The accuracy of risk-based cost estimation for water infrastructure projects: preliminary evidence from Australian projects

Author

Listed:
  • Li Liu
  • Zigrid Napier

Abstract

Infrastructure projects are still being plagued by cost overruns, delays and revenue shortfalls despite decades of practice and research. Risk-based estimating (RBE) is growing in popularity and has the potential to overcome the two main cost overrun factors—optimistic bias and strategic misrepresentation. Yet, little is known about the accuracy of RBE and its performance drivers. A comparison of water projects using RBE with a sample of construction projects using the conventional estimating approach shows that the projects estimated using RBE have better estimation accuracy than those estimated using more conventional approaches. In addition, the projects using RBE appear more likely to be under-budget while the ones using the conventional approach appear more likely to be over-budget. Further, through interviews and observations of the RBE process, three main performance drivers for the RBE method were identified to include outside view/collective experience, attention focusing and probabilistic, bottom-up modelling.

Suggested Citation

  • Li Liu & Zigrid Napier, 2010. "The accuracy of risk-based cost estimation for water infrastructure projects: preliminary evidence from Australian projects," Construction Management and Economics, Taylor & Francis Journals, vol. 28(1), pages 89-100.
  • Handle: RePEc:taf:conmgt:v:28:y:2010:i:1:p:89-100
    DOI: 10.1080/01446190903431525
    as

    Download full text from publisher

    File URL: http://www.tandfonline.com/doi/abs/10.1080/01446190903431525
    Download Restriction: Access to full text is restricted to subscribers.

    File URL: https://libkey.io/10.1080/01446190903431525?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Flyvbjerg, Bent & Bester, Dirk W., 2021. "The Cost-Benefit Fallacy: Why Cost-Benefit Analysis Is Broken and How to Fix It," Journal of Benefit-Cost Analysis, Cambridge University Press, vol. 12(3), pages 395-419, October.
    2. Bent Flyvbjerg & Chi-keung Hon & Wing Huen Fok, 2017. "Reference Class Forecasting for Hong Kong's Major Roadworks Projects," Papers 1710.09419, arXiv.org.
    3. Flyvbjerg, Bent & Ansar, Atif & Budzier, Alexander & Buhl, Søren & Cantarelli, Chantal & Garbuio, Massimo & Glenting, Carsten & Holm, Mette Skamris & Lovallo, Dan & Lunn, Daniel & Molin, Eric & Rønnes, 2018. "Five things you should know about cost overrun," Transportation Research Part A: Policy and Practice, Elsevier, vol. 118(C), pages 174-190.
    4. Love, Peter E.D. & Sing, Michael C.P. & Ika, Lavagnon A. & Newton, Sidney, 2019. "The cost performance of transportation projects: The fallacy of the Planning Fallacy account," Transportation Research Part A: Policy and Practice, Elsevier, vol. 122(C), pages 1-20.
    5. Love, Peter E.D. & Ahiaga-Dagbui, Dominic D., 2018. "Debunking fake news in a post-truth era: The plausible untruths of cost underestimation in transport infrastructure projects," Transportation Research Part A: Policy and Practice, Elsevier, vol. 113(C), pages 357-368.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:taf:conmgt:v:28:y:2010:i:1:p:89-100. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Longhurst (email available below). General contact details of provider: http://www.tandfonline.com/RCME20 .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.