Causes of delays in construction projects in the Province of Aceh, Indonesia

Author

Listed:
  • Anita Rauzana
  • Wira Dharma

Abstract

Implementations of construction projects in Indonesia, especially in Aceh Province, are often delayed. Time, quality, and cost are three important components of planning a construction project. The benchmark for a successful construction project is the project completion time being in accordance with the time period specified in the contract. In project implementation, there is often a risk of delays in completing construction projects that can cause losses and fines; therefore, it is necessary to know the risk factors potentially causing project delays. The purpose of this study was to identify the risk factors causing delays greatly affecting construction projects in Aceh Province. The data used in this study were questionnaire data distributed to 68 respondents. The data processing methods included validity tests, reliability tests, and the construction of descriptive statistics. Ultimately, 60 delay factors were obtained; of these, 30 risk indicators were included in the very influential category with a mode value of (= 5), 29 delay risk indicators were in the high influence category with a mode value of (= 4), and one indicator was included in the category of medium influence (= 3).

Suggested Citation

  • Anita Rauzana & Wira Dharma, 2022. "Causes of delays in construction projects in the Province of Aceh, Indonesia," PLOS ONE, Public Library of Science, vol. 17(1), pages 1-12, January.
  • Handle: RePEc:plo:pone00:0263337
    DOI: 10.1371/journal.pone.0263337
    as

    Download full text from publisher

    File URL: https://journals.plos.org/plosone/article?id=10.1371/journal.pone.0263337
    Download Restriction: no

    File URL: https://journals.plos.org/plosone/article/file?id=10.1371/journal.pone.0263337&type=printable
    Download Restriction: no

    File URL: https://libkey.io/10.1371/journal.pone.0263337?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Shamas-Ur-Rehman Toor & Stephen Ogunlana, 2008. "Problems causing delays in major construction projects in Thailand," Construction Management and Economics, Taylor & Francis Journals, vol. 26(4), pages 395-408.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2018. "Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project," Sustainability, MDPI, vol. 10(12), pages 1-18, December.
    2. Ajayi Babatunde Oluwaseun & Chinda Thanwadee, 2022. "Dynamics of Pertinent Project Delay Variables in the Thai Construction Sector: Mathematical Analysis," Engineering Management in Production and Services, Sciendo, vol. 14(2), pages 26-45, June.
    3. Goutom K. Pall & Adrian J. Bridge & Jason Gray & Martin Skitmore, 2019. "Causes of Delay in Power Transmission Projects: An Empirical Study," Energies, MDPI, vol. 13(1), pages 1-29, December.
    4. Alessandra Montenegro & Marina Dobrota & Marija Todorovic & Teodora Slavinski & Vladimir Obradovic, 2021. "Impact of Construction Project Managers’ Emotional Intelligence on Project Success," Sustainability, MDPI, vol. 13(19), pages 1-18, September.
    5. Iyer K. Chandrashekhar & Banerjee Partha S., 2016. "Project ambidexterity: case of recovering schedule delay in a brownfield airport project in India," Organization, Technology and Management in Construction, Sciendo, vol. 8(1), pages 1464-1481, December.
    6. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2020. "Delay Factors Management and Ranking for Reconstruction and Rehabilitation Projects Based on the Relative Importance Index (RII)," Sustainability, MDPI, vol. 12(15), pages 1-21, July.
    7. Dang Vo, Khoa & Thanh Nguyen, Phong & Le Hoang Thuy To Nguyen, Quyen, 2020. "Disputes in Managing Projects: A Case Study of Construction Industry in Vietnam," MPRA Paper 103436, University Library of Munich, Germany, revised 05 Jul 2020.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:plo:pone00:0263337. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: plosone (email available below). General contact details of provider: https://journals.plos.org/plosone/ .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.