Improving Manufacturing Supply Chain by Integrating SMED and Production Scheduling

Author

Listed:
  • Viren Parwani

    (Industrial and Manufacturing Systems Engineering (IMSE), Iowa State University, Ames, IA 50011, USA)

  • Guiping Hu

    (Industrial and Manufacturing Systems Engineering (IMSE), Iowa State University, Ames, IA 50011, USA)

Abstract

Globalization has led to a significant effect on today’s manufacturing sector. Manufacturers need to find new and innovative ways to increase efficiency and reduce waste in the manufacturing supply chain. Lean/six sigma tools can help companies increase production efficiency and stay in competition. Manufacturing in smaller batches can keep the supply chain lean and customizable. This leads to frequent changeovers and downtime. A changeover is usually required when a single machine produces different products based on the requirement. A large-scale industry can either install multiple individual production lines to cater to the demand (usually expensive) or make frequent machinery changes. Single Minute Exchange Die (SMED) is a system designed for reducing the changeover time for machines. It reduces the time taken to complete the activities and eliminates non-essential activities throughout the changeover. Scheduling an operating procedure within SMED in such case is a challenge. Project scheduling model with workforce constraints can be used to create a set of heuristics to provide us with an optimized list of tasks. The paper proposes to design a scheduling heuristic model to allocate tasks to the operators to get the least amount of operator idle time and reduce changeover downtime costs. The paper further illustrates the benefit of the model in a case study and proposes its integration within the existing SMED methodology. This results in a benefit-to-cost ratio of 7.5% for production scheduling compared to that of stages 4 and 5 in SMED, which is 1.2%.

Suggested Citation

  • Viren Parwani & Guiping Hu, 2021. "Improving Manufacturing Supply Chain by Integrating SMED and Production Scheduling," Logistics, MDPI, vol. 5(1), pages 1-14, January.
  • Handle: RePEc:gam:jlogis:v:5:y:2021:i:1:p:4-:d:478803
    as

    Download full text from publisher

    File URL: https://www.mdpi.com/2305-6290/5/1/4/pdf
    Download Restriction: no

    File URL: https://www.mdpi.com/2305-6290/5/1/4/
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Bikram Jit Singh, 2009. "SMED: for quick changeovers in foundry SMEs," International Journal of Productivity and Performance Management, Emerald Group Publishing, vol. 59(1), pages 98-116, December.
    2. Ruiz, Rubén & Vázquez-Rodríguez, José Antonio, 2010. "The hybrid flow shop scheduling problem," European Journal of Operational Research, Elsevier, vol. 205(1), pages 1-18, August.
    3. José Roberto Díaz-Reza & Jorge Luis García-Alcaraz & Valeria Martínez-Loya & Julio Blanco-Fernández & Emilio Jiménez-Macías & Liliana Avelar-Sosa, 2016. "The Effect of SMED on Benefits Gained in Maquiladora Industry," Sustainability, MDPI, vol. 8(12), pages 1-18, November.
    4. A Bachman & A Janiak, 2004. "Scheduling jobs with position-dependent processing times," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 55(3), pages 257-264, March.
    5. Huang, Rong-Hwa, 2010. "Multi-objective job-shop scheduling with lot-splitting production," International Journal of Production Economics, Elsevier, vol. 124(1), pages 206-213, March.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Patricia Inês Schwantz & Leander Luiz Klein & Eugênio de Oliveira Simonetto, 2023. "The Relationship between Lean Practices and Organizational Performance: An Analysis of Operations Management in a Public Institution," Logistics, MDPI, vol. 7(3), pages 1-14, August.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Zhe Zhang & Xiaoling Song & Huijun Huang & Yong Yin & Benjamin Lev, 2022. "Scheduling problem in seru production system considering DeJong’s learning effect and job splitting," Annals of Operations Research, Springer, vol. 312(2), pages 1119-1141, May.
    2. Bozorgirad, Mir Abbas & Logendran, Rasaratnam, 2013. "Bi-criteria group scheduling in hybrid flowshops," International Journal of Production Economics, Elsevier, vol. 145(2), pages 599-612.
    3. Weiya Zhong & Yun Shi, 2018. "Two-stage no-wait hybrid flowshop scheduling with inter-stage flexibility," Journal of Combinatorial Optimization, Springer, vol. 35(1), pages 108-125, January.
    4. Pan, Quan-Ke & Gao, Liang & Li, Xin-Yu & Gao, Kai-Zhou, 2017. "Effective metaheuristics for scheduling a hybrid flowshop with sequence-dependent setup times," Applied Mathematics and Computation, Elsevier, vol. 303(C), pages 89-112.
    5. A. G. Leeftink & R. J. Boucherie & E. W. Hans & M. A. M. Verdaasdonk & I. M. H. Vliegen & P. J. Diest, 2018. "Batch scheduling in the histopathology laboratory," Flexible Services and Manufacturing Journal, Springer, vol. 30(1), pages 171-197, June.
    6. Jin Xu & Natarajan Gautam, 2020. "On competitive analysis for polling systems," Naval Research Logistics (NRL), John Wiley & Sons, vol. 67(6), pages 404-419, September.
    7. Alexis Robbes & Yannick Kergosien & Virginie André & Jean-Charles Billaut, 2022. "Efficient heuristics to minimize the total tardiness of chemotherapy drug production and delivery," Flexible Services and Manufacturing Journal, Springer, vol. 34(3), pages 785-820, September.
    8. Fátima Pilar & Eliana Costa e Silva & Ana Borges, 2023. "Optimizing Vehicle Repairs Scheduling Using Mixed Integer Linear Programming: A Case Study in the Portuguese Automobile Sector," Mathematics, MDPI, vol. 11(11), pages 1-23, June.
    9. Peng Liu & Xiaoli Wang, 2017. "Maximum Lateness Scheduling on Two-Person Cooperative Games with Variable Processing Times and Common Due Date," Journal of Optimization, Hindawi, vol. 2017, pages 1-7, April.
    10. Nicolás Álvarez-Gil & Rafael Rosillo & David de la Fuente & Raúl Pino, 2021. "A discrete firefly algorithm for solving the flexible job-shop scheduling problem in a make-to-order manufacturing system," Central European Journal of Operations Research, Springer;Slovak Society for Operations Research;Hungarian Operational Research Society;Czech Society for Operations Research;Österr. Gesellschaft für Operations Research (ÖGOR);Slovenian Society Informatika - Section for Operational Research;Croatian Operational Research Society, vol. 29(4), pages 1353-1374, December.
    11. Billaut, Jean-Charles & Della Croce, Federico & Grosso, Andrea, 2015. "A single machine scheduling problem with two-dimensional vector packing constraints," European Journal of Operational Research, Elsevier, vol. 243(1), pages 75-81.
    12. Zhang, Rui & Song, Shiji & Wu, Cheng, 2013. "A hybrid artificial bee colony algorithm for the job shop scheduling problem," International Journal of Production Economics, Elsevier, vol. 141(1), pages 167-178.
    13. Weiwei Wang & Biao Zhang & Baoxian Jia, 2023. "A Multiobjective Optimization Approach for Multiobjective Hybrid Flowshop Green Scheduling with Consistent Sublots," Sustainability, MDPI, vol. 15(3), pages 1-29, February.
    14. Ji-Bo Wang & Ming-Zheng Wang, 2011. "Worst-case behavior of simple sequencing rules in flow shop scheduling with general position-dependent learning effects," Annals of Operations Research, Springer, vol. 191(1), pages 155-169, November.
    15. Li, Gang & Wang, Xiao-Yuan & Wang, Ji-Bo & Sun, Lin-Yan, 2013. "Worst case analysis of flow shop scheduling problems with a time-dependent learning effect," International Journal of Production Economics, Elsevier, vol. 142(1), pages 98-104.
    16. Vinod, V. & Sridharan, R., 2011. "Simulation modeling and analysis of due-date assignment methods and scheduling decision rules in a dynamic job shop production system," International Journal of Production Economics, Elsevier, vol. 129(1), pages 127-146, January.
    17. Alfaro-Fernández, Pedro & Ruiz, Rubén & Pagnozzi, Federico & Stützle, Thomas, 2020. "Automatic Algorithm Design for Hybrid Flowshop Scheduling Problems," European Journal of Operational Research, Elsevier, vol. 282(3), pages 835-845.
    18. Jun Pei & Jinling Wei & Baoyu Liao & Xinbao Liu & Panos M. Pardalos, 2020. "Two-agent scheduling on bounded parallel-batching machines with an aging effect of job-position-dependent," Annals of Operations Research, Springer, vol. 294(1), pages 191-223, November.
    19. S. M. Mousavi & I. Mahdavi & J. Rezaeian & M. Zandieh, 2018. "An efficient bi-objective algorithm to solve re-entrant hybrid flow shop scheduling with learning effect and setup times," Operational Research, Springer, vol. 18(1), pages 123-158, April.
    20. An, Xiangxin & Si, Guojin & Xia, Tangbin & Wang, Dong & Pan, Ershun & Xi, Lifeng, 2023. "An energy-efficient collaborative strategy of maintenance planning and production scheduling for serial-parallel systems under time-of-use tariffs," Applied Energy, Elsevier, vol. 336(C).

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jlogis:v:5:y:2021:i:1:p:4-:d:478803. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.