A finite capacity production scheduling procedure for a belgian steel company
Author
Abstract
Suggested Citation
Download full text from publisher
Other versions of this item:
- D. Debels & M. Vanhoucke, 2006. "A finite capacity production scheduling procedure for a Belgian steel company," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 06/418, Ghent University, Faculty of Economics and Business Administration.
References listed on IDEAS
- Peter J. Billington & John O. McClain & L. Joseph Thomas, 1983. "Mathematical Programming Approaches to Capacity-Constrained MRP Systems: Review, Formulation and Problem Reduction," Management Science, INFORMS, vol. 29(10), pages 1126-1141, October.
- Rom, Walter O. & Tukel, Oya Icmeli & Muscatello, Joseph R., 2002. "MRP in a job shop environment using a resource constrained project scheduling model," Omega, Elsevier, vol. 30(4), pages 275-286, August.
- Segerstedt, Anders, 1996. "A capacity-constrained multi-level inventory and production control problem," International Journal of Production Economics, Elsevier, vol. 45(1-3), pages 449-461, August.
- Peter J. Kolesar, 1967. "A Branch and Bound Algorithm for the Knapsack Problem," Management Science, INFORMS, vol. 13(9), pages 723-735, May.
- Tang, Lixin & Liu, Jiyin & Rong, Aiying & Yang, Zihou, 2001. "A review of planning and scheduling systems and methods for integrated steel production," European Journal of Operational Research, Elsevier, vol. 133(1), pages 1-20, August.
- Gabriel R. Bitran & Arnoldo C. Hax, 1981. "Disaggregation and Resource Allocation Using Convex Knapsack Problems with Bounded Variables," Management Science, INFORMS, vol. 27(4), pages 431-441, April.
Most related items
These are the items that most often cite the same works as this one and are cited by the same works as this one.- Rom, Walter O. & Tukel, Oya Icmeli & Muscatello, Joseph R., 2002. "MRP in a job shop environment using a resource constrained project scheduling model," Omega, Elsevier, vol. 30(4), pages 275-286, August.
- Tao Wu & Leyuan Shi & Joseph Geunes & Kerem Akartunalı, 2012. "On the equivalence of strong formulations for capacitated multi-level lot sizing problems with setup times," Journal of Global Optimization, Springer, vol. 53(4), pages 615-639, August.
- Vo[ss], Stefan & Witt, Andreas, 2007. "Hybrid flow shop scheduling as a multi-mode multi-project scheduling problem with batching requirements: A real-world application," International Journal of Production Economics, Elsevier, vol. 105(2), pages 445-458, February.
- J. Drechsel & A. Kimms, 2010. "The subcoalition-perfect core of cooperative games," Annals of Operations Research, Springer, vol. 181(1), pages 591-601, December.
- Walter, Rico & Boysen, Nils & Scholl, Armin, 2013. "The discrete forward–reserve problem – Allocating space, selecting products, and area sizing in forward order picking," European Journal of Operational Research, Elsevier, vol. 229(3), pages 585-594.
- Phillip O. Kriett & Sebastian Eirich & Martin Grunow, 2017. "Cycle time-oriented mid-term production planning for semiconductor wafer fabrication," International Journal of Production Research, Taylor & Francis Journals, vol. 55(16), pages 4662-4679, August.
- Xu, Jun & Wang, Jun-Qiang & Liu, Zhixin, 2022. "Parallel batch scheduling: Impact of increasing machine capacity," Omega, Elsevier, vol. 108(C).
- Xiaoyu Yu & Jingyi Qian & Yajing Zhang & Min Kong, 2023. "Supply Chain Scheduling Method for the Coordination of Agile Production and Port Delivery Operation," Mathematics, MDPI, vol. 11(15), pages 1-24, July.
- Milne, R. John & Mahapatra, Santosh & Wang, Chi-Tai, 2015. "Optimizing planned lead times for enhancing performance of MRP systems," International Journal of Production Economics, Elsevier, vol. 167(C), pages 220-231.
- G. Rius-Sorolla & J. Maheut & S. Estellés-Miguel & J. P. García-Sabater, 2021. "Operations planning test bed under rolling horizons, multiproduct, multiechelon, multiprocess for capacitated production planning modelling with strokes," Central European Journal of Operations Research, Springer;Slovak Society for Operations Research;Hungarian Operational Research Society;Czech Society for Operations Research;Österr. Gesellschaft für Operations Research (ÖGOR);Slovenian Society Informatika - Section for Operational Research;Croatian Operational Research Society, vol. 29(4), pages 1289-1315, December.
- Singer, Marcos & Donoso, Patricio, 2008. "Empirical validation of an activity-based optimization system," International Journal of Production Economics, Elsevier, vol. 113(1), pages 335-345, May.
- Muralidharan S. Kodialam & Hanan Luss, 1998. "Algorithms for Separable Nonlinear Resource Allocation Problems," Operations Research, INFORMS, vol. 46(2), pages 272-284, April.
- Almeder, Christian & Klabjan, Diego & Traxler, Renate & Almada-Lobo, Bernardo, 2015. "Lead time considerations for the multi-level capacitated lot-sizing problem," European Journal of Operational Research, Elsevier, vol. 241(3), pages 727-738.
- Bretthauer, Kurt M. & Ross, Anthony & Shetty, Bala, 1999. "Nonlinear integer programming for optimal allocation in stratified sampling," European Journal of Operational Research, Elsevier, vol. 116(3), pages 667-680, August.
- Torres, Nelson & Greivel, Gus & Betz, Joshua & Moreno, Eduardo & Newman, Alexandra & Thomas, Brian, 2024. "Optimizing steel coil production schedules under continuous casting and hot rolling," European Journal of Operational Research, Elsevier, vol. 314(2), pages 496-508.
- Zhang, Ruijun & Lu, Jie & Zhang, Guangquan, 2011. "A knowledge-based multi-role decision support system for ore blending cost optimization of blast furnaces," European Journal of Operational Research, Elsevier, vol. 215(1), pages 194-203, November.
- Hartmut Stadtler & Malte Meistering, 2019. "Model formulations for the capacitated lot-sizing problem with service-level constraints," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 41(4), pages 1025-1056, December.
- Patriksson, Michael, 2008. "A survey on the continuous nonlinear resource allocation problem," European Journal of Operational Research, Elsevier, vol. 185(1), pages 1-46, February.
- Mohebbi, E. & Choobineh, F. & Pattanayak, A., 2007. "Capacity-driven vs. demand-driven material procurement systems," International Journal of Production Economics, Elsevier, vol. 107(2), pages 451-466, June.
- Ferretti, Ivan & Zanoni, Simone & Zavanella, Lucio, 2006. "Production-inventory scheduling using Ant System metaheuristic," International Journal of Production Economics, Elsevier, vol. 104(2), pages 317-326, December.
More about this item
Keywords
Master production scheduling; manufacturing planning and control; scheduling/sequencing.;All these keywords.
NEP fields
This paper has been announced in the following NEP Reports:- NEP-CMP-2007-02-17 (Computational Economics)
Statistics
Access and download statisticsCorrections
All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:vlg:vlgwps:2006-41. See general information about how to correct material in RePEc.
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.
For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Isabelle Vandenbroere (email available below). General contact details of provider: https://edirc.repec.org/data/vlgmsbe.html .
Please note that corrections may take a couple of weeks to filter through the various RePEc services.