(1), pages 129-149, May.
    8. Xiaoyan Jiang & Sai Wang & Jie Wang & Sainan Lyu & Martin Skitmore, 2020. "A Decision Method for Construction Safety Risk Management Based on Ontology and Improved CBR: Example of a Subway Project," IJERPH, MDPI, vol. 17(11), pages 1-23, June.
    9. Azhar Iqbal & John Silvia, 2016. "Is Predicting Recessions Enough?," Business Economics, Palgrave Macmillan;National Association for Business Economics, vol. 51(4), pages 248-259, October.
    10. Bernhardt, Dan & Hughson, Eric, 2002. "Intraday trade in dealership markets," European Economic Review, Elsevier, vol. 46(9), pages 1697-1732, October.
    11. Dimitrakopoulos, Stefanos & Tsionas, Mike, 2019. "Ordinal-response GARCH models for transaction data: A forecasting exercise," International Journal of Forecasting, Elsevier, vol. 35(4), pages 1273-1287.
    12. Huang, Roger D. & Ting, Christopher, 2008. "A functional approach to the price impact of stock trades and the implied true price," Journal of Empirical Finance, Elsevier, vol. 15(1), pages 1-16, January.
    13. Avner Engel & Shalom Shachar, 2006. "Measuring and optimizing systems' quality costs and project duration," Systems Engineering, John Wiley & Sons, vol. 9(3), pages 259-280, September.
    14. Branstetter, Lee & Chatterjee, Chirantan & Higgins, Matthew J., 2022. "Generic competition and the incentives for early-stage pharmaceutical innovation," Research Policy, Elsevier, vol. 51(10).
    15. Alexander, Gordon J. & Peterson, Mark A., 2007. "An analysis of trade-size clustering and its relation to stealth trading," Journal of Financial Economics, Elsevier, vol. 84(2), pages 435-471, May.
    16. Dengsheng Wu & Xiaoqian Zhu & Jie Wan & Chunbing Bao & Jianping Li, 2019. "A Multiobjective Optimization Approach for Selecting Risk Response Strategies of Software Project: From the Perspective of Risk Correlations," International Journal of Information Technology & Decision Making (IJITDM), World Scientific Publishing Co. Pte. Ltd., vol. 18(01), pages 339-364, January.
    17. Mahsa Parsaei Motamed & Shahrooz Bamdad, 2022. "A multi-objective optimization approach for selecting risk response actions: considering environmental and secondary risks," OPSEARCH, Springer;Operational Research Society of India, vol. 59(1), pages 266-303, March.
    18. Ping Yung, 2015. "A new institutional economic theory of project management," Journal of Business Economics and Management, Taylor & Francis Journals, vol. 16(1), pages 228-243, February.
    19. Sinyagin, Yury (Синягин, Юрий) & Sheburakov, I.B. (Шебураков, И.Б.), 2017. "Mechanisms and Tools for the Formation of Effective Project Teams in the Executive Authorities of the Subjects of the Russian Federation [Механизмы И Инструменты Формирования Эффективных Проектных ," Working Papers 061704, Russian Presidential Academy of National Economy and Public Administration.
    20. Yang Lu, 2020. "A simple parameter‐driven binary time series model," Journal of Forecasting, John Wiley & Sons, Ltd., vol. 39(2), pages 187-199, March.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:wly:riskan:v:31:y:2011:i:1:p:25-37. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Wiley Content Delivery (email available below). General contact details of provider: https://doi.org/10.1111/(ISSN)1539-6924 .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.