Disorder considerations in resource-constrained scheduling

Author

Listed:
  • Symeon Christodoulou
  • Georgios Ellinas
  • Pooyan Aslani

Abstract

A method is presented for allocating resources to construction activities and for scheduling construction projects under resource constraints by considering the effects that such resource limitations may have on the tendency of the activities (and the project in general) to fall into disarray and behind schedule. Resource-constrained scheduling problems (RCSP) are very common in real-life construction projects and because of their nature their numerical solution is computationally intensive. The method utilizes a measure of each activity's perceived level of disorder stemming from resource limitations. The proposed technique aims to optimize the number of resources assigned to the activities and to schedule the project so as to minimize the overall project's tendency to fall into disorder. The entropy-like metric used in the scheduling optimization is related to the ratio of required over-assigned resource units per activity, and its utilization allows a planner to take into consideration project disorder when planning a project. A case study and its mathematical framework help demonstrate the 'duration vs. disorder' trade-off analysis that planners should perform when considering possible activity resource assignments and the feasibility of these assignments in terms of induced disorder. The entropy optimization method proves to be a powerful project-planning metric.

Suggested Citation

  • Symeon Christodoulou & Georgios Ellinas & Pooyan Aslani, 2009. "Disorder considerations in resource-constrained scheduling," Construction Management and Economics, Taylor & Francis Journals, vol. 27(3), pages 229-240.
  • Handle: RePEc:taf:conmgt:v:27:y:2009:i:3:p:229-240
    DOI: 10.1080/01446190802635416
    as

    Download full text from publisher

    File URL: http://www.tandfonline.com/doi/abs/10.1080/01446190802635416
    Download Restriction: Access to full text is restricted to subscribers.

    File URL: https://libkey.io/10.1080/01446190802635416?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Liu Shu-Shun & Kuo-Chuan Shih, 2009. "A framework of critical resource chain for project schedule analysis," Construction Management and Economics, Taylor & Francis Journals, vol. 27(9), pages 857-869.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:taf:conmgt:v:27:y:2009:i:3:p:229-240. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Longhurst (email available below). General contact details of provider: http://www.tandfonline.com/RCME20 .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.