IDEAS home Printed from https://ideas.repec.org/a/eee/proeco/v124y2010i2p482-488.html
   My bibliography  Save this article

The economic lot-sizing problem with remanufacturing and one-way substitution

Author

Listed:
  • Piñeyro, Pedro
  • Viera, Omar

Abstract

We investigate a lot-sizing problem with different demand streams for new and remanufactured items, in which the demand for remanufactured items can be also satisfied by new products, but not vice versa. We provide a mathematical model for the problem and demonstrate it is NP-hard, even under particular cost structures. We also show the key role that remanufacturing plays in the problem resolution. With the aim of finding a near optimal solution of the problem, we develop and evaluate a Tabu-Search-based procedure. The numerical experiment carried out confirms the success of the procedure for different cases.

Suggested Citation

  • Piñeyro, Pedro & Viera, Omar, 2010. "The economic lot-sizing problem with remanufacturing and one-way substitution," International Journal of Production Economics, Elsevier, vol. 124(2), pages 482-488, April.
  • Handle: RePEc:eee:proeco:v:124:y:2010:i:2:p:482-488
    as

    Download full text from publisher

    File URL: http://www.sciencedirect.com/science/article/pii/S0925-5273(10)00017-4
    Download Restriction: Full text for ScienceDirect subscribers only
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Richter, Knut & Weber, Jens, 2001. "The reverse Wagner/Whitin model with variable manufacturing and remanufacturing cost," International Journal of Production Economics, Elsevier, vol. 71(1-3), pages 447-456, May.
    2. Inderfurth, Karl, 2004. "Optimal policies in hybrid manufacturing/remanufacturing systems with product substitution," International Journal of Production Economics, Elsevier, vol. 90(3), pages 325-343, August.
    3. Fleischmann, M., 2001. "Reverse Logistics Network Structures and Design," ERIM Report Series Research in Management ERS-2001-52-LIS, Erasmus Research Institute of Management (ERIM), ERIM is the joint research institute of the Rotterdam School of Management, Erasmus University and the Erasmus School of Economics (ESE) at Erasmus University Rotterdam.
    4. Willard I. Zangwill, 1968. "Minimum Concave Cost Flows in Certain Networks," Management Science, INFORMS, vol. 14(7), pages 429-450, March.
    5. Teunter, R.H. & Bayindir, Z.P. & van den Heuvel, W., 2005. "Dynamic lot sizing with product returns," Econometric Institute Research Papers EI 2005-17, Erasmus University Rotterdam, Erasmus School of Economics (ESE), Econometric Institute.
    6. Harvey M. Wagner & Thomson M. Whitin, 1958. "Dynamic Version of the Economic Lot Size Model," Management Science, INFORMS, vol. 5(1), pages 89-96, October.
    7. Konstantaras, I. & Papachristos, S., 2007. "Optimal policy and holding cost stability regions in a periodic review inventory system with manufacturing and remanufacturing options," European Journal of Operational Research, Elsevier, vol. 178(2), pages 433-448, April.
    8. Ayres, Robert & Ferrer, Geraldo & Van Leynseele, Tania, 1997. "Eco-efficiency, asset recovery and remanufacturing," European Management Journal, Elsevier, vol. 15(5), pages 557-574, October.
    9. Fred Glover, 1990. "Tabu Search: A Tutorial," Interfaces, INFORMS, vol. 20(4), pages 74-94, August.
    10. van den Heuvel, W., 2004. "On the complexity of the economic lot-sizing problem with remanufacturing options," Econometric Institute Research Papers EI 2004-46, Erasmus University Rotterdam, Erasmus School of Economics (ESE), Econometric Institute.
    11. Z P Bayındır & N Erkip & R Güllü, 2005. "Assessing the benefits of remanufacturing option under one-way substitution," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 56(3), pages 286-296, March.
    12. Richter, Knut & Sombrutzki, Mirko, 2000. "Remanufacturing planning for the reverse Wagner/Whitin models," European Journal of Operational Research, Elsevier, vol. 121(2), pages 304-315, March.
    13. Awi Federgruen & Michal Tzur, 1991. "A Simple Forward Algorithm to Solve General Dynamic Lot Sizing Models with n Periods in 0(n log n) or 0(n) Time," Management Science, INFORMS, vol. 37(8), pages 909-925, August.
    14. Alok Aggarwal & James K. Park, 1993. "Improved Algorithms for Economic Lot Size Problems," Operations Research, INFORMS, vol. 41(3), pages 549-571, June.
    15. Pan, Zhendong & Tang, Jiafu & Liu, Ou, 2009. "Capacitated dynamic lot sizing problems in closed-loop supply chain," European Journal of Operational Research, Elsevier, vol. 198(3), pages 810-821, November.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Suliman, Saad M.A. & Jawad, Sayed Husain, 2012. "Optimization of preventive maintenance schedule and production lot size," International Journal of Production Economics, Elsevier, vol. 137(1), pages 19-28.
    2. Syed Ali, Sharifah Aishah & Doostmohammadi, Mahdi & Akartunalı, Kerem & van der Meer, Robert, 2018. "A theoretical and computational analysis of lot-sizing in remanufacturing with separate setups," International Journal of Production Economics, Elsevier, vol. 203(C), pages 276-285.
    3. Lin, Yizhong & Leung, Janny M.Y. & Zhang, Lianmin & Gu, Jia-Wen, 2020. "Single-item repairable inventory system with stochastic new and warranty demands," Transportation Research Part E: Logistics and Transportation Review, Elsevier, vol. 142(C).
    4. Zhang, Zhi-Hai & Jiang, Hai & Pan, Xunzhang, 2012. "A Lagrangian relaxation based approach for the capacitated lot sizing problem in closed-loop supply chain," International Journal of Production Economics, Elsevier, vol. 140(1), pages 249-255.
    5. Dhahri, Akrem & Gharbi, Ali & Ouhimmou, Mustapha, 2022. "Integrated production-delivery control policy for an unreliable manufacturing system and multiple retailers," International Journal of Production Economics, Elsevier, vol. 245(C).
    6. Ahmed Senoussi & Youcef Boutarfa & Nadjib Brahimi & Tarik Aouam, 2024. "Sustainable Hybrid Manufacturing and Refurbishing Systems with Substitution," Sustainability, MDPI, vol. 16(17), pages 1-33, August.
    7. Suzanne, Elodie & Absi, Nabil & Borodin, Valeria, 2020. "Towards circular economy in production planning: Challenges and opportunities," European Journal of Operational Research, Elsevier, vol. 287(1), pages 168-190.
    8. Sifaleras, Angelo & Konstantaras, Ioannis & Mladenović, Nenad, 2015. "Variable neighborhood search for the economic lot sizing problem with product returns and recovery," International Journal of Production Economics, Elsevier, vol. 160(C), pages 133-143.
    9. Timo Hilger & Florian Sahling & Horst Tempelmeier, 2016. "Capacitated dynamic production and remanufacturing planning under demand and return uncertainty," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 38(4), pages 849-876, October.
    10. Attila, Öykü Naz & Agra, Agostinho & Akartunalı, Kerem & Arulselvan, Ashwin, 2021. "Robust formulations for economic lot-sizing problem with remanufacturing," European Journal of Operational Research, Elsevier, vol. 288(2), pages 496-510.
    11. Malolan Sundararaman & Mathirajan Muthu, 2020. "Component remanufacturing: a new prospective profitable business approach for the Indian automobile sector," OPSEARCH, Springer;Operational Research Society of India, vol. 57(4), pages 1244-1280, December.
    12. Shin, Hojung & Park, Soohoon & Lee, Euncheol & Benton, W.C., 2015. "A classification of the literature on the planning of substitutable products," European Journal of Operational Research, Elsevier, vol. 246(3), pages 686-699.
    13. Piñeyro, Pedro & Viera, Omar, 2014. "Note on “The economic lot-sizing problem with remanufacturing and one-way substitution”," International Journal of Production Economics, Elsevier, vol. 156(C), pages 167-168.
    14. Mokhtari, Hadi, 2018. "Economic order quantity for joint complementary and substitutable items," Mathematics and Computers in Simulation (MATCOM), Elsevier, vol. 154(C), pages 34-47.
    15. Liao, Gwo-Liang & Sheu, Shey-Huei, 2011. "Economic production quantity model for randomly failing production process with minimal repair and imperfect maintenance," International Journal of Production Economics, Elsevier, vol. 130(1), pages 118-124, March.
    16. Mahmutoğulları, Özlem & Yaman, Hande, 2023. "A Branch-and-Cut Algorithm for the Inventory Routing Problem with Product Substitution," Omega, Elsevier, vol. 115(C).

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Guan, Yongpei & Liu, Tieming, 2010. "Stochastic lot-sizing problem with inventory-bounds and constant order-capacities," European Journal of Operational Research, Elsevier, vol. 207(3), pages 1398-1409, December.
    2. Hark‐Chin Hwang & Wilco van den Heuvel, 2012. "Improved algorithms for a lot‐sizing problem with inventory bounds and backlogging," Naval Research Logistics (NRL), John Wiley & Sons, vol. 59(3‐4), pages 244-253, April.
    3. Brahimi, Nadjib & Absi, Nabil & Dauzère-Pérès, Stéphane & Nordli, Atle, 2017. "Single-item dynamic lot-sizing problems: An updated survey," European Journal of Operational Research, Elsevier, vol. 263(3), pages 838-863.
    4. Jans, R.F. & Degraeve, Z., 2005. "Modeling Industrial Lot Sizing Problems: A Review," ERIM Report Series Research in Management ERS-2005-049-LIS, Erasmus Research Institute of Management (ERIM), ERIM is the joint research institute of the Rotterdam School of Management, Erasmus University and the Erasmus School of Economics (ESE) at Erasmus University Rotterdam.
    5. Martel, Alain & Gascon, Andre, 1998. "Dynamic lot-sizing with price changes and price-dependent holding costs," European Journal of Operational Research, Elsevier, vol. 111(1), pages 114-128, November.
    6. Suzanne, Elodie & Absi, Nabil & Borodin, Valeria, 2020. "Towards circular economy in production planning: Challenges and opportunities," European Journal of Operational Research, Elsevier, vol. 287(1), pages 168-190.
    7. Hark-Chin Hwang & Hyun-Soo Ahn & Philip Kaminsky, 2013. "Basis Paths and a Polynomial Algorithm for the Multistage Production-Capacitated Lot-Sizing Problem," Operations Research, INFORMS, vol. 61(2), pages 469-482, April.
    8. Hwang, Hark-Chin & Kang, Jangha, 2020. "The two-level lot-sizing problem with outbound shipment," Omega, Elsevier, vol. 90(C).
    9. Zhang, Zhi-Hai & Jiang, Hai & Pan, Xunzhang, 2012. "A Lagrangian relaxation based approach for the capacitated lot sizing problem in closed-loop supply chain," International Journal of Production Economics, Elsevier, vol. 140(1), pages 249-255.
    10. Gutiérrez, J. & Sedeí±o-Noda, A. & Colebrook, M. & Sicilia, J., 2008. "An efficient approach for solving the lot-sizing problem with time-varying storage capacities," European Journal of Operational Research, Elsevier, vol. 189(3), pages 682-693, September.
    11. Sifaleras, Angelo & Konstantaras, Ioannis & Mladenović, Nenad, 2015. "Variable neighborhood search for the economic lot sizing problem with product returns and recovery," International Journal of Production Economics, Elsevier, vol. 160(C), pages 133-143.
    12. Mathijn Retel Helmrich & Raf Jans & Wilco van den Heuvel & Albert Wagelmans, 2014. "Economic lot-sizing with remanufacturing: complexity and efficient formulations," IISE Transactions, Taylor & Francis Journals, vol. 46(1), pages 67-86.
    13. van den Heuvel, W., 2004. "On the complexity of the economic lot-sizing problem with remanufacturing options," Econometric Institute Research Papers EI 2004-46, Erasmus University Rotterdam, Erasmus School of Economics (ESE), Econometric Institute.
    14. Hwang, Hark-Chin & Jaruphongsa, Wikrom, 2008. "Dynamic lot-sizing model for major and minor demands," European Journal of Operational Research, Elsevier, vol. 184(2), pages 711-724, January.
    15. Jian Yang & Boaz Golany & Gang Yu, 2005. "A concave‐cost production planning problem with remanufacturing options," Naval Research Logistics (NRL), John Wiley & Sons, vol. 52(5), pages 443-458, August.
    16. Hwang, H.C., 2009. "Economic Lot-Sizing Problem with Bounded Inventory and Lost-Sales," Econometric Institute Research Papers EI 2009-01, Erasmus University Rotterdam, Erasmus School of Economics (ESE), Econometric Institute.
    17. Andreas Goerler & Stefan Voß, 2016. "Dynamic lot-sizing with rework of defective items and minimum lot-size constraints," International Journal of Production Research, Taylor & Francis Journals, vol. 54(8), pages 2284-2297, April.
    18. Minjiao Zhang & Simge Küçükyavuz & Hande Yaman, 2012. "A Polyhedral Study of Multiechelon Lot Sizing with Intermediate Demands," Operations Research, INFORMS, vol. 60(4), pages 918-935, August.
    19. Eksioglu, Sandra Duni, 2009. "A primal-dual algorithm for the economic lot-sizing problem with multi-mode replenishment," European Journal of Operational Research, Elsevier, vol. 197(1), pages 93-101, August.
    20. Brahimi, Nadjib & Dauzere-Peres, Stephane & Najid, Najib M. & Nordli, Atle, 2006. "Single item lot sizing problems," European Journal of Operational Research, Elsevier, vol. 168(1), pages 1-16, January.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:proeco:v:124:y:2010:i:2:p:482-488. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/locate/ijpe .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.