Letter to the Editor---The PERT Model for the Distribution of an Activity Time

Author

Listed:
  • Charles E. Clark

    (System Development Corporation, Santa Monica, California)

Abstract

An earlier paper describes the PERT analysis of a network of activities (Malcolm, D. G., J. H. Roseboom, C. E. Clark, W. Fazar. 1959. Application of a technique for research and development program evaluation. Opns Res. 7 646--669.), its analytic details, not written by a mathematician, are confusing to many analysts who continually request elucidation. This note is intended to answer the question most frequently asked, namely, whence the statements in that paper concerning the distribution of an activity time?

Suggested Citation

  • Charles E. Clark, 1962. "Letter to the Editor---The PERT Model for the Distribution of an Activity Time," Operations Research, INFORMS, vol. 10(3), pages 405-406, June.
  • Handle: RePEc:inm:oropre:v:10:y:1962:i:3:p:405-406
    DOI: 10.1287/opre.10.3.405
    as

    Download full text from publisher

    File URL: http://dx.doi.org/10.1287/opre.10.3.405
    Download Restriction: no

    File URL: https://libkey.io/10.1287/opre.10.3.405?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Sergei Sabanov & Abdullah Rasheed Qureshi & Zhaudir Dauitbay & Gulim Kurmangazy, 2023. "A Method for the Modified Estimation of Oil Shale Mineable Reserves for Shale Oil Projects: A Case Study," Energies, MDPI, vol. 16(16), pages 1-17, August.
    2. Moayyad Al-Fawaeer & Abdul Sattar Al-Ali & Mousa Khaireddin, 2021. "The Impact of Changing the Expected Time and Variance Equations of the Project Activities on The Completion Time and Cost of the Project in PERT Model," International Journal of Business and Economics, School of Management Development, Feng Chia University, Taichung, Taiwan, vol. 20(2), pages 119-140, September.
    3. Moayyad Al-Fawaeer & Abdul Sattar Al-Ali & Mousa Khaireddin, 2021. "The Impact of Changing the Expected Time and Variance Equations of the Project Activities on The Completion Time and Cost of the Project in PERT Model," International Journal of Business and Economics, School of Management Development, Feng Chia University, Taichung, Taiwan, vol. 20(2), pages 1-22, September.
    4. Lucas Coffman & Clayton R. Featherstone & Judd B. Kessler, 2024. "A Model of Information Nudges," Boston College Working Papers in Economics 1077, Boston College Department of Economics.
    5. Opabola, Eyitayo A. & Galasso, Carmine, 2024. "A probabilistic framework for post-disaster recovery modeling of buildings and electric power networks in developing countries," Reliability Engineering and System Safety, Elsevier, vol. 242(C).
    6. Hajdu M. & Isaac S., 2016. "Sixty years of project planning: history and future," Organization, Technology and Management in Construction, Sciendo, vol. 8(1), pages 1499-1510, December.
    7. Nicholas G. Hall & Marc E. Posner, 2001. "Generating Experimental Data for Computational Testing with Machine Scheduling Applications," Operations Research, INFORMS, vol. 49(6), pages 854-865, December.
    8. Zhen Song & Håkan Schunnesson & Mikael Rinne & John Sturgul, 2015. "An Approach to Realizing Process Control for Underground Mining Operations of Mobile Machines," PLOS ONE, Public Library of Science, vol. 10(6), pages 1-17, June.
    9. Anna Antonova & Konstantin Aksyonov & Olga Aksyonova, 2021. "An Imitation and Heuristic Method for Scheduling with Subcontracted Resources," Mathematics, MDPI, vol. 9(17), pages 1-22, August.
    10. Samadi, S. Yaser & Billard, Lynne, 2021. "Analysis of dependent data aggregated into intervals," Journal of Multivariate Analysis, Elsevier, vol. 186(C).
    11. Yousry Abdelkader, 2010. "Adjustment of the moments of the project completion times when activity times are exponentially distributed," Annals of Operations Research, Springer, vol. 181(1), pages 503-514, December.
    12. Catalina García & José Pérez & Salvador Rambaud, 2010. "Proposal of a new distribution in PERT methodology," Annals of Operations Research, Springer, vol. 181(1), pages 515-538, December.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:inm:oropre:v:10:y:1962:i:3:p:405-406. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Asher (email available below). General contact details of provider: https://edirc.repec.org/data/inforea.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.