Effective expediting to improve project due date and cost performance through buffer management

Author

Listed:
  • Xuejun Hu
  • Nanfang Cui
  • Erik Demeulemeester

Abstract

The rapidly changing marketplace together with the increasing complexity of contemporary projects makes it more likely that project activities will have uncertain durations, incurring a generally low probability of on-time delivery. Thus, project control that aims to track the project performance and to expedite relevant activities when necessary has become the main aspect within the scope of project management in order to ensure a successful scheduling outcome. The Critical Chain Scheduling and Buffer Management (CC/BM) has shown to provide a popular approach to build robust project schedules and to offer a valuable control tool for coping with schedule variability. However, the most current buffer management (BM) practice faces a problem of neglecting the cost information when taking expediting actions. In view of this defect, we introduce a new control procedure on the basis of CC/BM that evaluates the probability of successful project completion relative to the cost of crashing and that determines when to expedite which activities in a cost-effective manner. Results of an experimental application of the proposed method present its relative dominance over the currently widely adopted BM approach with respect to project time and cost performance.

Suggested Citation

  • Xuejun Hu & Nanfang Cui & Erik Demeulemeester, 2015. "Effective expediting to improve project due date and cost performance through buffer management," International Journal of Production Research, Taylor & Francis Journals, vol. 53(5), pages 1460-1471, March.
  • Handle: RePEc:taf:tprsxx:v:53:y:2015:i:5:p:1460-1471
    DOI: 10.1080/00207543.2014.948972
    as

    Download full text from publisher

    File URL: http://hdl.handle.net/10.1080/00207543.2014.948972
    Download Restriction: Access to full text is restricted to subscribers.

    File URL: https://libkey.io/10.1080/00207543.2014.948972?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Chen, Bo & Hall, Nicholas G., 2021. "Incentive schemes for resolving Parkinson’s Law in project management," European Journal of Operational Research, Elsevier, vol. 288(2), pages 666-681.
    2. Cui, Nanfang & Demeulemeester, Erik & Bie, Li, 2016. "Incorporation of activity sensitivity measures into buffer management to manage project schedule riskAuthor-Name: Hu, Xuejun," European Journal of Operational Research, Elsevier, vol. 249(2), pages 717-727.
    3. Yangyang Liang & Nanfang Cui & Tian Wang & Erik Demeulemeester, 2019. "Robust resource-constrained max-NPV project scheduling with stochastic activity duration," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 41(1), pages 219-254, March.
    4. Zhai, Yue & Zhong, Ray Y. & Huang, George Q., 2018. "Buffer space hedging and coordination in prefabricated construction supply chain management," International Journal of Production Economics, Elsevier, vol. 200(C), pages 192-206.
    5. She, Bingling & Chen, Bo & Hall, Nicholas G., 2021. "Buffer sizing in critical chain project management by network decomposition," Omega, Elsevier, vol. 102(C).
    6. Xuejun Hu & Erik Demeulemeester & Nanfang Cui & Jianjiang Wang & Wendi Tian, 2017. "Improved critical chain buffer management framework considering resource costs and schedule stability," Flexible Services and Manufacturing Journal, Springer, vol. 29(2), pages 159-183, June.
    7. Wenhui Zhao & Nicholas G. Hall & Zhixin Liu, 2020. "Project Evaluation and Selection with Task Failures," Production and Operations Management, Production and Operations Management Society, vol. 29(2), pages 428-446, February.
    8. Antonio J. Conejo & Nicholas G. Hall & Daniel Zhuoyu Long & Runhao Zhang, 2021. "Robust Capacity Planning for Project Management," INFORMS Journal on Computing, INFORMS, vol. 33(4), pages 1533-1550, October.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:taf:tprsxx:v:53:y:2015:i:5:p:1460-1471. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Longhurst (email available below). General contact details of provider: http://www.tandfonline.com/TPRS20 .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.