IDEAS home Printed from https://ideas.repec.org/a/spr/orspec/v38y2016i2d10.1007_s00291-015-0419-6.html
   My bibliography  Save this article

On the efficient modeling and solution of the multi-mode resource-constrained project scheduling problem with generalized precedence relations

Author

Listed:
  • Alexander Schnell

    (University of Vienna)

  • Richard F. Hartl

    (University of Vienna)

Abstract

For variants of the single-mode resource-constrained project scheduling problem, state-of-the-art exact algorithms combine a Branch and Bound algorithm with principles from Constraint Programming and Boolean Satisfiability Solving. In our paper, we propose new exact approaches extending the above principles to the multi-mode RCPSP (MRCPSP) with generalized precedence relations (GPRs). More precisely, we implemented two constraint handlers cumulativemm and gprecedencemm for the optimization framework SCIP. With the latter, one can model renewable resource constraints and GPRs in the context of multi-mode activities, respectively. Moreover, they integrate domain propagation and explanation generation techniques for the above problem characteristics. We formulate three SCIP-models for the MRCPSP with GPRs, two without and one with our constraint handler gprecedencemm. Our computational results on instances from the literature with 30, 50 and 100 activities show that the addition of this constraint handler significantly strengthens the SCIP-model. Moreover, we outperform the state-of-the-art exact approach on instances with 50 activities when imposing time limits of 27 s. In addition, we close (find the optimal solution and prove its optimality for) 289 open instances and improve the best known makespan for 271 instances from the literature.

Suggested Citation

  • Alexander Schnell & Richard F. Hartl, 2016. "On the efficient modeling and solution of the multi-mode resource-constrained project scheduling problem with generalized precedence relations," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 38(2), pages 283-303, March.
  • Handle: RePEc:spr:orspec:v:38:y:2016:i:2:d:10.1007_s00291-015-0419-6
    DOI: 10.1007/s00291-015-0419-6
    as

    Download full text from publisher

    File URL: http://link.springer.com/10.1007/s00291-015-0419-6
    File Function: Abstract
    Download Restriction: Access to the full text of the articles in this series is restricted.

    File URL: https://libkey.io/10.1007/s00291-015-0419-6?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Andrei Horbach, 2010. "A Boolean satisfiability approach to the resource-constrained project scheduling problem," Annals of Operations Research, Springer, vol. 181(1), pages 89-107, December.
    2. Brucker, Peter & Knust, Sigrid, 2003. "Lower bounds for resource-constrained project scheduling problems," European Journal of Operational Research, Elsevier, vol. 149(2), pages 302-313, September.
    3. Heilmann, Roland, 2003. "A branch-and-bound procedure for the multi-mode resource-constrained project scheduling problem with minimum and maximum time lags," European Journal of Operational Research, Elsevier, vol. 144(2), pages 348-365, January.
    4. De Reyck, Bert & Herroelen, Willy, 1999. "The multi-mode resource-constrained project scheduling problem with generalized precedence relations," European Journal of Operational Research, Elsevier, vol. 119(2), pages 538-556, December.
    5. Guidong Zhu & Jonathan F. Bard & Gang Yu, 2006. "A Branch-and-Cut Procedure for the Multimode Resource-Constrained Project-Scheduling Problem," INFORMS Journal on Computing, INFORMS, vol. 18(3), pages 377-390, August.
    6. Rainer Kolisch & Arno Sprecher & Andreas Drexl, 1995. "Characterization and Generation of a General Class of Resource-Constrained Project Scheduling Problems," Management Science, INFORMS, vol. 41(10), pages 1693-1703, October.
    7. Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
    8. Matteo Fischetti & Michele Monaci, 2014. "Exploiting Erraticism in Search," Operations Research, INFORMS, vol. 62(1), pages 114-122, February.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Hartmann, Sönke & Briskorn, Dirk, 2022. "An updated survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 297(1), pages 1-14.
    2. Rainer Kolisch & Erik Demeulemeester & Rubén Ruiz Garcia & Vincent T’Kindt & Jan Węglarz, 2016. "Editorial “Project Management and Scheduling”," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 38(2), pages 279-281, March.
    3. Abdollah Arasteh, 2020. "Considering Project Management Activities for Engineering Design Groups," SN Operations Research Forum, Springer, vol. 1(4), pages 1-29, December.
    4. Farnaz Torabi Yeganeh & Seyed Hessameddin Zegordi, 2020. "A multi-objective optimization approach to project scheduling with resiliency criteria under uncertain activity duration," Annals of Operations Research, Springer, vol. 285(1), pages 161-196, February.
    5. Felix Hübner & Patrick Gerhards & Christian Stürck & Rebekka Volk, 2021. "Solving the nuclear dismantling project scheduling problem by combining mixed-integer and constraint programming techniques and metaheuristics," Journal of Scheduling, Springer, vol. 24(3), pages 269-290, June.
    6. Servranckx, Tom & Coelho, José & Vanhoucke, Mario, 2024. "A genetic algorithm for the Resource-Constrained Project Scheduling Problem with Alternative Subgraphs using a boolean satisfiability solver," European Journal of Operational Research, Elsevier, vol. 316(3), pages 815-827.
    7. Patrick Gerhards, 2020. "The multi-mode resource investment problem: a benchmark library and a computational study of lower and upper bounds," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 42(4), pages 901-933, December.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
    2. Hartmann, Sönke & Briskorn, Dirk, 2008. "A survey of variants and extensions of the resource-constrained project scheduling problem," Working Paper Series 02/2008, Hamburg School of Business Administration (HSBA).
    3. Alessandro Hill & Eduardo Lalla-Ruiz & Stefan Voß & Marcos Goycoolea, 2019. "A multi-mode resource-constrained project scheduling reformulation for the waterway ship scheduling problem," Journal of Scheduling, Springer, vol. 22(2), pages 173-182, April.
    4. Weglarz, Jan & Józefowska, Joanna & Mika, Marek & Waligóra, Grzegorz, 2011. "Project scheduling with finite or infinite number of activity processing modes - A survey," European Journal of Operational Research, Elsevier, vol. 208(3), pages 177-205, February.
    5. Chen, Jiaqiong & Askin, Ronald G., 2009. "Project selection, scheduling and resource allocation with time dependent returns," European Journal of Operational Research, Elsevier, vol. 193(1), pages 23-34, February.
    6. Dayal Madhukar & Verma, Sanjay, 2014. "Breadth-first and Best-first Exact Procedures for Regular Measures of the Multi-mode RCPSP," IIMA Working Papers WP2014-10-04, Indian Institute of Management Ahmedabad, Research and Publication Department.
    7. Dayal Madhukar & Verma, Sanjay, 2015. "Multi-processor Exact Procedures for Regular Measures of the Multi-mode RCPSP," IIMA Working Papers WP2015-03-25, Indian Institute of Management Ahmedabad, Research and Publication Department.
    8. Alexander Tesch, 2020. "A polyhedral study of event-based models for the resource-constrained project scheduling problem," Journal of Scheduling, Springer, vol. 23(2), pages 233-251, April.
    9. Maryam Sadeghloo & Saeed Emami & Ali Divsalar, 2024. "A Benders decomposition algorithm for the multi-mode resource-constrained multi-project scheduling problem with uncertainty," Annals of Operations Research, Springer, vol. 339(3), pages 1637-1677, August.
    10. Abdollah Arasteh, 2020. "Considering Project Management Activities for Engineering Design Groups," SN Operations Research Forum, Springer, vol. 1(4), pages 1-29, December.
    11. Wendi Tian & Erik Demeulemeester, 2014. "Railway scheduling reduces the expected project makespan over roadrunner scheduling in a multi-mode project scheduling environment," Annals of Operations Research, Springer, vol. 213(1), pages 271-291, February.
    12. Ripon K. Chakrabortty & Ruhul A. Sarker & Daryl L. Essam, 2020. "Single mode resource constrained project scheduling with unreliable resources," Operational Research, Springer, vol. 20(3), pages 1369-1403, September.
    13. Alireza Etminaniesfahani & Hanyu Gu & Leila Moslemi Naeni & Amir Salehipour, 2024. "An efficient relax-and-solve method for the multi-mode resource constrained project scheduling problem," Annals of Operations Research, Springer, vol. 338(1), pages 41-68, July.
    14. Cédric Verbeeck & Vincent Peteghem & Mario Vanhoucke & Pieter Vansteenwegen & El-Houssaine Aghezzaf, 2017. "A metaheuristic solution approach for the time-constrained project scheduling problem," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 39(2), pages 353-371, March.
    15. Naber, Anulark & Kolisch, Rainer, 2014. "MIP models for resource-constrained project scheduling with flexible resource profiles," European Journal of Operational Research, Elsevier, vol. 239(2), pages 335-348.
    16. Van Peteghem, Vincent & Vanhoucke, Mario, 2014. "An experimental investigation of metaheuristics for the multi-mode resource-constrained project scheduling problem on new dataset instances," European Journal of Operational Research, Elsevier, vol. 235(1), pages 62-72.
    17. Hermel, Dror & Hasheminia, Hamed & Adler, Nicole & Fry, Michael J., 2016. "A solution framework for the multi-mode resource-constrained cross-dock scheduling problem," Omega, Elsevier, vol. 59(PB), pages 157-170.
    18. Gonzalo Muñoz & Daniel Espinoza & Marcos Goycoolea & Eduardo Moreno & Maurice Queyranne & Orlando Rivera Letelier, 2018. "A study of the Bienstock–Zuckerberg algorithm: applications in mining and resource constrained project scheduling," Computational Optimization and Applications, Springer, vol. 69(2), pages 501-534, March.
    19. Mick Van Den Eeckhout & Broos Maenhout & Mario Vanhoucke, 2020. "Mode generation rules to define activity flexibility for the integrated project staffing problem with discrete time/resource trade-offs," Annals of Operations Research, Springer, vol. 292(1), pages 133-160, September.
    20. Alfredo S. Ramos & Pablo A. Miranda-Gonzalez & Samuel Nucamendi-Guillén & Elias Olivares-Benitez, 2023. "A Formulation for the Stochastic Multi-Mode Resource-Constrained Project Scheduling Problem Solved with a Multi-Start Iterated Local Search Metaheuristic," Mathematics, MDPI, vol. 11(2), pages 1-25, January.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:spr:orspec:v:38:y:2016:i:2:d:10.1007_s00291-015-0419-6. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Sonal Shukla or Springer Nature Abstracting and Indexing (email available below). General contact details of provider: http://www.springer.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.