Efficient priority rules for the resource-constrained project scheduling problem

Author

Listed:
  • Kolisch, Rainer

Abstract

We review the well-known RSM priority rule to solve the resource constrained project scheduling problem. A detailed analysis of this rule reveals that it is based on assumptions which do not hold in general and hence might lead to poor solutions. Consequently, an improved RSM priority rule is derived. Furthermore, two new priority rules are developed which extend the well-known precedence based minimum slack priority rule (MSLK) to a precedence and resource based slack priority rule, respectively. An experimental investigation on the basis of two instance-sets from the open literature shows that the new rules outperform all other priority rules which were proposed so far.

Suggested Citation

  • Kolisch, Rainer, 1994. "Efficient priority rules for the resource-constrained project scheduling problem," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 350, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
  • Handle: RePEc:zbw:cauman:350
    as

    Download full text from publisher

    File URL: https://www.econstor.eu/bitstream/10419/155422/1/manuskript_350.pdf
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Kolisch, Rainer, 1994. "Serial and parallel resource-constrained projekt scheduling methodes revisited: Theory and computation," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 344, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    2. A. Alan B. Pritsker & Lawrence J. Waiters & Philip M. Wolfe, 1969. "Multiproject Scheduling with Limited Resources: A Zero-One Programming Approach," Management Science, INFORMS, vol. 16(1), pages 93-108, September.
    3. Christofides, Nicos & Alvarez-Valdes, R. & Tamarit, J. M., 1987. "Project scheduling with resource constraints: A branch and bound approach," European Journal of Operational Research, Elsevier, vol. 29(3), pages 262-273, June.
    4. Edward W. Davis & James H. Patterson, 1975. "A Comparison of Heuristic and Optimum Solutions in Resource-Constrained Project Scheduling," Management Science, INFORMS, vol. 21(8), pages 944-955, April.
    5. Drexl, Andreas & Kolisch, Rainer, 1994. "Model-based assembly management in machine tool manufacturing," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 346, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    6. James H. Patterson & Walter D. Huber, 1974. "A Horizon-Varying, Zero-One Approach to Project Scheduling," Management Science, INFORMS, vol. 20(6), pages 990-998, February.
    7. Robert H. Storer & S. David Wu & Renzo Vaccari, 1992. "New Search Spaces for Sequencing Problems with Application to Job Shop Scheduling," Management Science, INFORMS, vol. 38(10), pages 1495-1509, October.
    8. Boctor, Fayer F., 1990. "Some efficient multi-heuristic procedures for resource-constrained project scheduling," European Journal of Operational Research, Elsevier, vol. 49(1), pages 3-13, November.
    9. Oguz, Osman & Bala, Hasan, 1994. "A comparative study of computational procedures for the resource constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 72(2), pages 406-416, January.
    10. Erik Demeulemeester & Willy Herroelen, 1992. "A Branch-and-Bound Procedure for the Multiple Resource-Constrained Project Scheduling Problem," Management Science, INFORMS, vol. 38(12), pages 1803-1818, December.
    11. Dale F. Cooper, 1976. "Heuristics for Scheduling Resource-Constrained Projects: An Experimental Investigation," Management Science, INFORMS, vol. 22(11), pages 1186-1194, July.
    12. Jerome D. Wiest, 1967. "A Heuristic Model for Scheduling Large Projects with Limited Resources," Management Science, INFORMS, vol. 13(6), pages 359-377, February.
    13. Edward H. Bowman, 1959. "The Schedule-Sequencing Problem," Operations Research, INFORMS, vol. 7(5), pages 621-624, October.
    14. Edward W. Davis & George E. Heidorn, 1971. "An Algorithm for Optimal Project Scheduling under Multiple Resource Constraints," Management Science, INFORMS, vol. 17(12), pages 803-816, August.
    15. Arne Thesen, 1976. "Heuristic Scheduling of Activities under Resource and Precedence Restrictions," Management Science, INFORMS, vol. 23(4), pages 412-422, December.
    16. F. Brian Talbot & James H. Patterson, 1978. "An Efficient Integer Programming Algorithm with Network Cuts for Solving Resource-Constrained Scheduling Problems," Management Science, INFORMS, vol. 24(11), pages 1163-1174, July.
    17. James H. Patterson, 1984. "A Comparison of Exact Approaches for Solving the Multiple Constrained Resource, Project Scheduling Problem," Management Science, INFORMS, vol. 30(7), pages 854-867, July.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Icmeli-Tukel, Oya & Rom, Walter O., 1997. "Ensuring quality in resource constrained project scheduling," European Journal of Operational Research, Elsevier, vol. 103(3), pages 483-496, December.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Kolisch, Rainer, 1994. "Serial and parallel resource-constrained projekt scheduling methodes revisited: Theory and computation," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 344, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    2. Kolisch, R. & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Omega, Elsevier, vol. 29(3), pages 249-272, June.
    3. Kolisch, Rainer, 1996. "Serial and parallel resource-constrained project scheduling methods revisited: Theory and computation," European Journal of Operational Research, Elsevier, vol. 90(2), pages 320-333, April.
    4. Aristide Mingozzi & Vittorio Maniezzo & Salvatore Ricciardelli & Lucio Bianco, 1998. "An Exact Algorithm for the Resource-Constrained Project Scheduling Problem Based on a New Mathematical Formulation," Management Science, INFORMS, vol. 44(5), pages 714-729, May.
    5. Schirmer, Andreas & Riesenberg, Sven, 1997. "Parameterized heuristics for project scheduling: Biased random sampling methods," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 456, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    6. Kolisch, Rainer & Sprecher, Arno & Drexl, Andreas, 1992. "Characterization and generation of a general class of resource-constrained project scheduling problems: Easy and hard instances," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 301, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    7. Brucker, Peter & Drexl, Andreas & Mohring, Rolf & Neumann, Klaus & Pesch, Erwin, 1999. "Resource-constrained project scheduling: Notation, classification, models, and methods," European Journal of Operational Research, Elsevier, vol. 112(1), pages 3-41, January.
    8. Kolisch, Rainer & Drexl, Andreas, 1994. "Hybrid biased random sampling for multiple resourse-constrained project scheduling problems," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 354, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    9. Jan Böttcher & Andreas Drexl & Rainer Kolisch & Frank Salewski, 1999. "Project Scheduling Under Partially Renewable Resource Constraints," Management Science, INFORMS, vol. 45(4), pages 543-559, April.
    10. Böttcher, Jan & Drexl, Andreas & Kolisch, Rainer & Salewski, Frank, 1996. "Project scheduling under partially renewable resource constraints," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 398, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    11. Salewski, Frank & Schirmer, Andreas & Drexl, Andreas, 1997. "Project scheduling under resource and mode identity constraints: Model, complexity, methods, and application," European Journal of Operational Research, Elsevier, vol. 102(1), pages 88-110, October.
    12. Rainer Kolisch & Andreas Drexl, 1996. "Adaptive search for solving hard project scheduling problems," Naval Research Logistics (NRL), John Wiley & Sons, vol. 43(1), pages 23-40, February.
    13. Simpson, Wendell P. & Patterson, James H., 1996. "A multiple-tree search procedure for the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 89(3), pages 525-542, March.
    14. Kolisch, Rainer & Hartmann, Sönke, 1998. "Heuristic algorithms for solving the resource-constrained project scheduling problem: Classification and computational analysis," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 469, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    15. Salewski, Frank & Schirmer, Andreas & Drexl, Andreas, 1996. "Project Scheduling under Resource and Mode Identity Constraints. Part I: Model, Complexity Status, and Methods," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 387, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    16. Ahn, Taeho & Erenguc, S. Selcuk, 1998. "The resource constrained project scheduling problem with multiple crashable modes: A heuristic procedure," European Journal of Operational Research, Elsevier, vol. 107(2), pages 250-259, June.
    17. Kolisch, Rainer & Hartmann, Sonke, 2006. "Experimental investigation of heuristics for resource-constrained project scheduling: An update," European Journal of Operational Research, Elsevier, vol. 174(1), pages 23-37, October.
    18. Yang, Kum-Khiong, 1998. "A comparison of dispatching rules for executing a resource-constrained project with estimated activity durations," Omega, Elsevier, vol. 26(6), pages 729-738, December.
    19. Klein, Robert & Scholl, Armin, 1999. "Computing lower bounds by destructive improvement: An application to resource-constrained project scheduling," European Journal of Operational Research, Elsevier, vol. 112(2), pages 322-346, January.
    20. Kolisch, Rainer & Sprecher, Arno, 1997. "PSPLIB - A project scheduling problem library : OR Software - ORSEP Operations Research Software Exchange Program," European Journal of Operational Research, Elsevier, vol. 96(1), pages 205-216, January.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:zbw:cauman:350. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: ZBW - Leibniz Information Centre for Economics (email available below). General contact details of provider: https://edirc.repec.org/data/ibkiede.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.